  * Fabian prepared a work space in the ATC cleanroom and moved in nearly all the parts for the dummy BS, RM, IM and IRM.
  * Fabian finally got perfect agreement between the Mathematica and Matlab models of the BS. (The wire thicknesses had in µm instead of mm, leading to some modes off by 1E3.)
  * Hirata-san remeasured the BF for the BS. He noted that the cap went on and came off easily (unlike some other filters).
  * Hirata-san worked on final details of the Mirapro order for the assembly frame.
  * Hirata-san and Takahashi-san washed a large batch of parts.
  * Tatsumi-san will glue flags, sapphire primary prisms and metal secondary prisms to the dummy BS some time in the week of 6/8. Fabian and possibly Mark and/or Hirata-san will travel to KEK to help and observe.
  * Mark worked more on [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235|E1504235 BS Assembly Procedure]] ([[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|Draft on OneDrive]])
  * Mark updated the BS circuit diagram [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=3600|D1503600]]:
   * Added information on the binary IO.
   * Renamed channels to conform to Okutomi-kun's new scheme.
   * Made the ADC/DAC channel assignment consistent and more logical.
   * Updated the stepper motor sections with info about the new driver chassis.
  * Mark and Hirata-san worked on collecting parts and tools that will be needed for cabling of the BS next week. (11 special-purpose cables need to be made for the picos/steppers/OSEMs/LVDT on the RM/IRM/IM/BF and, time permitting, 2 more for the SF.)
  * Mark worked on schedule.
  * Mark updated the installation procedure with lessons learned from the last few weeks.
  * Mark downloaded Hirata-san's Inventor model of the BS in the tank and starting thinking about installation of the suspension and lower bread board.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

  • Type B Past Week Summary
    • Mark updated the BS circuit diagram D1503600:

      • Added information on the binary IO.
      • Renamed channels to conform to Okutomi-kun's new scheme.
      • Made the ADC/DAC channel assignment consistent and more logical.
      • Updated the stepper motor sections with info about the new driver chassis.
    • Mark and Hirata-san worked on collecting parts and tools that will be needed for cabling of the BS next week. (11 special-purpose cables need to be made for the picos/steppers/OSEMs/LVDT on the RM/IRM/IM/BF and, time permitting, 2 more for the SF.)
    • Mark worked on schedule.
    • Mark updated the installation procedure with lessons learned from the last few weeks.
    • Mark downloaded Hirata-san's Inventor model of the BS in the tank and starting thinking about installation of the suspension and lower bread board.