==== Past week report ==== At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun): * We solved the problem with the OSEMs: cables had been plugged into the LED current monitor outputs, not the PD outputs. * We solved a problem with the real-time model freezing which turned out to be the IO chassis having lost power. * We took some mass off the IM to allow for the weight of the cables, and readjusted it in pitch and roll. * We aligned the IM |
==== Past two weeks report ==== At Kamioka (Mark, Enzo, Kozu-kun): * Supported IA team. * Replaced LPCDs for IM OSEMs with HPCDs for increased pitch/yaw range. * Re-zeroed OL after significant change of beam position during IA. * Re-laid-out OL to improve focus of lens to LEN QPD. * Offloaded the pitch/yaw actuation at the IM OSEMs using the IM pitch/yaw picos. * Enzo worked on design of control loops using the OL. * Kozu-kun worked on diagonalizing the OL. |
Line 13: | Line 16: |
==== Plan for week of 8/28 ==== Kamioka: Mark (except Tue), Ohishi-san, Fabian (except Tue), Enzo (except Tue), Hirata-san, Yoshioka-kun (Fri), Kozu-kun (Thu, Fri). * Fix/adjust IRM OSEMs. * Add BF cap; cable and test BF-1 and BF-2 picos. * Lift and weigh BF/IRM/IM/RM/BS; adjust ballast mass. * Crane in SF. * Suspend BF/IRM/IM/RM/BS. |
Mitaka (Fabian, Hirata-san): * Hirata-san published his inventory of SR parts on Dropbox. |
Line 21: | Line 19: |
==== Plan for week of 9/4 ==== * Install SF cap; route cables. * Lift and weigh SF/BF/IRM/IM/RM/BS. * Adjust SF ballast. |
==== Plan for week of 11/13 ==== |
Line 26: | Line 21: |
==== Vacation Info ==== Mark: TBD Mid-Oct |
Kamioka: Mark * Attend commissioning workshop at U Toyama. * Be person-on-site for BF work. * Set up for mirror gluing. Mitaka: Fabian and Hirata-san * SR procurement. * New PI GAS FR design. * BS LBB ballast mass design. * SR cable lamp design. Mitaka: Enzo and Kozu-kun (Wed, Thu) * Servos * TFs of BF * Documentation |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Past two weeks report
At Kamioka (Mark, Enzo, Kozu-kun):
- Supported IA team.
- Replaced LPCDs for IM OSEMs with HPCDs for increased pitch/yaw range.
- Re-zeroed OL after significant change of beam position during IA.
- Re-laid-out OL to improve focus of lens to LEN QPD.
- Offloaded the pitch/yaw actuation at the IM OSEMs using the IM pitch/yaw picos.
- Enzo worked on design of control loops using the OL.
- Kozu-kun worked on diagonalizing the OL.
Mitaka (Fabian, Hirata-san):
- Hirata-san published his inventory of SR parts on Dropbox.
Plan for week of 11/13
Kamioka: Mark
- Attend commissioning workshop at U Toyama.
- Be person-on-site for BF work.
- Set up for mirror gluing.
Mitaka: Fabian and Hirata-san
- SR procurement.
- New PI GAS FR design.
- BS LBB ballast mass design.
- SR cable lamp design.
Mitaka: Enzo and Kozu-kun (Wed, Thu)
- Servos
- TFs of BF