Line 8: | Line 8: |
* We solved the problem with the OSEMs: cables had been plugged into the confusingly named "PD current monitor" outputs (actually LED current monitors), not the "OSEM outputs". * We solved a problem with the real-time model freezing which turned out to be the IO chassis having lost power. * We took some mass off the IM to allow for the weight of the cables, and readjusted it in pitch and roll. * We aligned the IRM to the IM and set the OSEMs to mid-range. * We added ballast to the BF. * We changed the receptacles for the SF-BF rod. The low receptacle did not fit properly into the BF keystone and Hirata-san had to file it. * We fixed a broken wire on the BF yaw pico, retested the pico and added the BF cap. * We cabled and tested the BF cap picos. * We lifted the BF and weighed and balanced it. * We installed the SF ring and brought in the SF. * We installed the Cu segments on the SF. * We cabled the SF LVDT and did a quick test (not a full calibration). * We replaced non-vacuum compatible cables in the PI, removed various sticky labels and wiped it with ethanol. * We tried to hook the SF-BF rod but found the hole in the hex cable clamp was too small for the 8 mm rod head. We enlarged the hole but then found the PEEK pieces were too loose. We tried using foil, but then managed to lose a PEEK piece into the BF, so we will need to remove the cap of the BF to get it. |
* We disconnected the SF/... section and reinstalled the F0-SF rod with the hex cable clamp attached. * We debugged an issue with the actuation (the real-time model needed rebooting). * We routed all the SF/... cables up to the bottom of the PI, and then to the feedthroughs. * We unlocked the F0 keystone and experimented to find the amount of mass needed on the SF (≈845 g). * We attached the SF trim mass, adjusting it laterally so that the SF was level in pitch and roll. * We corrected some errors on the MEDM screens (some broken links and Take/Restore Safe.snap buttons). * We cabled all the PI items through to the rack and did very basic testing. * We disconnected the security structure from the assembly frame and adjusted the PI till the SS was vertical. * We unlocked the IP and adjusted the PI jacks and FRs till the IP was centered. * We passed the halves of the LBB Cu damping ring (less the Cu) into the chamber and joined them. * We put the magnets on the LBB damper ring using the template. * We locked various combinations of keystones and measured the vertical resonance frequencies of the unlocked filters. * We spent time on getting the geophones working. The original descrambler adapters had gone missing, so Enzo created three new ones. We borrowed a cable to replace one that had broken. The geophone distributor (S1402167) failed (no power on the negative rail), and a replacement borrowed from SR3 (S1605513) kept switching off. |
Line 23: | Line 22: |
==== Plan for week of 9/4 ==== Mark, Fabian, Enzo (Tue-Fri), Ohishi-san, Hirata-san, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun (Thu, Fri) * Retrieve PEEK piece from BF. * Crane SF back in. * Suspend BF/IRM/IM/RM/BS. * Test SF FR. * Calibrate SF LVDT. * Install SF cap; route cables. * Lift and weigh SF/BF/IRM/IM/RM/BS. * Adjust SF ballast. |
==== Plan for week of 9/19 ==== No work Mon 9/18 (敬老の日)<<BR>> Mark, Fabian, Enzo, Ohishi-san, Hirata-san, Yoshioka-kun (Tue, Wed, Thu, Fri), Kozu-kun * Double check BS pitch with OL. * Adjust SF damper ring to correct gap. * Install lock nuts on F0 GAS FR at TBD positions. * Lock BF and F0 keystones (but ''not'' SF keystone). * Lock RM to BS and IRM to IM. * Lock RM, IRM and BF (but not SF) to security structure. * Lock IP. * Remove F0 keystone top plate (including yaw stepper) and immobilize SF/... in yaw. * Attach lifting fixture. * Remove BF- and SF-level crossbars. * Remove geophones for craning. * Disconnect in-vacuum cables from feedthrough and coil neatly for craning. * Attach lifting plates. * Attach Cu segments to LBB damper ring (needs Cu segments and BUMAX countersunk screws, expected 9/20). * Pass halves of LBB magnet ring into tank, join, and make sandwich for craning. * Crane tank lid off. * Crane LBB damper rings to top of tank and suspend. * Crane suspension out of assembly frame. * Attach LBB upper rods to LBB blade tips and rotate suspension 45° clockwise. * Crane suspension into tank and connect upper rods to LBB Cu ring. * Unclamp LBB ring "sandwich" so LBB Cu ring is suspended on upper rods. * Install LBB lower rods and hook LBB. * Measure required ballast for LBB. * Unlock suspension and readjust. * Move in-air cabling and feedthroughs and reconnect in-vacuum cables (through Cu O-rings). |
Line 34: | Line 51: |
==== Plan for week of 9/13 ==== Mark (except Wed), Fabian (except ASJ), Enzo, Ohishi-san, Hirata-san, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun * Prepare magnet ring. * Bring in PI. * Route cables. * Suspend SF/..., adjust tilt of SF and total mass. * Adjust damper gap. |
==== Plan for week of 9/25 ==== TBD * Debug cabling. * Run TFs. * Install LSOL? |
Line 44: | Line 59: |
Mark: TBD Mid-Oct | Mark: 10/16-24 |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Past week report
At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun):
- We disconnected the SF/... section and reinstalled the F0-SF rod with the hex cable clamp attached.
