* Type B Past Week Summary * Fabian worked on IM and dummy BS assembly: [[https://photos.google.com/share/AF1QipMNVSExyP3TuyhK4s_VD-ARDlNoCPCf13ZDbHUlwOw14AKgj4XUe0vYg27dQ12icQ?key=SjJ0dXJ1bjN2OGVCN3d6RnoySEtFSjVJUmVwSlZR|photos1]], [[https://photos.google.com/share/AF1QipPQdoB5vYN1VcD32TkA4QSGldODvKRwiT5h-m122ahSpWmFyyrO5MX-9ajL1LeRIg?key=VFFuUVktcEtlMURQUldhZUlRcGFhbzNDeU5IN3NB|photos2]] * A hole in a picomotor holder was too small. ATC staff solved this isue quickly and Hirata-san cleaned the piece. * Some ballast discs for the dummy optic were dirty (seen by visual inspection). Hirata-san cleaned them. * Some arrows were cleaned from the mirrors for the dummy optic. * Hirata-san worked on checking Mirapro's assembly frame design - some minor issues with rail system found. * Hirata-san measured another filter. * Hirata-san washed a large batch of parts. * All parts for gluing of dummy BS are in hand. We arranged with Tatsumi-san to glue magnets at Mitaka on 6/6, glue flags at Kashiwa on 6/8, and inspect bonds and bring dummy BS back to Mitaka 6/13. * Mark worked on solutions to allow a [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Subgroups/VIS/TypeB/dummyBS|larger mirror on dummy BS]]. After discussions with Simon and Akutsu-san we decided to go with a stainless steel plate solution. The gluing can go ahead and we can attach the plates later. * Mark worked on list of items for purchase in FY2016. * Mark worked more on [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235|E1504235 BS Assembly Procedure]] ([[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|Draft on OneDrive]]) |
=== Type B (Mark) === ==== Report for week of 1/29 ==== * We moved the top filter intended for SR2 (#1) into the SR3 cleanbooth. * Unfortunately we noticed one of the blades had many small X-shaped stress fractures on the top surface (klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=4058|4058]]). * We moved the top filter entered for SR3 (#3) into the SRM cleanbooth and inspected the blades. Two had one smallish stress fracture each and one had a huge fracture and looks close to failing (klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=4061|4061]]). * We referred the BS OL. * We removed the BS tank lid and inspected the BS top filter blades. They seemed fine. * Hirata-san received and washed some ferromagnetic disks for IM flags and other small parts. * Hirata-san moved the BF with the tilted keystone (#1) out of the cleanbooth in preparation for rebuilding. * Hirata-san * Fabian measured the gain of the ADC system (homework from the Commissioning Workshop). ==== Plan for week of 1/29 ==== * Enzo at Mitaka 1/29 and most of 1/30, then vacation. * Kozu-kun away. * All others at Kamioka. * Make in-air pico adapter cables. * Test IM picos and BF yaw pico. * Test FR. * Calibrate LVDT. * Get screws for ballast mass from Takahashi-san. * Install ballast mass in BF. * Set up for F0 test. * Lower IM crossbars in SR3 assembly frame. * Open curtain on SR3 crane slot. * Set up dummy load (weight carrier, rods etc). * Do F0 test. * Bring in F0. * Hook up dummy load. * Adjust dummy load. ==== Plan for week of 2/5 ==== * Enzo on vacation; all others at Kamioka. * Build IRM around IM. * Cable/test/adjust IM OSEMs. * Time permitting, do TFs from IM OSEMs to themselves and to optical sensor. ==== Plan for week of 2/12 ==== * Enzo on vacation; all others at Kamioka. ==== Vacation Info ==== * Enzo 1/30-2/19 (at Mitaka 1/29, part of 1/30) * Kozu-kun 1/29-2/2 |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 1/29
- We moved the top filter intended for SR2 (#1) into the SR3 cleanbooth.
Unfortunately we noticed one of the blades had many small X-shaped stress fractures on the top surface (klog 4058).
We moved the top filter entered for SR3 (#3) into the SRM cleanbooth and inspected the blades. Two had one smallish stress fracture each and one had a huge fracture and looks close to failing (klog 4061).
- We referred the BS OL.
- We removed the BS tank lid and inspected the BS top filter blades. They seemed fine.
- Hirata-san received and washed some ferromagnetic disks for IM flags and other small parts.
- Hirata-san moved the BF with the tilted keystone (#1) out of the cleanbooth in preparation for rebuilding.
- Hirata-san
- Fabian measured the gain of the ADC system (homework from the Commissioning Workshop).
Plan for week of 1/29
- Enzo at Mitaka 1/29 and most of 1/30, then vacation.
- Kozu-kun away.
- All others at Kamioka.
- Make in-air pico adapter cables.
- Test IM picos and BF yaw pico.
- Test FR.
- Calibrate LVDT.
- Get screws for ballast mass from Takahashi-san.
- Install ballast mass in BF.
- Set up for F0 test.
- Lower IM crossbars in SR3 assembly frame.
- Open curtain on SR3 crane slot.
- Set up dummy load (weight carrier, rods etc).
- Do F0 test.
- Bring in F0.
- Hook up dummy load.
- Adjust dummy load.
Plan for week of 2/5
- Enzo on vacation; all others at Kamioka.
- Build IRM around IM.
- Cable/test/adjust IM OSEMs.
- Time permitting, do TFs from IM OSEMs to themselves and to optical sensor.
Plan for week of 2/12
- Enzo on vacation; all others at Kamioka.
Vacation Info
- Enzo 1/30-2/19 (at Mitaka 1/29, part of 1/30)