* Type B Past Week Summary * Fabian prepared a work space in the ATC cleanroom and moved in nearly all the parts for the dummy BS, RM, IM and IRM. * Fabian finally got perfect agreement between the Mathematica and Matlab models of the BS. (The wire thicknesses had in µm instead of mm, leading to some modes off by 1E3.) * Hirata-san remeasured the BF for the BS. He noted that the cap went on and came off easily (unlike some other filters). * Hirata-san worked on final details of the Mirapro order for the assembly frame. * Hirata-san and Takahashi-san washed a large batch of parts. * Tatsumi-san will glue flags, sapphire primary prisms and metal secondary prisms to the dummy BS some time in the week of 6/8. Fabian and possibly Mark and/or Hirata-san will travel to KEK to help and observe. * Mark worked more on [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235|E1504235 BS Assembly Procedure]] ([[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|Draft on OneDrive]]) |
=== Type B (Mark) === ==== Past week report ==== At Kamioka (Mark, Fabian, Enzo, Perry, Hirata-san): * Craned in the PI. * Assembled the thrust bearing holder that receives the PI-SF rod. (It originally had a burr that prevented the bearing from seating properly, and so required filing and re-cleaning.) * Hooked the SF and lowered the jacks under the SF to suspend the SF/... section. * The top filter rose when unlocked, and required about 1.8 kg to send it back down. Therefore we may be OK - the top filter seems to have about 8 kg more capacity than as measured by G&M. The hex cable clamp (≈0.25 kg) and the cables between the PI and SF still have to be added, but we can get an extra 3 kg by removing one of the three Cu damper segments (and rearranging the other two). * Built and installed three LBB blade units. * Kept debugging the SF LVDT. We repaired several broken wires, but it's still not behaving correctly. ==== Plan for coming weeks ==== For more detail, see [[KAGRA/Subgroups/VIS/TypeB/ToDo]]. Week of 5/1: * No activity (Golden Week). Week of 5/8: * Work from Tuesday. * Remove PI temporarily. * Add magnets to upper SF damper ring. * Reinstall PI with damper ring. * Reinstall PI-SF rod, this time with hex cable clamp. * Install PI yaw stepper. * Wire up PI yaw and vertical steppers. * Route cables from SF to PI (may involve removing part of Cu damper). |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Past week report
At Kamioka (Mark, Fabian, Enzo, Perry, Hirata-san):
- Craned in the PI.
- Assembled the thrust bearing holder that receives the PI-SF rod. (It originally had a burr that prevented the bearing from seating properly, and so required filing and re-cleaning.)
- Hooked the SF and lowered the jacks under the SF to suspend the SF/... section.
The top filter rose when unlocked, and required about 1.8 kg to send it back down. Therefore we may be OK - the top filter seems to have about 8 kg more capacity than as measured by G&M. The hex cable clamp (≈0.25 kg) and the cables between the PI and SF still have to be added, but we can get an extra 3 kg by removing one of the three Cu damper segments (and rearranging the other two).
- Built and installed three LBB blade units.
- Kept debugging the SF LVDT. We repaired several broken wires, but it's still not behaving correctly.
Plan for coming weeks
For more detail, see KAGRA/Subgroups/VIS/TypeB/ToDo.
Week of 5/1:
- No activity (Golden Week).
Week of 5/8:
- Work from Tuesday.
- Remove PI temporarily.
- Add magnets to upper SF damper ring.
- Reinstall PI with damper ring.
- Reinstall PI-SF rod, this time with hex cable clamp.
- Install PI yaw stepper.
- Wire up PI yaw and vertical steppers.
- Route cables from SF to PI (may involve removing part of Cu damper).