Size: 3359
Comment:
|
Size: 1581
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 6: | Line 6: |
==== Past week report ==== At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun): * We disconnected the SF/... section and reinstalled the F0-SF rod with the hex cable clamp attached. * We debugged an issue with the actuation (the real-time model needed rebooting). * We routed all the SF/... cables up to the bottom of the PI, and then to the feedthroughs. * We unlocked the F0 keystone and experimented to find the amount of mass needed on the SF (≈845 g). * We attached the SF trim mass, adjusting it laterally so that the SF was level in pitch and roll. * We corrected some errors on the MEDM screens (some broken links and Take/Restore Safe.snap buttons). * We cabled all the PI items through to the rack and did very basic testing. * We disconnected the security structure from the assembly frame and adjusted the PI till the SS was vertical. * We unlocked the IP and adjusted the PI jacks and FRs till the IP was centered. * We passed the halves of the LBB Cu damping ring (less the Cu) into the chamber and joined them. * We put the magnets on the LBB damper ring using the template. * We locked various combinations of keystones and measured the vertical resonance frequencies of the unlocked filters. * We spent time on getting the geophones working. The original descrambler adapters had gone missing, so Enzo created three new ones. We borrowed a cable to replace one that had broken. The geophone distributor (S1402167) failed (no power on the negative rail), and a replacement borrowed from SR3 (S1605513) kept switching off. |
==== Past two weeks report ==== Kamioka (Mark, Enzo, Kozu-kun): * Supported IA team. * Replaced LPCDs for IM OSEMs with HPCDs for increased pitch/yaw range. * Re-zeroed OL after significant change of beam position during IA. * Re-laid-out OL to improve focus of lens to LEN QPD. * Offloaded the pitch/yaw actuation at the IM OSEMs using the IM pitch/yaw picos. * Enzo worked on design of control loops using the OL. * Kozu-kun worked on diagonalizing the OL. |
Line 22: | Line 16: |
==== Plan for week of 9/19 ==== No work Mon 9/18 (敬老の日)<<BR>> Mark, Fabian, Enzo, Ohishi-san, Hirata-san, Yoshioka-kun (Tue, Wed, Thu, Fri), Kozu-kun * Double check BS pitch with OL. * Adjust SF damper ring to correct gap. * Install lock nuts on F0 GAS FR at TBD positions. * Lock BF and F0 keystones (but ''not'' SF keystone). * Lock RM to BS and IRM to IM. * Lock RM, IRM and BF (but not SF) to security structure. * Lock IP. * Remove F0 keystone top plate (including yaw stepper) and immobilize SF/... in yaw. * Attach lifting fixture. * Remove BF- and SF-level crossbars. * Remove geophones for craning. * Disconnect in-vacuum cables from feedthrough and coil neatly for craning. * Attach lifting plates. * Attach Cu segments to LBB damper ring (needs Cu segments and BUMAX countersunk screws, expected 9/20). * Pass halves of LBB magnet ring into tank, join, and make sandwich for craning. * Crane tank lid off. * Crane LBB damper rings to top of tank and suspend. * Crane suspension out of assembly frame. * Attach LBB upper rods to LBB blade tips and rotate suspension 45° clockwise. * Crane suspension into tank and connect upper rods to LBB Cu ring. * Unclamp LBB ring "sandwich" so LBB Cu ring is suspended on upper rods. * Install LBB lower rods and hook LBB. * Measure required ballast for LBB. * Unlock suspension and readjust. * Move in-air cabling and feedthroughs and reconnect in-vacuum cables (through Cu O-rings). |
Mitaka (Fabian, Hirata-san): * Fabian did mechanical design: * F0 FR * Cable clamps for the SR IP base. * New SR recoil ballast masses. * LBB ballast. * Update of BS 3D CAD with the as-built ballast. * Hirata-san * made and updated inventory list for SR. * made order list and asked some quotes. * Ordered some parts. * Talked with mirapro about SRM optical bench. * Made some drawings for SR preparation. |
Line 51: | Line 30: |
==== Plan for week of 9/25 ==== TBD |
==== Plan for week of 11/13 ==== |
Line 54: | Line 32: |
* Debug cabling. * Run TFs. * Install LSOL? |
Enzo and Kozu-kun at Mitaka * Servos * Diagonalization of OL * TFs of BF * Documentation |
Line 58: | Line 38: |
==== Vacation Info ==== Mark: 10/16-24 |
Mark and Fabian at Kamioka. * Mark attends commissioning workshop at U Toyama. * Support BF characterization work. * Prepare for mirror gluing. * Prepare for IM assembly. Hirata-san at Mitaka * SR procurement. * Get BS prism-gluing jigs reworked for use with PR/SR mirror box. ==== Plan for week of 11/20 ==== * Holiday on Thu 3/23 * Fabian at commissioning workshop * |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Past two weeks report
Kamioka (Mark, Enzo, Kozu-kun):
- Supported IA team.
- Replaced LPCDs for IM OSEMs with HPCDs for increased pitch/yaw range.
- Re-zeroed OL after significant change of beam position during IA.
- Re-laid-out OL to improve focus of lens to LEN QPD.
- Offloaded the pitch/yaw actuation at the IM OSEMs using the IM pitch/yaw picos.
- Enzo worked on design of control loops using the OL.
- Kozu-kun worked on diagonalizing the OL.
Mitaka (Fabian, Hirata-san):
- Fabian did mechanical design:
- F0 FR
- Cable clamps for the SR IP base.
- New SR recoil ballast masses.
- LBB ballast.
- Update of BS 3D CAD with the as-built ballast.
- Hirata-san
- made and updated inventory list for SR.
- made order list and asked some quotes.
- Ordered some parts.
- Talked with mirapro about SRM optical bench.
- Made some drawings for SR preparation.
Plan for week of 11/13
Enzo and Kozu-kun at Mitaka
- Servos
- Diagonalization of OL
- TFs of BF
- Documentation
Mark and Fabian at Kamioka.
- Mark attends commissioning workshop at U Toyama.
- Support BF characterization work.
- Prepare for mirror gluing.
- Prepare for IM assembly.
Hirata-san at Mitaka
- SR procurement.
- Get BS prism-gluing jigs reworked for use with PR/SR mirror box.
Plan for week of 11/20
- Holiday on Thu 3/23
- Fabian at commissioning workshop