==== Past week report ====
At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun):
 * We craned out the SF temporarily and retrieved the lost PEEK cable clamp collet from the BF.
 * We installed the BF.
 * We routed cables from the BF via the hex cable clamp to the SF level.
 * We adjusted the BF trim mass for pitch, roll and vertical, and got the IRM hanging symmetrically around the IM.
 * We adjusted all the IRM OSEMs laterally and in/out.
 * We calibrated the SF LVDT and tested the SF FR stepper.
 * We suspended the SF/... section and weighed it but found the old 7-mm maraging rod adapter did not hold it at the center, so we chad to lift it with slings and could not accurately trim it for pitch/roll.
 * We craned in the PI with the SF damper ring hanging from it.
 * We suspended the SF successfully from the PI and unlocked the F0 keystone to check the mass budget. We needed about 1.5 kg extra, which is about right.
 * However we had to leave out the F0-SF hex cable clamp because of a bad thread on the inside of the cap. Hirata-san will make a new cap by enlarging the 7-mm hole in an old cap to 8 mm.
==== Past two weeks report ====
Kamioka (Mark, Enzo, Kozu-kun):
 * Supported IA team.
 * Replaced LPCDs for IM OSEMs with HPCDs for increased pitch/yaw range.
 * Re-zeroed OL after significant change of beam position during IA.
 * Re-laid-out OL to improve focus of lens to LEN QPD.
 * Offloaded the pitch/yaw actuation at the IM OSEMs using the IM pitch/yaw picos.
 * Enzo worked on design of control loops using the OL.
 * Kozu-kun worked on diagonalizing the OL.
Line 19: Line 16:
==== Plan for week of 9/4 ====
Mark, Fabian, Enzo (Tue-Fri), Ohishi-san, Hirata-san, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun (Thu, Fri)
 * Retrieve PEEK piece from BF.
 * Crane SF back in.
 * Suspend BF/IRM/IM/RM/BS.
 * Test SF FR.
 * Calibrate SF LVDT.
 * Install SF cap; route cables.
 * Lift and weigh SF/BF/IRM/IM/RM/BS.
 * Adjust SF ballast.
Mitaka (Fabian, Hirata-san):
 * Fabian did mechanical design:
  * F0 FR
  * Cable clamps for the SR IP base.
  * New SR recoil ballast masses.
  * LBB ballast.
  * Update of BS 3D CAD with the as-built ballast.
 * Hirata-san
  * made and updated inventory list for SR.
  * made order list and asked some quotes.
  * Ordered some parts.
  * Talked with mirapro about SRM optical bench.
  * Made some drawings for SR preparation.
Line 30: Line 30:
==== Plan for week of 9/13 ====
Mark (except Wed), Fabian (except ASJ), Enzo, Ohishi-san, Hirata-san, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun
 * Prepare magnet ring.
 * Bring in PI.
 * Route cables.
 * Suspend SF/..., adjust tilt of SF and total mass.
 * Adjust damper gap.
  
==== Plan for week of 11/13 ====
Line 39: Line 32:
==== Vacation Info ====
Mark: 10/16-24
Enzo and Kozu-kun at Mitaka
 * Servos
 * Diagonalization of OL
 * TFs of BF
 * Documentation

Mark and Fabian at Kamioka.
 * Mark attends commissioning workshop at U Toyama.
 * Support BF characterization work.
 * Prepare for mirror gluing.
 * Prepare for IM assembly.

Hirata-san at Mitaka
 * SR procurement.
 * Get BS prism-gluing jigs reworked for use with PR/SR mirror box.

==== Plan for week of 11/20 ====
 * Holiday on Thu 3/23
 * Fabian at commissioning workshop
 *

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past two weeks report

Kamioka (Mark, Enzo, Kozu-kun):

  • Supported IA team.
  • Replaced LPCDs for IM OSEMs with HPCDs for increased pitch/yaw range.
  • Re-zeroed OL after significant change of beam position during IA.
  • Re-laid-out OL to improve focus of lens to LEN QPD.
  • Offloaded the pitch/yaw actuation at the IM OSEMs using the IM pitch/yaw picos.
  • Enzo worked on design of control loops using the OL.
  • Kozu-kun worked on diagonalizing the OL.

Mitaka (Fabian, Hirata-san):

  • Fabian did mechanical design:
    • F0 FR
    • Cable clamps for the SR IP base.
    • New SR recoil ballast masses.
    • LBB ballast.
    • Update of BS 3D CAD with the as-built ballast.
  • Hirata-san
    • made and updated inventory list for SR.
    • made order list and asked some quotes.
    • Ordered some parts.
    • Talked with mirapro about SRM optical bench.
    • Made some drawings for SR preparation.

Plan for week of 11/13

Enzo and Kozu-kun at Mitaka

  • Servos
  • Diagonalization of OL
  • TFs of BF
  • Documentation

Mark and Fabian at Kamioka.

  • Mark attends commissioning workshop at U Toyama.
  • Support BF characterization work.
  • Prepare for mirror gluing.
  • Prepare for IM assembly.

Hirata-san at Mitaka

  • SR procurement.
  • Get BS prism-gluing jigs reworked for use with PR/SR mirror box.

Plan for week of 11/20

  • Holiday on Thu 3/23
  • Fabian at commissioning workshop