==== Past week report ==== At Kamioka (Mark, Ohishi-san, Enzo, Yoshioka-kun): * We installed the cut-down ballast mass under the IM and tweaked the IM height and balance. * We checked the range of the BF FR. * We adjusted the BF yoke by 2.5 mm to make it give ≈0 output for nominal height. * We found a good gain setting for the LVDT driver and calibrated the BF LVDT. * We set up the optical sensors facing the RM. * We assembled the IRM (with OSEMs) around the IM and got it mostly adjusted. * We changed the k1visbs model to restore the as-designed mapping of OSEMs to DAQ channels. * We confirmed that the BF LVDT actuation coil and the TM OSEM coils were working. * We connected up the IRM OSEMs (with the new Type 5-1.7 cables) but found there was an electrical issue: all the OSEMs are reading back the same constant value, around 1115. * We left the suspension in a state suitable for TFs from BF GAS actuation to sensing (in vertical) and from RM OSEM actuation to the optical sensors (in horizontal) over the weekend. At Mitaka (Hirata-san): * He got quotes for the SR assembly frame and did cost-reduction negotiations with Aso-san and Mirapro. got quotes for assembly frame. * He did 2D drawings and a parts list for the divided LBB dampers. * He contacted a company about SDC. * He made a 3D model and drawings for the SR wire clamps. |
==== Report for week of 12/25 ==== * Hirata-san got the L-brackets machined and washed, and installed them on the IM ring bars. * Shoda-san recovered the BS from the power outage on 12/25. * Miyakawa-san fixed an issue with the SR2 RTM which had prevented it from running. * Shoda-san, Hirata-san and Kozu-kun weighed the IM without ballast masses, and then added the lower masses and installed the IM on the assembly frame. * They cleaned the assembly frame and installed new jack receptacles on the load gauge adapter. * They installed the winch system on the IM, and inspected the clamp pieces for possible scratches. * They ran cables for the SR2 steppers and OSEMs. * They calibrated the BF LVDT. |
Line 25: | Line 16: |
==== Plan for week of 8/28 ==== Kamioka: Mark (except Tue), Ohishi-san, Fabian (except Tue), Enzo (except Tue), Hirata-san, Yoshioka-kun (Fri), Kozu-kun (Thu, Fri). * Fix/adjust IRM OSEMs. * Add BF cap; cable and test BF-1 and BF-2 picos. * Lift and weigh BF/IRM/IM/RM/BS; adjust ballast mass. * Crane in SF. * Suspend BF/IRM/IM/RM/BS. |
==== Report for week of 1/4 ==== * Mark fixed a number of errors with the Type B screens. |
Line 33: | Line 19: |
==== Plan for week of 9/4 ==== * Install SF cap; route cables. * Lift and weigh SF/BF/IRM/IM/RM/BS. * Adjust SF ballast. |
==== Report for week of 1/9 ==== * We weighed the mirror in its box (and later the empty box), and the RM. * Fabian worked on the SR2/SR3/SRM mass budget and did an inventory of spare ballast masses. * We hung the SR2 and RM. * We assembled the bottom section of the security structure below the RM. * Hirata-san gave up on waiting for a third quote for the blades and blade parts and started the ordering process. * Hirata-san got rod cable clamp parts from Takahashi-san and worked on drawings for the improved BS vertical and yaw adjusters. ==== Plan for week of 1/15 ==== * Shoda-san at Mitaka making OSEMs. * ==== Plan for week of 1/22 ==== ==== Plan for week of 1/22 ==== * Mark, Fabian, Enzo, Shoda-san at Kamioka Tue-Fri. * Hang SR and RM. |
Line 39: | Line 37: |
Mark: TBD Mid-Oct | * Enzo 1/30-2/19 (at Mitaka 1/29, part of 1/30) * Kozu-kun 1/29-2/2 |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 12/25
- Hirata-san got the L-brackets machined and washed, and installed them on the IM ring bars.
- Shoda-san recovered the BS from the power outage on 12/25.
- Miyakawa-san fixed an issue with the SR2 RTM which had prevented it from running.
- Shoda-san, Hirata-san and Kozu-kun weighed the IM without ballast masses, and then added the lower masses and installed the IM on the assembly frame.
- They cleaned the assembly frame and installed new jack receptacles on the load gauge adapter.
- They installed the winch system on the IM, and inspected the clamp pieces for possible scratches.
- They ran cables for the SR2 steppers and OSEMs.
- They calibrated the BF LVDT.
Report for week of 1/4
- Mark fixed a number of errors with the Type B screens.
Report for week of 1/9
- We weighed the mirror in its box (and later the empty box), and the RM.
- Fabian worked on the SR2/SR3/SRM mass budget and did an inventory of spare ballast masses.
- We hung the SR2 and RM.
- We assembled the bottom section of the security structure below the RM.
- Hirata-san gave up on waiting for a third quote for the blades and blade parts and started the ordering process.
- Hirata-san got rod cable clamp parts from Takahashi-san and worked on drawings for the improved BS vertical and yaw adjusters.
Plan for week of 1/15
- Shoda-san at Mitaka making OSEMs.
Plan for week of 1/22
Plan for week of 1/22
- Mark, Fabian, Enzo, Shoda-san at Kamioka Tue-Fri.
- Hang SR and RM.
Vacation Info
- Enzo 1/30-2/19 (at Mitaka 1/29, part of 1/30)
- Kozu-kun 1/29-2/2