Differences between revisions 18 and 141 (spanning 123 versions)
Revision 18 as of 2016-05-26 15:26:29
Size: 1192
Editor: MarkBarton
Comment:
Revision 141 as of 2017-05-12 13:38:40
Size: 3153
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 5: Line 5:
 * Type B Past Week Summary
  * Fabian prepared a work space in the ATC cleanroom and moved in nearly all the parts for the dummy BS, RM, IM and IRM.
  * Fabian finally got perfect agreement between the Mathematica and Matlab models of the BS. (The wire thicknesses had in µm instead of mm, leading to some modes off by 1E3.)
  * Hirata-san remeasured the BF for the BS. He noted that the cap went on and came off easily (unlike some other filters).
  * Hirata-san worked on final details of the Mirapro order for the assembly frame.
  * Hirata-san and Takahashi-san washed a large batch of parts.
  * Tatsumi-san will glue flags, sapphire primary prisms and metal secondary prisms to the dummy BS some time in the week of 6/8. Fabian and possibly Mark and/or Hirata-san will travel to KEK to help and observe.
  * Mark worked more on [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235|E1504235 BS Assembly Procedure]] ([[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|Draft on OneDrive]])
=== Type B (Mark) ===
==== Past week report ====
At Kamioka (Mark, Fabian, Enzo, Perry, Hirata-san):

 * We counted the used/broken/unused/need cables for Type B.
 * Hirata-san and Mark installed blades in three LBB blade units.
 * Hirata-san checked the LBB blade units to see how badly the blade tips were misaligned. The bases will need to be moved towards the clamp end by 21 mm. It is probably not feasible to turn the screw holes into slots, so an adapter part will need to be designed.
 * We checked that the new in-vacuum geophone cables that Takahashi-san had got for us were the proper new-style ones. (Thus we will need in-air descrambler cables.)
 * Shoda-san sent Enzo a document by Joris on the tuning of the LVDTs, so he stated working through it. He also researched the specifications of all the coils (PI and SF as well as BF.)
 * We found the damper magnets and the template for placing the magnets on the ring for the SF.
 * Hirata-san installed and wired up the PI yaw stepper. The vertical stepper still needs wiring, and the horizontal stepper wiring needs to be made vacuum-compatible.
 * We installed safety bars on the ±X side of the assembly frame about 3 m off the floor, so they are at waist height for a person standing on one of the tall ladders. The one on the +X side will be very good for safety where it is, but the one on the -X side will need re-doing: it is too close and not very securely attached because of interference from vacuum pump cabling.
 * We unlocked the inverted pendulum and experimented with adding weight. It was still stable with 4 layers of arc weights.
 * We also experimented with getting both the IP centered and the security structure vertical (so that the suspension hang centrally within it). We managed to get it all right with a combination of leveling the PI with the jacks and moving the IP with the fishing rods.
 * Adjusting the verticality of the SS had left the bottom of it off-center in the assembly frame, so we picked the entire system up with the crane and moved it in +Y and -X a few mm to re-center it.
 * We started to remove the PI so we could do various adjustments (check the SF LVDT, reconfigure the Cu damper, add the hex cable clamp on the rod and hang the magnet disk for the SF damper) but gave up when the PI-SF jammed in the SF.


==== Plan for coming weeks ====
For more detail, see [[KAGRA/Subgroups/VIS/TypeB/ToDo]].

Week of 5/15:
 * Enzo from Tuesday 5/16 (driving test), rest of team from Monday.
 * Fix PI-SF rod jamming.
 * Remove PI and SF cap.
 * Continue debugging SF LVDT.
 * Reconfigure Cu damper ring on SF.
 * Add magnets to upper SF damper ring.
 * Add cable clamps on the PI (a few places are inaccessible when the PI is on the assembly frame).
 * Reinstall PI, this time with rods and damper ring.
 * Reinstall PI-SF rod, this time with hex cable clamp.
 * Prepare for PR2 bellows removal on 5/15 (move table with tools).
 * Cable/test PI horizontal LVDTs and steppers.
 * Install/cable/test geophones.
 

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Mark, Fabian, Enzo, Perry, Hirata-san):

  • We counted the used/broken/unused/need cables for Type B.
  • Hirata-san and Mark installed blades in three LBB blade units.
  • Hirata-san checked the LBB blade units to see how badly the blade tips were misaligned. The bases will need to be moved towards the clamp end by 21 mm. It is probably not feasible to turn the screw holes into slots, so an adapter part will need to be designed.
  • We checked that the new in-vacuum geophone cables that Takahashi-san had got for us were the proper new-style ones. (Thus we will need in-air descrambler cables.)
  • Shoda-san sent Enzo a document by Joris on the tuning of the LVDTs, so he stated working through it. He also researched the specifications of all the coils (PI and SF as well as BF.)
  • We found the damper magnets and the template for placing the magnets on the ring for the SF.
  • Hirata-san installed and wired up the PI yaw stepper. The vertical stepper still needs wiring, and the horizontal stepper wiring needs to be made vacuum-compatible.
  • We installed safety bars on the ±X side of the assembly frame about 3 m off the floor, so they are at waist height for a person standing on one of the tall ladders. The one on the +X side will be very good for safety where it is, but the one on the -X side will need re-doing: it is too close and not very securely attached because of interference from vacuum pump cabling.
  • We unlocked the inverted pendulum and experimented with adding weight. It was still stable with 4 layers of arc weights.
  • We also experimented with getting both the IP centered and the security structure vertical (so that the suspension hang centrally within it). We managed to get it all right with a combination of leveling the PI with the jacks and moving the IP with the fishing rods.
  • Adjusting the verticality of the SS had left the bottom of it off-center in the assembly frame, so we picked the entire system up with the crane and moved it in +Y and -X a few mm to re-center it.
  • We started to remove the PI so we could do various adjustments (check the SF LVDT, reconfigure the Cu damper, add the hex cable clamp on the rod and hang the magnet disk for the SF damper) but gave up when the PI-SF jammed in the SF.

Plan for coming weeks

For more detail, see KAGRA/Subgroups/VIS/TypeB/ToDo.

Week of 5/15:

  • Enzo from Tuesday 5/16 (driving test), rest of team from Monday.
  • Fix PI-SF rod jamming.
  • Remove PI and SF cap.
  • Continue debugging SF LVDT.
  • Reconfigure Cu damper ring on SF.
  • Add magnets to upper SF damper ring.
  • Add cable clamps on the PI (a few places are inaccessible when the PI is on the assembly frame).
  • Reinstall PI, this time with rods and damper ring.
  • Reinstall PI-SF rod, this time with hex cable clamp.
  • Prepare for PR2 bellows removal on 5/15 (move table with tools).
  • Cable/test PI horizontal LVDTs and steppers.
  • Install/cable/test geophones.

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)