- We debugged an issue with the actuation (the real-time model needed rebooting).
- We routed all the SF/... cables up to the bottom of the PI, and then to the feedthroughs.
- We unlocked the F0 keystone and experimented to find the amount of mass needed on the SF (≈845 g).
- We attached the SF trim mass, adjusting it laterally so that the SF was level in pitch and roll.
- We corrected some errors on the MEDM screens (some broken links and Take/Restore Safe.snap buttons).
- We cabled all the PI items through to the rack and did very basic testing.
- We disconnected the security structure from the assembly frame and adjusted the PI till the SS was vertical.
- We unlocked the IP and adjusted the PI jacks and FRs till the IP was centered.
- We passed the halves of the LBB Cu damping ring (less the Cu) into the chamber and joined them.
- We put the magnets on the LBB damper ring using the template.
- We locked various combinations of keystones and measured the vertical resonance frequencies of the unlocked filters.
- We spent time on getting the geophones working. The original descrambler adapters had gone missing, so Enzo created three new ones. We borrowed a cable to replace one that had broken. The geophone distributor (S1402167) failed (no power on the negative rail), and a replacement borrowed from SR3 (S1605513) kept switching off.
Plan for week of 9/19
No work Mon 9/18 (敬老の日)
Mark, Fabian, Enzo, Ohishi-san, Hirata-san, Yoshioka-kun (Tue, Wed, Thu, Fri), Kozu-kun
- Double check BS pitch with OL.
- Adjust SF damper ring to correct gap.
- Install lock nuts on F0 GAS FR at TBD positions.
Lock BF and F0 keystones (but not SF keystone).
- Lock RM to BS and IRM to IM.
- Lock RM, IRM and BF (but not SF) to security structure.
- Lock IP.
- Remove F0 keystone top plate (including yaw stepper) and immobilize SF/... in yaw.
- Attach lifting fixture.
- Remove BF- and SF-level crossbars.
- Remove geophones for craning.
- Disconnect in-vacuum cables from feedthrough and coil neatly for craning.
- Attach lifting plates.
- Attach Cu segments to LBB damper ring (needs Cu segments and BUMAX countersunk screws, expected 9/20).
- Pass halves of LBB magnet ring into tank, join, and make sandwich for craning.
- Crane tank lid off.
- Crane LBB damper rings to top of tank and suspend.
- Crane suspension out of assembly frame.
- Attach LBB upper rods to LBB blade tips and rotate suspension 45° clockwise.
- Crane suspension into tank and connect upper rods to LBB Cu ring.
- Unclamp LBB ring "sandwich" so LBB Cu ring is suspended on upper rods.
- Install LBB lower rods and hook LBB.
- Measure required ballast for LBB.
- Unlock suspension and readjust.
- Move in-air cabling and feedthroughs and reconnect in-vacuum cables (through Cu O-rings).
Plan for week of 9/25
TBD
- Debug cabling.
- Run TFs.
- Install LSOL?
Vacation Info
Mark: 10/16-24