At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun):
 * We put lock nuts on the F0 FR and calibrated the F0 LVDT against FR position and keystone height.
 * Enzo traced the issue with the geophones to a specific cable.
 * We measured the BF and F0 GAS resonant frequencies.
 * We adjusted the spacing of the SR damper.
 * We double-checked the BS pitch with the OL.
 * We debugged the PI yaw mechanism. We managed to get the return spring properly adjusted, but the stepper motor tends to jam because of the strange design.
 * '''We prepared the suspension for lifting and craned it into the tank.'''
 * Hirata-san fixed an issue with one of the nailheads on the LBB intermediate ring support rods not properly seating, by removing the rod and reinstalling it upside down (with the problem nailhead in a less critical position).
 * Enzo and team moved all the in-air cables from the assembly frame to the tank.
 * Fabian and Ohishi-san unlocked the bottom section of the suspension and got it hanging freely.
 
==== Plan for week of 9/25 ====
Mark, Fabian, Enzo (Mon, Tue), Ohishi-san (Tue, Fri), Hirata-san, Yoshioka-kun (Tue, Wed, Fri), Kozu-kun
 * Finish moving in-air cabling and feedthroughs and reconnect in-vacuum cables (through Cu O-rings).
 * Unlock rest of suspension and readjust.
 * Debug electronics.
 * Unclamp LBB ring "sandwich" so LBB Cu ring is suspended on upper rods.
 * Install LBB lower rods and hook LBB.
 * Adjust LBB damper Cu-magnet gap.
 * Measure required ballast for LBB.
 * Remove First Contact, try OL.
 * Prepare for SR2 work.
Line 31: Line 8:
==== Plan for week of 10/2 ====
Kamioka: Mark, Enzo, Fabian, Ohishi-san.
 * TFs etc.
Mitaka: Hirata-san?
 * SF design/purchasing.
 * Mark analyzed the QPD data from Friday 12/1 and derived matrices to diagonalize the QPD, and calibrate output in µrad. In the process an error in the IM OSEM diagonalization was discovered: the P and Y gains were low by a factor 2.
 * Mark re-zeroed the QPD after noting the micrometer readings so we can do TFs over the weekend.
 * We prepared for the SR2 gluing:
  * We aligned the SR2 in the box with the wedge on the correct side.
  * We checked that the remachined BS prism holders fit on the PR2 mirror box.
  * We checked that with Tatsumi-san's support ring, the prisms would go on at the right height.
  * We checked the new magnet jigs.
 * We glued ferromagnetic disks in a large number of IM flag tips and flag bases, and in the SR magnet jigs.
 * We also glued SR magnets in the magnet bases.

==== Plan for week of 12/11
 * Mark, Fabian, Enzo, Kozu-kun (Mon-Thu only), Hirata-san, Shoda-san at Kamioka.
 * Mirror gluing.
 * IM assembly and pico test.
 * Assembly frame alignment and optical table centering.
 * Move trolley system from SR3.
 * OL setup.

==== Plan for week of 12/18 ====
 * Shoda-san vacation
 * Mark, Fabian, Enzo, Kozu-kun at Kamioka Mon-Wed.
Line 38: Line 31:
Mark: 10/16-24
Enzo: 9/27-29
 * Mark 12/22-1/3
 * Enzo, 12/21-12/27 (but ''not'' 12/28)
 * Fabian 12/22-1/5
 * Hirata-san 12/21-22 (conference)
 * Shoda-san 12/18-21
  

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

  • Mark analyzed the QPD data from Friday 12/1 and derived matrices to diagonalize the QPD, and calibrate output in µrad. In the process an error in the IM OSEM diagonalization was discovered: the P and Y gains were low by a factor 2.
  • Mark re-zeroed the QPD after noting the micrometer readings so we can do TFs over the weekend.
  • We prepared for the SR2 gluing:
    • We aligned the SR2 in the box with the wedge on the correct side.
    • We checked that the remachined BS prism holders fit on the PR2 mirror box.
    • We checked that with Tatsumi-san's support ring, the prisms would go on at the right height.
    • We checked the new magnet jigs.
  • We glued ferromagnetic disks in a large number of IM flag tips and flag bases, and in the SR magnet jigs.
  • We also glued SR magnets in the magnet bases.

==== Plan for week of 12/11

  • Mark, Fabian, Enzo, Kozu-kun (Mon-Thu only), Hirata-san, Shoda-san at Kamioka.
  • Mirror gluing.
  • IM assembly and pico test.
  • Assembly frame alignment and optical table centering.
  • Move trolley system from SR3.
  • OL setup.

Plan for week of 12/18

  • Shoda-san vacation
  • Mark, Fabian, Enzo, Kozu-kun at Kamioka Mon-Wed.

Vacation Info

  • Mark 12/22-1/3
  • Enzo, 12/21-12/27 (but not 12/28)

  • Fabian 12/22-1/5
  • Hirata-san 12/21-22 (conference)
  • Shoda-san 12/18-21