* Type B Past Week Summary * Fabian worked on IM and dummy BS assembly: [[https://photos.google.com/share/AF1QipMNVSExyP3TuyhK4s_VD-ARDlNoCPCf13ZDbHUlwOw14AKgj4XUe0vYg27dQ12icQ?key=SjJ0dXJ1bjN2OGVCN3d6RnoySEtFSjVJUmVwSlZR|photos1]], [[https://photos.google.com/share/AF1QipPQdoB5vYN1VcD32TkA4QSGldODvKRwiT5h-m122ahSpWmFyyrO5MX-9ajL1LeRIg?key=VFFuUVktcEtlMURQUldhZUlRcGFhbzNDeU5IN3NB|photos2]] * A hole in a picomotor holder was too small. ATC staff solved this isue quickly and Hirata-san cleaned the piece. * Some ballast discs for the dummy optic were dirty (seen by visual inspection). Hirata-san cleaned them. * Some arrows were cleaned from the mirrors for the dummy optic. * Hirata-san worked on checking Mirapro's assembly frame design - some minor issues with rail system found. * Hirata-san measured another filter. * Hirata-san washed a large batch of parts. * Mark worked on solutions to allow a [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Subgroups/VIS/TypeB/dummyBS|larger mirror on dummy BS]] * Mark worked on list of items for purchase in FY2016. * Mark worked more on [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235|E1504235 BS Assembly Procedure]] ([[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|Draft on OneDrive]]) |
=== Type B (Mark) === ==== Past week report ==== At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun): * We solved the problem with the OSEMs: cables had been plugged into the confusingly named "PD current monitor" outputs (actually LED current monitors), not the "OSEM outputs". * We solved a problem with the real-time model freezing which turned out to be the IO chassis having lost power. * We took some mass off the IM to allow for the weight of the cables, and readjusted it in pitch and roll. * We aligned the IRM to the IM and set the OSEMs to mid-range. * We added ballast to the BF. * We changed the receptacles for the SF-BF rod. The low receptacle did not fit properly into the BF keystone and Hirata-san had to file it. * We fixed a broken wire on the BF yaw pico, retested the pico and added the BF cap. * We cabled and tested the BF cap picos. * We lifted the BF and weighed and balanced it. * We installed the SF ring and brought in the SF. * We cabled the SF LVDT and did a quick test (not a full calibration). * We replaced non-vacuum compatible cables in the PI, removed various sticky labels and wiped it with ethanol. * We tried to hook the SF-BF rod but found the hole in the hex cable clamp was too small for the 8 mm rod head. We enlarged the hole but then found the PEEK pieces were too loose. We tried using foil, but then managed to lose a PEEK piece into the BF, so we will need to remove the cap of the BF to get it. ==== Plan for week of 8/28 ==== Kamioka: Mark (except Tue), Ohishi-san, Fabian (except Tue), Enzo (except Tue), Hirata-san, Yoshioka-kun (Fri), Kozu-kun (Thu, Fri). * Fix/adjust IRM OSEMs. * Add BF cap; cable and test BF-1 and BF-2 picos. * Lift and weigh BF/IRM/IM/RM/BS; adjust ballast mass. * Crane in SF. * Suspend BF/IRM/IM/RM/BS. ==== Plan for week of 9/4 ==== * Install SF cap; route cables. * Lift and weigh SF/BF/IRM/IM/RM/BS. * Adjust SF ballast. ==== Vacation Info ==== Mark: TBD Mid-Oct |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Past week report
At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun):
- We solved the problem with the OSEMs: cables had been plugged into the confusingly named "PD current monitor" outputs (actually LED current monitors), not the "OSEM outputs".
- We solved a problem with the real-time model freezing which turned out to be the IO chassis having lost power.
- We took some mass off the IM to allow for the weight of the cables, and readjusted it in pitch and roll.
- We aligned the IRM to the IM and set the OSEMs to mid-range.
- We added ballast to the BF.
- We changed the receptacles for the SF-BF rod. The low receptacle did not fit properly into the BF keystone and Hirata-san had to file it.
- We fixed a broken wire on the BF yaw pico, retested the pico and added the BF cap.
- We cabled and tested the BF cap picos.
- We lifted the BF and weighed and balanced it.
- We installed the SF ring and brought in the SF.
- We cabled the SF LVDT and did a quick test (not a full calibration).
- We replaced non-vacuum compatible cables in the PI, removed various sticky labels and wiped it with ethanol.
- We tried to hook the SF-BF rod but found the hole in the hex cable clamp was too small for the 8 mm rod head. We enlarged the hole but then found the PEEK pieces were too loose. We tried using foil, but then managed to lose a PEEK piece into the BF, so we will need to remove the cap of the BF to get it.
Plan for week of 8/28
Kamioka: Mark (except Tue), Ohishi-san, Fabian (except Tue), Enzo (except Tue), Hirata-san, Yoshioka-kun (Fri), Kozu-kun (Thu, Fri).
- Fix/adjust IRM OSEMs.
- Add BF cap; cable and test BF-1 and BF-2 picos.
- Lift and weigh BF/IRM/IM/RM/BS; adjust ballast mass.
- Crane in SF.
- Suspend BF/IRM/IM/RM/BS.
Plan for week of 9/4
- Install SF cap; route cables.
- Lift and weigh SF/BF/IRM/IM/RM/BS.
- Adjust SF ballast.
Vacation Info
Mark: TBD Mid-Oct