Size: 2134
Comment:
|
Size: 1817
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 6: | Line 6: |
==== Past week report ==== At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun): * We solved the problem with the OSEMs: cables had been plugged into the confusingly named "PD current monitor" outputs (actually LED current monitors), not the "OSEM outputs". * We solved a problem with the real-time model freezing which turned out to be the IO chassis having lost power. * We took some mass off the IM to allow for the weight of the cables, and readjusted it in pitch and roll. * We aligned the IRM to the IM and set the OSEMs to mid-range. * We added ballast to the BF. * We changed the receptacles for the SF-BF rod. The low receptacle did not fit properly into the BF keystone and Hirata-san had to file it. * We fixed a broken wire on the BF yaw pico, retested the pico and added the BF cap. * We cabled and tested the BF cap picos. * We lifted the BF and weighed and balanced it. * We installed the SF ring and brought in the SF. * We cabled the SF LVDT and did a quick test (not a full calibration). * We replaced non-vacuum compatible cables in the PI, removed various sticky labels and wiped it with ethanol. * We tried to hook the SF-BF rod but found the hole in the hex cable clamp was too small for the 8 mm rod head. We enlarged the hole but then found the PEEK pieces were too loose. We tried using foil, but then managed to lose a PEEK piece into the BF, so we will need to remove the cap of the BF to get it. |
==== Report for week of 1/15 ==== * We set up the QPD for the OL, initialized the OL and TM sections of the RTM, and did TFs from the TM OSEMs to the OL. * Initially we had no coherence, but we debugged issues with the watchdog, LPCD, and DAC board and then got good TFs. * We lifted the IM/RM/SR with the load gauge adapter and checked the weight, which was close to the mass budget. * We installed the section of the AF above the IM, and the BF cross bars and jacks, and craned in the BF. * We installed the BF-IRM rods, IRM, BF-IM rod, flying saucer and the cable clamps on the bottom of the BF. * We hooked the IM section, but found it was heavy by several hundred grams. We also noticed the BF keystone had a noticeable tilt of about 1.2 mm (high on the +X side). * We removed 738 g of trim mass and found that load rose and sat about 2 mm high. So the discrepancy is of order 500-600 g. * Shoda-san, Enzo and Kozu-kun made and characterized a batch of OSEMs. * Hirata-san finished drawings for the improved BS PI yaw/vertical adjustment, placed orders for damping ring receptacles and other items, and prepared the second SR BF in case we needed to swap it in. ==== Plan for week of 1/22 ==== * Fix or swap BF. * Route selected cables to flange. * Test IM picos and BF yaw pico. |
Line 22: | Line 22: |
==== Plan for week of 8/28 ==== Kamioka: Mark (except Tue), Ohishi-san, Fabian (except Tue), Enzo (except Tue), Hirata-san, Yoshioka-kun (Fri), Kozu-kun (Thu, Fri). * Fix/adjust IRM OSEMs. * Add BF cap; cable and test BF-1 and BF-2 picos. * Lift and weigh BF/IRM/IM/RM/BS; adjust ballast mass. * Crane in SF. * Suspend BF/IRM/IM/RM/BS. ==== Plan for week of 9/4 ==== * Install SF cap; route cables. * Lift and weigh SF/BF/IRM/IM/RM/BS. * Adjust SF ballast. |
==== Plan for week of 1/29 ==== * Enzo at Mitaka 1/29 and most of 1/30, then vacation. * Kozu-kun away. * All others at Kamioka. * Build IRM around IM. * Cable/test/adjust IM OSEMs. * Time permitting, do TFs from IM OSEMs to themselves and to optical sensor. |
Line 36: | Line 31: |
Mark: TBD Mid-Oct | * Enzo 1/30-2/19 (at Mitaka 1/29, part of 1/30) * Kozu-kun 1/29-2/2 |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 1/15
- We set up the QPD for the OL, initialized the OL and TM sections of the RTM, and did TFs from the TM OSEMs to the OL.
- Initially we had no coherence, but we debugged issues with the watchdog, LPCD, and DAC board and then got good TFs.
- We lifted the IM/RM/SR with the load gauge adapter and checked the weight, which was close to the mass budget.
- We installed the section of the AF above the IM, and the BF cross bars and jacks, and craned in the BF.
- We installed the BF-IRM rods, IRM, BF-IM rod, flying saucer and the cable clamps on the bottom of the BF.
- We hooked the IM section, but found it was heavy by several hundred grams. We also noticed the BF keystone had a noticeable tilt of about 1.2 mm (high on the +X side).
- We removed 738 g of trim mass and found that load rose and sat about 2 mm high. So the discrepancy is of order 500-600 g.
- Shoda-san, Enzo and Kozu-kun made and characterized a batch of OSEMs.
- Hirata-san finished drawings for the improved BS PI yaw/vertical adjustment, placed orders for damping ring receptacles and other items, and prepared the second SR BF in case we needed to swap it in.
Plan for week of 1/22
- Fix or swap BF.
- Route selected cables to flange.
- Test IM picos and BF yaw pico.
Plan for week of 1/29
- Enzo at Mitaka 1/29 and most of 1/30, then vacation.
- Kozu-kun away.
- All others at Kamioka.
- Build IRM around IM.
- Cable/test/adjust IM OSEMs.
- Time permitting, do TFs from IM OSEMs to themselves and to optical sensor.
Vacation Info
- Enzo 1/30-2/19 (at Mitaka 1/29, part of 1/30)
- Kozu-kun 1/29-2/2