Line 7: Line 7:
At Kamioka (Mark, Ohishi-san, Enzo, Yoshioka-kun):
 * We installed the cut-down ballast mass under the IM and tweaked the IM height and balance.
 * We checked the range of the BF FR.
 * We adjusted the BF yoke by 2.5 mm to make it give ≈0 output for nominal height.
 * We found a good gain setting for the LVDT driver and calibrated the BF LVDT.
 * We set up the optical sensors facing the RM.
 * We assembled the IRM (with OSEMs) around the IM and got it mostly adjusted.
 * We changed the k1visbs model to restore the as-designed mapping of OSEMs to DAQ channels.
 * We confirmed that the BF LVDT actuation coil and the TM OSEM coils were working.
 * We connected up the IRM OSEMs (with the new Type 5-1.7 cables) but found there was an electrical issue: all the OSEMs are reading back the same constant value, around 1115.
 * We left the suspension in a state suitable for TFs from BF GAS actuation to sensing (in vertical) and from RM OSEM actuation to the optical sensors (in horizontal) over the weekend.
At Mitaka (Hirata-san):
 * Hirata-san did 2D drawings of the SR LBB rods and sent off an RFQ.
 * Hirata-san did several cost-reduction negotiations with Mirapro.
At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun):
 * We put lock nuts on the F0 FR and calibrated the F0 LVDT against FR position and keystone height.
 * Enzo traced the issue with the geophones to a specific cable.
 * We measured the BF and F0 GAS resonant frequencies.
 * We adjusted the spacing of the SR damper.
 * We double-checked the BS pitch with the OL.
 * We debugged the PI yaw mechanism. We managed to get the return spring properly adjusted, but the stepper motor tends to jam because of the strange design.
 * '''We prepared the suspension for lifting and craned it into the tank.'''
 * Hirata-san fixed an issue with one of the nailheads on the LBB intermediate ring support rods not properly seating, by removing the rod and reinstalling it upside down (with the problem nailhead in a less critical position).
 * Enzo and team moved all the in-air cables from the assembly frame to the tank.
 * Fabian and Ohishi-san unlocked the bottom section of the suspension and got it hanging freely.
 
==== Plan for week of 9/25 ====
Mark, Fabian, Enzo (Mon, Tue), Ohishi-san (Tue, Fri), Hirata-san, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun
 * Finish moving in-air cabling and feedthroughs and reconnect in-vacuum cables (through Cu O-rings).
 * Unlock rest of suspension and readjust.
 * Debug electronics.
 * Unclamp LBB ring "sandwich" so LBB Cu ring is suspended on upper rods.
 * Install LBB lower rods and hook LBB.
 * Adjust LBB damper Cu-magnet gap.
 * Measure required ballast for LBB.
 * Remove First Contact, try OL.
 * Prepare for SR2 work.
Line 22: Line 31:

==== Plan for week of 8/28 ====
Kamioka: Mark (except Tue), Ohishi-san, Fabian (except Tue), Enzo (except Tue), Hirata-san, Yoshioka-kun (Fri), Kozu-kun (Thu, Fri).
 * Fix/adjust IRM OSEMs.
 * Add BF cap; cable and test BF-1 and BF-2 picos.
 * Lift and weigh BF/IRM/IM/RM/BS; adjust ballast mass.
 * Crane in SF.
 * Suspend BF/IRM/IM/RM/BS.

==== Plan for week of 9/4 ====
 * Install SF cap; route cables.
 * Lift and weigh SF/BF/IRM/IM/RM/BS.
 * Adjust SF ballast.
==== Plan for week of 10/2 ====
Kamioka: Mark, Enzo, Fabian, Ohishi-san.
 * TFs etc.
Mitaka: Hirata-san?
 * SF design/purchasing.
Line 37: Line 38:
Mark: TBD Mid-Oct Mark: 10/16-24
Enzo: 9/27-29

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun):

  • We put lock nuts on the F0 FR and calibrated the F0 LVDT against FR position and keystone height.
  • Enzo traced the issue with the geophones to a specific cable.
  • We measured the BF and F0 GAS resonant frequencies.
  • We adjusted the spacing of the SR damper.
  • We double-checked the BS pitch with the OL.
  • We debugged the PI yaw mechanism. We managed to get the return spring properly adjusted, but the stepper motor tends to jam because of the strange design.
  • We prepared the suspension for lifting and craned it into the tank.

  • Hirata-san fixed an issue with one of the nailheads on the LBB intermediate ring support rods not properly seating, by removing the rod and reinstalling it upside down (with the problem nailhead in a less critical position).
  • Enzo and team moved all the in-air cables from the assembly frame to the tank.
  • Fabian and Ohishi-san unlocked the bottom section of the suspension and got it hanging freely.

Plan for week of 9/25

Mark, Fabian, Enzo (Mon, Tue), Ohishi-san (Tue, Fri), Hirata-san, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun

  • Finish moving in-air cabling and feedthroughs and reconnect in-vacuum cables (through Cu O-rings).
  • Unlock rest of suspension and readjust.
  • Debug electronics.
  • Unclamp LBB ring "sandwich" so LBB Cu ring is suspended on upper rods.
  • Install LBB lower rods and hook LBB.
  • Adjust LBB damper Cu-magnet gap.
  • Measure required ballast for LBB.
  • Remove First Contact, try OL.
  • Prepare for SR2 work.

Plan for week of 10/2

Kamioka: Mark, Enzo, Fabian, Ohishi-san.

  • TFs etc.

Mitaka: Hirata-san?

  • SF design/purchasing.

Vacation Info

Mark: 10/16-24 Enzo: 9/27-29

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)