1874
Comment:
|
1657
|
Deletions are marked like this. | Additions are marked like this. |
Line 6: | Line 6: |
==== Past week report ==== At Kamioka (Mark, Ohishi-san, Enzo, Yoshioka-kun): * We installed the cut-down ballast mass under the IM and tweaked the IM height and balance. * We checked the range of the BF FR. * We adjusted the BF yoke by 2.5 mm to make it give ≈0 output for nominal height. * We found a good gain setting for the LVDT driver and calibrated the BF LVDT. * We set up the optical sensors facing the RM. * We assembled the IRM (with OSEMs) around the IM and got it mostly adjusted. * We changed the k1visbs model to restore the as-designed mapping of OSEMs to DAQ channels. * We confirmed that the BF LVDT actuation coil and the TM OSEM coils were working. * We connected up the IRM OSEMs (with the new Type 5-1.7 cables) but found there was an electrical issue: all the OSEMs are reading back the same constant value, around 1115. * We left the suspension in a state suitable for TFs from BF GAS actuation to sensing (in vertical) and from RM OSEM actuation to the optical sensors (in horizontal) over the weekend. At Mitaka (Hirata-san): * Hirata-san did 2D drawings of the SR LBB rods and sent off an RFQ. * Hirata-san did several cost-reduction negotiations with Mirapro. |
==== Report for week of 1/29 ==== * Mark made two sets of in-air pico splitter cables (each with a triple for IM and a double for BF) for SR2 and SR3. * Fabian, Hirata-san and Kozu-kun worked on cabling and testing the IM pitch/roll/yaw picos, the BF FR and the BF LVDT. The LVDT connections were initially unreliable and Hirata-san had to redo the pins on the coil wires. * Fabian installed ballast masses in the BF. * Mark worked on schedule. * Mark did inventory of the stepper motor drivers (many were not accounted for on the wiki and/or JGWDoc and one is missing) and reserved two for SR3. |
Line 22: | Line 13: |
==== Plan for week of 2/13 ==== * No work Monday (建国記念の日の振替休日) * Enzo on vacation * Hirata-san at Mitaka Tue, Wed (to receive and wash parts). * Shoda-san at Mitaka * All others at Kamioka. * - * Build IRM around IM. * Cable/test/adjust IM OSEMs. * Do TFs from IM OSEMs to IM OSEMs, OL pitch/yaw. |
|
Line 23: | Line 24: |
==== Plan for week of 8/28 ==== Kamioka: Mark (except Tue), Ohishi-san, Fabian (except Tue), Enzo (except Tue), Hirata-san, Yoshioka-kun (Fri), Kozu-kun (Thu, Fri). * Fix/adjust IRM OSEMs. * Add BF cap; cable and test BF-1 and BF-2 picos. * Lift and weigh BF/IRM/IM/RM/BS; adjust ballast mass. * Crane in SF. * Suspend BF/IRM/IM/RM/BS. |
==== Plan for week of 2/19 ==== * Enzo back from Tuesday. * Shoda-san at Mitaka * All others at Kamioka. * - * Lift BF/... section and check total mass and balance. * Cable and test BF picos. * Add section of SS up to SF ring. * Bring in SF. * Hook BF/... section. * Route cables up to under SF. * Check/adjust total mass of BF/... section. |
Line 31: | Line 37: |
==== Plan for week of 9/4 ==== * Install SF cap; route cables. * Lift and weigh SF/BF/IRM/IM/RM/BS. * Adjust SF ballast. |
==== Plan for week of 2/26 ==== * Add Cu segments to SF cap. * Lift SF/... section and check total mass and balance. |
Line 37: | Line 42: |
Mark: TBD Mid-Oct | * Enzo 1/30-2/19. * Fabian 4/2-4/27 vacation (then gone). |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 1/29
- Mark made two sets of in-air pico splitter cables (each with a triple for IM and a double for BF) for SR2 and SR3.
- Fabian, Hirata-san and Kozu-kun worked on cabling and testing the IM pitch/roll/yaw picos, the BF FR and the BF LVDT. The LVDT connections were initially unreliable and Hirata-san had to redo the pins on the coil wires.
- Fabian installed ballast masses in the BF.
- Mark worked on schedule.
- Mark did inventory of the stepper motor drivers (many were not accounted for on the wiki and/or JGWDoc and one is missing) and reserved two for SR3.
Plan for week of 2/13
- No work Monday (建国記念の日の振替休日)
- Enzo on vacation
- Hirata-san at Mitaka Tue, Wed (to receive and wash parts).
- Shoda-san at Mitaka
- All others at Kamioka.
- -
- Build IRM around IM.
- Cable/test/adjust IM OSEMs.
- Do TFs from IM OSEMs to IM OSEMs, OL pitch/yaw.
Plan for week of 2/19
- Enzo back from Tuesday.
- Shoda-san at Mitaka
- All others at Kamioka.
- -
- Lift BF/... section and check total mass and balance.
- Cable and test BF picos.
- Add section of SS up to SF ring.
- Bring in SF.
- Hook BF/... section.
- Route cables up to under SF.
- Check/adjust total mass of BF/... section.
Plan for week of 2/26
- Add Cu segments to SF cap.
- Lift SF/... section and check total mass and balance.
Vacation Info
- Enzo 1/30-2/19.
- Fabian 4/2-4/27 vacation (then gone).