* Type B Past Week Summary * Fabian prepared a work space in the ATC cleanroom and moved in nearly all the parts for the dummy BS, RM, IM and IRM. * Fabian finally got perfect agreement between the Mathematica and Matlab models of the BS. (The wire thicknesses had in µm instead of mm, leading to some modes off by 1E3.) * Hirata-san remeasured the BF for the BS. He noted that the cap went on and came off easily (unlike some other filters). * Hirata-san worked on final details of the Mirapro order for the assembly frame. * Hirata-san and Takahashi-san washed a large batch of parts. * Tatsumi-san will glue flags, sapphire primary prisms and metal secondary prisms to the dummy BS some time in the week of 6/8. Fabian and possibly Mark and/or Hirata-san will travel to KEK to help and observe. * Mark worked more on [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235|E1504235 BS Assembly Procedure]] ([[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|Draft on OneDrive]]) |
=== Type B (Mark) === ==== Report for week of 3/26 ==== BFs: * BF No. 1: * Fujii-san finished tuning. Optimal load: 52.15[kg]. Resonance frequency: 0.37[Hz]. Optimal height: 64.7[mm]. * We wired the LVDT, Picomotor and Steppermotor. * We measured the keystone tilt at different points and the diferences are within 0.1[mm] * We added cable clamps to the base. * BF No.7: * Fujii-san replaced the blades corresponding to the BS and for the SR type blades. * The yoke position was corrected. * The fishing rod was assembled. * Compression tuning is ongoing. SFs: * Hirata-san and Tanioka-san set up the frame to check the SFs. * SF (B2-5): * Hirata-san, Fujii-san and Tanioka-san checked the optimal load with and without cap. The optimal load changes about 250[g]. * We measured the keystone tilt at different points, and the diferences are within 0.1[mm] * SF (B2-6): * Hirata-san, Fujii-san and Tanioka-san checked the optimal load with and without cap (On going?). * We measured the keystone tilt at different points, and the diferences are within 0.3[mm] SR3/SRM: * Kozu-kun and Enzo finished the SR3 in-air cabling. * Enzo prepared the SR3 and SRM rack in parallel (On going). BS: * Kozu-kun and Enzo helped Enomoto-san troubleshooting the BS Oplev issue (On going). * We finished the SR3 in-air cabling. ==== Plan for week of 4/2 ==== * Mark at Mitaka Mon, Kamioka from Tue. * Shoda-san at Mitaka * Others at Kamioka * -- * Finish BFs tasks (cabling +calibration) * Finish SFs tasks (cabling +calibration) * Add cable clamps to bases. * Add cable clamps and Cu segments to caps (only if they fit well). * Build 2xIM, 2xIRM * Glue SR3 mirror? ==== Plan for week of 4/9 ==== * Shoda-san at Mitaka * Others at Kamioka * -- * Finish IMs and IRMs * Build 1xRM ==== Plan for week of 4/16 ==== * Start SR3 Hang? ==== Plan for week of 4/23 ==== * F0 blade prototype test ==== Plan for week of 4/30 ==== * Golden Week! ==== To-Do Lists, Schedule ==== * [[KAGRA/Subgroups/VIS/TypeB/March2018]] * [[KAGRA/Subgroups/VIS/TypeB/April2018]] * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]] * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]] * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]] ==== Vacation Info ==== * Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun) * Fabian vacation, 3/26-4/27 (then gone). |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 3/26
BFs:
- BF No. 1:
- Fujii-san finished tuning. Optimal load: 52.15[kg]. Resonance frequency: 0.37[Hz]. Optimal height: 64.7[mm].
- We wired the LVDT, Picomotor and Steppermotor.
- We measured the keystone tilt at different points and the diferences are within 0.1[mm]
- We added cable clamps to the base.
- BF No.7:
- Fujii-san replaced the blades corresponding to the BS and for the SR type blades.
- The yoke position was corrected.
- The fishing rod was assembled.
- Compression tuning is ongoing.
SFs:
- Hirata-san and Tanioka-san set up the frame to check the SFs.
- SF (B2-5):
- Hirata-san, Fujii-san and Tanioka-san checked the optimal load with and without cap. The optimal load changes about 250[g].
- We measured the keystone tilt at different points, and the diferences are within 0.1[mm]
- SF (B2-6):
- Hirata-san, Fujii-san and Tanioka-san checked the optimal load with and without cap (On going?).
- We measured the keystone tilt at different points, and the diferences are within 0.3[mm]
SR3/SRM:
- Kozu-kun and Enzo finished the SR3 in-air cabling.
- Enzo prepared the SR3 and SRM rack in parallel (On going).
BS:
- Kozu-kun and Enzo helped Enomoto-san troubleshooting the BS Oplev issue (On going).
- We finished the SR3 in-air cabling.
Plan for week of 4/2
- Mark at Mitaka Mon, Kamioka from Tue.
- Shoda-san at Mitaka
- Others at Kamioka
- --
- Finish BFs tasks (cabling +calibration)
- Finish SFs tasks (cabling +calibration)
- Add cable clamps to bases.
- Add cable clamps and Cu segments to caps (only if they fit well).
- Build 2xIM, 2xIRM
- Glue SR3 mirror?
Plan for week of 4/9
- Shoda-san at Mitaka
- Others at Kamioka
- --
- Finish IMs and IRMs
- Build 1xRM
Plan for week of 4/16
- Start SR3 Hang?
Plan for week of 4/23
- F0 blade prototype test
Plan for week of 4/30
- Golden Week!
To-Do Lists, Schedule
Vacation Info
- Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun)
- Fabian vacation, 3/26-4/27 (then gone).