At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun): * We solved the problem with the OSEMs: cables had been plugged into the confusingly named "PD current monitor" outputs (actually LED current monitors), not the "OSEM outputs". * We solved a problem with the real-time model freezing which turned out to be the IO chassis having lost power. * We took some mass off the IM to allow for the weight of the cables, and readjusted it in pitch and roll. * We aligned the IRM to the IM and set the OSEMs to mid-range. * We added ballast to the BF. * We changed the receptacles for the SF-BF rod. The low receptacle did not fit properly into the BF keystone and Hirata-san had to file it. * We fixed a broken wire on the BF yaw pico, retested the pico and added the BF cap. * We cabled and tested the BF cap picos. * We lifted the BF and weighed and balanced it. * We installed the SF ring and brought in the SF. * We cabled the SF LVDT and did a quick test (not a full calibration). * We replaced non-vacuum compatible cables in the PI, removed various sticky labels and wiped it with ethanol. * We tried to hook the SF-BF rod but found the hole in the hex cable clamp was too small for the 8 mm rod head. We enlarged the hole but then found the PEEK pieces were too loose. We tried using foil, but then managed to lose a PEEK piece into the BF, so we will need to remove the cap of the BF to get it. |
|
Line 22: | Line 8: |
==== Plan for week of 8/28 ==== Kamioka: Mark (except Tue), Ohishi-san, Fabian (except Tue), Enzo (except Tue), Hirata-san, Yoshioka-kun (Fri), Kozu-kun (Thu, Fri). * Fix/adjust IRM OSEMs. * Add BF cap; cable and test BF-1 and BF-2 picos. * Lift and weigh BF/IRM/IM/RM/BS; adjust ballast mass. * Crane in SF. * Suspend BF/IRM/IM/RM/BS. |
* Mark analyzed the QPD data from Friday 12/1 and derived matrices to diagonalize the QPD, and calibrate output in µrad. In the process an error in the IM OSEM diagonalization was discovered: the P and Y gains were low by a factor 2. * Mark re-zeroed the QPD after noting the micrometer readings so we can do TFs over the weekend. * We prepared for the SR2 gluing: * We aligned the SR2 in the box with the wedge on the correct side. * We checked that the remachined BS prism holders fit on the PR2 mirror box. * We checked that with Tatsumi-san's support ring, the prisms would go on at the right height. * We checked the new magnet jigs. * We glued ferromagnetic disks in a large number of IM flag tips and flag bases, and in the SR magnet jigs. * We also glued SR magnets in the magnet bases. |
Line 30: | Line 18: |
==== Plan for week of 9/4 ==== * Install SF cap; route cables. * Lift and weigh SF/BF/IRM/IM/RM/BS. * Adjust SF ballast. |
==== Plan for week of 12/11 * Mark, Fabian, Enzo, Kozu-kun (Mon-Thu only), Hirata-san, Shoda-san at Kamioka. * Mirror gluing. * IM assembly and pico test. * Assembly frame alignment and optical table centering. * Move trolley system from SR3. * OL setup. ==== Plan for week of 12/18 ==== * Shoda-san vacation * Mark, Fabian, Enzo, Kozu-kun at Kamioka Mon-Wed. |
Line 36: | Line 31: |
Mark: TBD Mid-Oct | * Mark 12/22-1/3 * Enzo, 12/21-12/27 (but ''not'' 12/28) * Fabian 12/22-1/5 * Hirata-san 12/21-22 (conference) * Shoda-san 12/18-21 |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Past week report
- Mark analyzed the QPD data from Friday 12/1 and derived matrices to diagonalize the QPD, and calibrate output in µrad. In the process an error in the IM OSEM diagonalization was discovered: the P and Y gains were low by a factor 2.
- Mark re-zeroed the QPD after noting the micrometer readings so we can do TFs over the weekend.
- We prepared for the SR2 gluing:
- We aligned the SR2 in the box with the wedge on the correct side.
- We checked that the remachined BS prism holders fit on the PR2 mirror box.
- We checked that with Tatsumi-san's support ring, the prisms would go on at the right height.
- We checked the new magnet jigs.
- We glued ferromagnetic disks in a large number of IM flag tips and flag bases, and in the SR magnet jigs.
- We also glued SR magnets in the magnet bases.
==== Plan for week of 12/11
- Mark, Fabian, Enzo, Kozu-kun (Mon-Thu only), Hirata-san, Shoda-san at Kamioka.
- Mirror gluing.
- IM assembly and pico test.
- Assembly frame alignment and optical table centering.
- Move trolley system from SR3.
- OL setup.
Plan for week of 12/18
- Shoda-san vacation
- Mark, Fabian, Enzo, Kozu-kun at Kamioka Mon-Wed.
Vacation Info
- Mark 12/22-1/3
Enzo, 12/21-12/27 (but not 12/28)
- Fabian 12/22-1/5
- Hirata-san 12/21-22 (conference)
- Shoda-san 12/18-21