==== Past week report ====
At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun):
 * We disconnected the SF/... section and reinstalled the F0-SF rod with the hex cable clamp attached.
 * We debugged an issue with the actuation (the real-time model needed rebooting).
 * We routed all the SF/... cables up to the bottom of the PI, and then to the feedthroughs.
 * We unlocked the F0 keystone and experimented to find the amount of mass needed on the SF (≈845 g).
 * We attached the SF trim mass, adjusting it laterally so that the SF was level in pitch and roll.
 * We corrected some errors on the MEDM screens (some broken links and Take/Restore Safe.snap buttons).
 * We cabled all the PI items through to the rack and did very basic testing.
 * We disconnected the security structure from the assembly frame and adjusted the PI till the SS was vertical.
 * We unlocked the IP and adjusted the PI jacks and FRs till the IP was centered.
 * We passed the halves of the LBB Cu damping ring (less the Cu) into the chamber and joined them.
 * We put the magnets on the LBB damper ring using the template.
 * We locked various combinations of keystones and measured the vertical resonance frequencies of the unlocked filters.
 * We spent time on getting the geophones working. The original descrambler adapters had gone missing, so Enzo created three new ones. We borrowed a cable to replace one that had broken. The geophone distributor (S1402167) failed (no power on the negative rail), and a replacement borrowed from SR3 (S1605513) kept switching off.
==== Report for week of 1/29 ====
 * Mark made two sets of in-air pico splitter cables (each with a triple for IM and a double for BF) for SR2 and SR3.
 * Fabian, Hirata-san and Kozu-kun worked on cabling and testing the IM pitch/roll/yaw picos, the BF FR and the BF LVDT. The LVDT connections were initially unreliable and Hirata-san had to redo the pins on the coil wires.
 * Fabian installed ballast masses in the BF.
 * Mark worked on schedule.
 * Mark did inventory of the stepper motor drivers (many were not accounted for on the wiki and/or JGWDoc and one is missing) and reserved two for SR3.
Line 22: Line 13:
==== Plan for week of 9/19 ====
No work Mon 9/18 (敬老の日)<<BR>>
Mark, Fabian, Enzo, Ohishi-san, Hirata-san, Yoshioka-kun (Tue, Wed, Thu, Fri), Kozu-kun
 * Double check BS pitch with OL.
 * Adjust SF damper ring to correct gap.
 * Install lock nuts on F0 GAS FR at TBD positions.
 * Lock BF and F0 keystones (but ''not'' SF keystone).
 * Lock RM to BS and IRM to IM.
 * Lock RM, IRM and BF (but not SF) to security structure.
 * Lock IP.
 * Remove F0 keystone top plate (including yaw stepper) and immobilize SF/... in yaw.
 * Attach lifting fixture.
 * Remove BF- and SF-level crossbars.
 * Remove geophones for craning.
 * Disconnect in-vacuum cables from feedthrough and coil neatly for craning.
 * Attach lifting plates.
 * Attach Cu segments to LBB damper ring (needs Cu segments and BUMAX countersunk screws, expected 9/20).
 * Pass halves of LBB magnet ring into tank, join, and make sandwich for craning.
 * Crane tank lid off.
 * Crane LBB damper rings to top of tank and suspend.
 * Crane suspension out of assembly frame.
 * Attach LBB upper rods to LBB blade tips and rotate suspension 45° clockwise.
 * Crane suspension into tank and connect upper rods to LBB Cu ring.
 * Unclamp LBB ring "sandwich" so LBB Cu ring is suspended on upper rods.
 * Install LBB lower rods and hook LBB.
 * Measure required ballast for LBB.
 * Unlock suspension and readjust.
 * Move in-air cabling and feedthroughs and reconnect in-vacuum cables (through Cu O-rings).
==== Plan for week of 2/13 ====
 * No work Monday (建国記念の日の振替休日)
 * Enzo on vacation
 * Hirata-san at Mitaka Tue, Wed (to receive and wash parts).
 * Shoda-san at Mitaka
 * All others at Kamioka.
 * -
 * Build IRM around IM.
 * Cable/test/adjust IM OSEMs.
 * Do TFs from IM OSEMs to IM OSEMs, OL pitch/yaw.
Line 51: Line 24:
==== Plan for week of 9/25 ====
TBD
==== Plan for week of 2/19 ====
 * Enzo back from Tuesday.
 * Shoda-san at Mitaka
 * All others at Kamioka.
 * -
 * Lift BF/... section and check total mass and balance.
 * Cable and test BF picos.
 * Add section of SS up to SF ring.
 * Bring in SF.
 * Hook BF/... section.
 * Route cables up to under SF.
 * Check/adjust total mass of BF/... section.
Line 54: Line 37:
 * Debug cabling.
 * Run TFs.
 * Install LSOL?
==== Plan for week of 2/26 ====
 * Add Cu segments to SF cap.
 * Lift SF/... section and check total mass and balance.
Line 59: Line 42:
Mark: 10/16-24  * Enzo 1/30-2/19.
 * Fabian 4/2-4/27 vacation (then gone).

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 1/29

  • Mark made two sets of in-air pico splitter cables (each with a triple for IM and a double for BF) for SR2 and SR3.
  • Fabian, Hirata-san and Kozu-kun worked on cabling and testing the IM pitch/roll/yaw picos, the BF FR and the BF LVDT. The LVDT connections were initially unreliable and Hirata-san had to redo the pins on the coil wires.
  • Fabian installed ballast masses in the BF.
  • Mark worked on schedule.
  • Mark did inventory of the stepper motor drivers (many were not accounted for on the wiki and/or JGWDoc and one is missing) and reserved two for SR3.

Plan for week of 2/13

  • No work Monday (建国記念の日の振替休日)
  • Enzo on vacation
  • Hirata-san at Mitaka Tue, Wed (to receive and wash parts).
  • Shoda-san at Mitaka
  • All others at Kamioka.
  • -
  • Build IRM around IM.
  • Cable/test/adjust IM OSEMs.
  • Do TFs from IM OSEMs to IM OSEMs, OL pitch/yaw.

Plan for week of 2/19

  • Enzo back from Tuesday.
  • Shoda-san at Mitaka
  • All others at Kamioka.
  • -
  • Lift BF/... section and check total mass and balance.
  • Cable and test BF picos.
  • Add section of SS up to SF ring.
  • Bring in SF.
  • Hook BF/... section.
  • Route cables up to under SF.
  • Check/adjust total mass of BF/... section.

Plan for week of 2/26

  • Add Cu segments to SF cap.
  • Lift SF/... section and check total mass and balance.

Vacation Info

  • Enzo 1/30-2/19.
  • Fabian 4/2-4/27 vacation (then gone).