Line 7: Line 7:
At Kamioka (Mark, Ohishi-san, Enzo, Yoshioka-kun):
 * We installed the cut-down ballast mass under the IM and tweaked the IM height and balance.
 * We checked the range of the BF FR.
 * We adjusted the BF yoke by 2.5 mm to make it give ≈0 output for nominal height.
 * We found a good gain setting for the LVDT driver and calibrated the BF LVDT.
 * We set up the optical sensors facing the RM.
 * We assembled the IRM (with OSEMs) around the IM and got it mostly adjusted.
 * We changed the k1visbs model to restore the as-designed mapping of OSEMs to DAQ channels.
 * We confirmed that the BF LVDT actuation coil and the TM OSEM coils were working.
 * We connected up the IRM OSEMs (with the new Type 5-1.7 cables) but found there was an electrical issue: all the OSEMs are reading back the same constant value, around 1115.
 * We left the suspension in a state suitable for TFs from BF GAS actuation to sensing (in vertical) and from RM OSEM actuation to the optical sensors (in horizontal) over the weekend.
At Mitaka (Hirata-san):
 * He got quotes for the SR assembly frame and did cost-reduction negotiations with Aso-san and Mirapro.
got quotes for assembly frame.
 * He did 2D drawings and a parts list for the divided LBB dampers.
 * He contacted a company about SDC.
 * He made a 3D model and drawings for the SR wire clamps.
At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun):
 * We moved or covered stuff in the BS cleanbooth to prepare for the SR2 crane slot cutting and BS-> SR2 assembly frame move.
 * We put the service port covers back on at the BF level of the BS tank.
 * We used the PI jacks to center the bottom of the security structure around the RM.
 * We debugged a mechanical issue where the #2 IP LVDT had too narrow a gap between the moving and fixed parts, so that there was interference with only a very small clockwise yaw of the IP. We fixed it by moving the bottom baseplate (taking advantage of the fact that it was held by screws in oversize holes for this purpose).
 * We used the IP FRs to center the IP.
 * We set the gains on the IP LVDT driver.
 * We tested the picos and most of the steppers. The picos and IP steppers all work nicely. The PI FR and yaw steppers have jamming issues. We haven't tested the BF and SF FR steppers.
 * We debugged an issue with one of the geophones (#1) which has a DC offset. We did cable swaps and determined that the issue is internal to the geophone pod. A second geophone (#2) saturates at a suspiciously small voltage on the negative side. Again the issue is internal.
 * Fabian designed an improvement to the PI yaw stepper driver mount to stop the stepper jamming.
 * Fabian worked on a plan to measure the load capacity of the SR PIs.
 * Hirata-san did 2D drawings of the PI for the SR, and of SF2 and SRM in their vacuum chambers.
 * Hirata-san did drawings if the SR LBB damper rings and asked for quotes.
 * Hirata-san asked for quotes for SR secondary wire breakers and SR IM/IRM lock screws
 * Hirata-san ordered SR IM wire clamps.
 * Hirata-san worked on parts lists for SR cable clamps.
Line 25: Line 24:
==== Plan for week of 8/28 ====
Kamioka: Mark (except Tue), Ohishi-san, Fabian (except Tue), Enzo (except Tue), Hirata-san, Yoshioka-kun (Fri), Kozu-kun (Thu, Fri).
 * Fix/adjust IRM OSEMs.
 * Add BF cap; cable and test BF-1 and BF-2 picos.
 * Lift and weigh BF/IRM/IM/RM/BS; adjust ballast mass.
 * Crane in SF.
 * Suspend BF/IRM/IM/RM/BS.
==== Plan for week of 10/2 ====
 * Design ballast for LBB.
 * Design improved PI yaw adjustment.
 * SR procurement.
Line 33: Line 29:
==== Plan for week of 9/4 ====
 * Install SF cap; route cables.
 * Lift and weigh SF/BF/IRM/IM/RM/BS.
 * Adjust SF ballast.
==== Plan for week of 10/10 ====
Kamioka: Mark, Fabian, Enzo, Ohishi-san, Kozu-kun.
Mitaka: Hirata-san
Holiday Mon 10/9, Open Day prep Fri 10/13.<<BR>>
 * Tune IP, do LVDT/stepper calibration.
 * Remove First Contact, try OL.
 * TFs, final preparation for alignment in week of 10/16.

==== Plan for week of 10/16 ====
Kamioka: all but Mark
 * Work with alignment team.
Line 39: Line 42:
Mark: TBD Mid-Oct Mark: 10/16-24

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun):

  • We moved or covered stuff in the BS cleanbooth to prepare for the SR2 crane slot cutting and BS-> SR2 assembly frame move.

  • We put the service port covers back on at the BF level of the BS tank.
  • We used the PI jacks to center the bottom of the security structure around the RM.
  • We debugged a mechanical issue where the #2 IP LVDT had too narrow a gap between the moving and fixed parts, so that there was interference with only a very small clockwise yaw of the IP. We fixed it by moving the bottom baseplate (taking advantage of the fact that it was held by screws in oversize holes for this purpose).
  • We used the IP FRs to center the IP.
  • We set the gains on the IP LVDT driver.
  • We tested the picos and most of the steppers. The picos and IP steppers all work nicely. The PI FR and yaw steppers have jamming issues. We haven't tested the BF and SF FR steppers.
  • We debugged an issue with one of the geophones (#1) which has a DC offset. We did cable swaps and determined that the issue is internal to the geophone pod. A second geophone (#2) saturates at a suspiciously small voltage on the negative side. Again the issue is internal.
  • Fabian designed an improvement to the PI yaw stepper driver mount to stop the stepper jamming.
  • Fabian worked on a plan to measure the load capacity of the SR PIs.
  • Hirata-san did 2D drawings of the PI for the SR, and of SF2 and SRM in their vacuum chambers.
  • Hirata-san did drawings if the SR LBB damper rings and asked for quotes.
  • Hirata-san asked for quotes for SR secondary wire breakers and SR IM/IRM lock screws
  • Hirata-san ordered SR IM wire clamps.
  • Hirata-san worked on parts lists for SR cable clamps.

Plan for week of 10/2

  • Design ballast for LBB.
  • Design improved PI yaw adjustment.
  • SR procurement.

Plan for week of 10/10

Kamioka: Mark, Fabian, Enzo, Ohishi-san, Kozu-kun. Mitaka: Hirata-san Holiday Mon 10/9, Open Day prep Fri 10/13.

  • Tune IP, do LVDT/stepper calibration.
  • Remove First Contact, try OL.
  • TFs, final preparation for alignment in week of 10/16.

Plan for week of 10/16

Kamioka: all but Mark

  • Work with alignment team.

Vacation Info

Mark: 10/16-24