Differences between revisions 19 and 212 (spanning 193 versions)
Revision 19 as of 2016-06-03 13:40:03
Size: 1472
Editor: MarkBarton
Comment:
Revision 212 as of 2017-12-15 15:23:00
Size: 2929
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 5: Line 5:
 * Type B Past Week Summary
  * Fabian worked on IM and dummy BS assembly: [[https://photos.google.com/share/AF1QipMNVSExyP3TuyhK4s_VD-ARDlNoCPCf13ZDbHUlwOw14AKgj4XUe0vYg27dQ12icQ?key=SjJ0dXJ1bjN2OGVCN3d6RnoySEtFSjVJUmVwSlZR|photos1]], [[https://photos.google.com/share/AF1QipPQdoB5vYN1VcD32TkA4QSGldODvKRwiT5h-m122ahSpWmFyyrO5MX-9ajL1LeRIg?key=VFFuUVktcEtlMURQUldhZUlRcGFhbzNDeU5IN3NB|photos2]]
   * A hole in a picomotor holder was too small. ATC staff solved this isue quickly and Hirata-san cleaned the piece.
   * Some ballast discs for the dummy optic were dirty (seen by visual inspection). Hirata-san cleaned them.
   * Some arrows were cleaned from the mirrors for the dummy optic.
  * Hirata-san worked on checking Mirapro's assembly frame design - some minor issues with rail system found.
  * Hirata-san measured another filter.
  * Hirata-san washed a large batch of parts.
  * Mark worked on solutions to allow a [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Subgroups/VIS/TypeB/dummyBS|larger mirror on dummy BS]]
  * Mark worked on list of items for purchase in FY2016.
  * Mark worked more on [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235|E1504235 BS Assembly Procedure]] ([[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|Draft on OneDrive]])
=== Type B (Mark) ===
==== Past week report ====

 * Mark finished the OL calibration/diagonalization calculation and wrote it up as klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=3835|3835]] and [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7205| T1707205-v4]].
 * We glued the prisms and magnets on the SR2.
 * We got Miyo-kun to set up the SR2-IM pico driver and tested it and the picos that will be used in the IM.
 * We weighed the BF for the SR2.
 * Enzo put DIO cards in the IO chassis and cabled them to the coil drivers.
 * Enzo found more of the in-vacuum cables that will be needed for SR2. Only a few remain to be found.
 * Enzo and Shoda-san installed the vacuum-feedthroughs on the assembly frame and routed many of the in-air cables.
 * Hirata-san and Mark moved the PR/SR trolley system from SR3 to SR2, reconfigured the top of the assembly frame and checked the crossbar heights. (Everything was quite close to the drawing, but a few small adjustments up/down will be required.)
 * Fabian found an issue with the IM: we have two of the upper movable masses and no lower ones. Probably one of the PRs has been built with two lower masses. Unfortunately an upper mass has an extra hole in an inconvenient place and can't be used as a lower mass. Hirata-san ordered a suitable plug part from Misumi, and Fabian washed it and glued it in with EP30.
 * Fabian assembled the RM and test-assembled the IRM. (The IRM will have to be partly disassembled during installation.)
 * Shoda-san and Enzo got all the control loops working on the BS, and worked with Izumi-san to steer the beam down the Y-arm. They found the passive damping was not working very well, even after correcting a 1.5 mm height error in F0. We may need to lower the damper ring.
 * Shoda-san created a BS Guardian.
 * We got Yamamoto-san to connect up the SR2 rack and create an SR2 real-time model.

==== Plan for week of 12/18 ====
 * Shoda-san vacation
 * Mark, Fabian, Enzo, Kozu-kun at Kamioka Mon-Wed.
 * Find plumb bob.
 * Assembly frame alignment and optical table centering. (Mark and Hirata)
 * Finish IM assembly and pico test. (Fabian and Enzo)
 * Do inventory of ballast masses. (Fabian)

==== Plan for week of 12/25 ====
 * Mark, Enzo, Fabian vacation
 * Shoda-san, Kozu-kun, Hirata-san at Kamioka Mon-Thu.
 * Install IM ring interface blocks and IM ring.
 * Install new jack receptacles (in SR3 area, second floor) on load gauge adapter (SR2 area, second floor). (Hirata-san)
 * OL setup.

==== Plan for week of 1/9 ====
 * Mark, Fabian, Enzo, Shoda-san at Kamioka Tue-Fri.
 * Hang SR and RM.

==== Vacation Info ====
 * Mark 12/22-1/3
 * Enzo, 12/21-12/27 (but ''not'' 12/28)
 * Fabian 12/22-1/5
 * Hirata-san 12/21-22 (conference)
 * Shoda-san 12/18-21
  

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

  • Mark finished the OL calibration/diagonalization calculation and wrote it up as klog 3835 and T1707205-v4.

  • We glued the prisms and magnets on the SR2.
  • We got Miyo-kun to set up the SR2-IM pico driver and tested it and the picos that will be used in the IM.
  • We weighed the BF for the SR2.
  • Enzo put DIO cards in the IO chassis and cabled them to the coil drivers.
  • Enzo found more of the in-vacuum cables that will be needed for SR2. Only a few remain to be found.
  • Enzo and Shoda-san installed the vacuum-feedthroughs on the assembly frame and routed many of the in-air cables.
  • Hirata-san and Mark moved the PR/SR trolley system from SR3 to SR2, reconfigured the top of the assembly frame and checked the crossbar heights. (Everything was quite close to the drawing, but a few small adjustments up/down will be required.)
  • Fabian found an issue with the IM: we have two of the upper movable masses and no lower ones. Probably one of the PRs has been built with two lower masses. Unfortunately an upper mass has an extra hole in an inconvenient place and can't be used as a lower mass. Hirata-san ordered a suitable plug part from Misumi, and Fabian washed it and glued it in with EP30.
  • Fabian assembled the RM and test-assembled the IRM. (The IRM will have to be partly disassembled during installation.)
  • Shoda-san and Enzo got all the control loops working on the BS, and worked with Izumi-san to steer the beam down the Y-arm. They found the passive damping was not working very well, even after correcting a 1.5 mm height error in F0. We may need to lower the damper ring.
  • Shoda-san created a BS Guardian.
  • We got Yamamoto-san to connect up the SR2 rack and create an SR2 real-time model.

Plan for week of 12/18

  • Shoda-san vacation
  • Mark, Fabian, Enzo, Kozu-kun at Kamioka Mon-Wed.
  • Find plumb bob.
  • Assembly frame alignment and optical table centering. (Mark and Hirata)
  • Finish IM assembly and pico test. (Fabian and Enzo)
  • Do inventory of ballast masses. (Fabian)

Plan for week of 12/25

  • Mark, Enzo, Fabian vacation
  • Shoda-san, Kozu-kun, Hirata-san at Kamioka Mon-Thu.
  • Install IM ring interface blocks and IM ring.
  • Install new jack receptacles (in SR3 area, second floor) on load gauge adapter (SR2 area, second floor). (Hirata-san)
  • OL setup.

Plan for week of 1/9

  • Mark, Fabian, Enzo, Shoda-san at Kamioka Tue-Fri.
  • Hang SR and RM.

Vacation Info

  • Mark 12/22-1/3
  • Enzo, 12/21-12/27 (but not 12/28)

  • Fabian 12/22-1/5
  • Hirata-san 12/21-22 (conference)
  • Shoda-san 12/18-21

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)