Line 5: Line 5:
 * Type B Past Week Summary
  * Fabian prepared a work space in the ATC cleanroom and moved in nearly all the parts for the dummy BS, RM, IM and IRM.
  * Fabian finally got perfect agreement between the Mathematica and Matlab models of the BS. (The wire thicknesses had in µm instead of mm, leading to some modes off by 1E3.)
  * Hirata-san remeasured the BF for the BS. He noted that the cap went on and came off easily (unlike some other filters).
  * Hirata-san worked on final details of the Mirapro order for the assembly frame.
  * Hirata-san and Takahashi-san washed a large batch of parts.
  * Tatsumi-san will glue flags, sapphire primary prisms and metal secondary prisms to the dummy BS some time in the week of 6/8. Fabian and possibly Mark and/or Hirata-san will travel to KEK to help and observe.
  * Mark worked more on [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235|E1504235 BS Assembly Procedure]] ([[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|Draft on OneDrive]])
=== Type B (Mark) ===
==== Past week report ====

 * Mark analyzed the QPD data from Friday 12/1 and derived matrices to diagonalize the QPD, and calibrate output in µrad. In the process an error in the IM OSEM diagonalization was discovered: the P and Y gains were low by a factor 2.
 * Mark re-zeroed the QPD after noting the micrometer readings so we can do TFs over the weekend.
 * We prepared for the SR2 gluing:
  * We aligned the SR2 in the box with the wedge on the correct side.
  * We checked that the remachined BS prism holders fit on the PR2 mirror box.
  * We checked that with Tatsumi-san's support ring, the prisms would go on at the right height.
  * We checked the new magnet jigs.
 * We glued ferromagnetic disks in a large number of IM flag tips and flag bases, and in the SR magnet jigs.
 * We also glued SR magnets in the magnet bases.

==== Plan for week of 12/11
 * Mark, Fabian, Enzo, Kozu-kun (Mon-Thu only), Hirata-san, Shoda-san at Kamioka.
 * Mirror gluing.
 * IM assembly and pico test.
 * Assembly frame alignment and optical table centering.
 * Move trolley system from SR3.
 * OL setup.

==== Plan for week of 12/18 ====
 * Shoda-san vacation
 * Mark, Fabian, Enzo, Kozu-kun at Kamioka Mon-Wed.

==== Vacation Info ====
 * Mark 12/22-1/3
 * Enzo, 12/21-12/27 (but ''not'' 12/28)
 * Fabian 12/22-1/5
 * Hirata-san 12/21-22 (conference)
 * Shoda-san 12/18-21
  

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

  • Mark analyzed the QPD data from Friday 12/1 and derived matrices to diagonalize the QPD, and calibrate output in µrad. In the process an error in the IM OSEM diagonalization was discovered: the P and Y gains were low by a factor 2.
  • Mark re-zeroed the QPD after noting the micrometer readings so we can do TFs over the weekend.
  • We prepared for the SR2 gluing:
    • We aligned the SR2 in the box with the wedge on the correct side.
    • We checked that the remachined BS prism holders fit on the PR2 mirror box.
    • We checked that with Tatsumi-san's support ring, the prisms would go on at the right height.
    • We checked the new magnet jigs.
  • We glued ferromagnetic disks in a large number of IM flag tips and flag bases, and in the SR magnet jigs.
  • We also glued SR magnets in the magnet bases.

==== Plan for week of 12/11

  • Mark, Fabian, Enzo, Kozu-kun (Mon-Thu only), Hirata-san, Shoda-san at Kamioka.
  • Mirror gluing.
  • IM assembly and pico test.
  • Assembly frame alignment and optical table centering.
  • Move trolley system from SR3.
  • OL setup.

Plan for week of 12/18

  • Shoda-san vacation
  • Mark, Fabian, Enzo, Kozu-kun at Kamioka Mon-Wed.

Vacation Info

  • Mark 12/22-1/3
  • Enzo, 12/21-12/27 (but not 12/28)

  • Fabian 12/22-1/5
  • Hirata-san 12/21-22 (conference)
  • Shoda-san 12/18-21