==== Past week report ====
At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Kozu-kun):
 * We couldn't account for a bubble level, so we removed a service port cover, searched again on top of the BF and found it.
 * We put the table KOACH filters on the table. Ohishi-san then removed the FC in two stages (AR side on Tue, HR side on Fri).
 * Ohishi-san measured the height of the SS and optic relative to the tank and found the optic was 3 mm low but the SS was 2 mm high. According to the GAS LVDTs, the suspension had not sagged but was 1.7 mm high.
 * Therefore we raised the suspension by 9 quarter-turns of the tank jacks (4.5 mm) so that the optic would be in the right position after (future) downward adjustment of the GAS filters.
 * We put the GAS LVDT calibration data as offsets and gains in the LVDTINF filters so the output would be height in µm relative to nominal.
 * We calibrated the IP LVDTs. We had worked around a mechanical interference due to the poor design of the old LVDTs by setting them to be 4 mm off-center with the IP locked centrally, but we discovered this was overkill and we have lost some linear range on the LVDT sensor in the opposite direction. If we have time we may move the LVDT bases 1-2 mm to a compromise position.
 * We worked with Simon to get the OL aligned and to learn the adjustment procedure.
 * Mark updated Sekiguchi-san's SUMCON to allow for comments to be entered next to all values (75% finished).
 * Kozu-kun worked on deriving the diagonalization matrices for the IP FRs.
==== Report for week of 1/15 ====
 * We set up the QPD for the OL, initialized the OL and TM sections of the RTM, and did TFs from the TM OSEMs to the OL.
 * Initially we had no coherence, but we debugged issues with the watchdog, LPCD, and DAC board and then got good TFs.
 * We lifted the IM/RM/SR with the load gauge adapter and checked the weight, which was close to the mass budget.
 * We installed the section of the AF above the IM, and the BF cross bars and jacks, and craned in the BF.
 * We installed the BF-IRM rods, IRM, BF-IM rod, flying saucer and the cable clamps on the bottom of the BF.
 * We hooked the IM section, but found it was heavy by several hundred grams. We also noticed the BF keystone had a noticeable tilt of about 1.2 mm (high on the +X side).
 * We removed 738 g of trim mass and found that load rose and sat about 2 mm high. So the discrepancy is of order 500-600 g.
 * Shoda-san, Enzo and Kozu-kun made and characterized a batch of OSEMs.
 * Hirata-san finished drawings for the improved BS PI yaw/vertical adjustment, placed orders for damping ring receptacles and other items, and prepared the second SR BF in case we needed to swap it in.
Line 18: Line 17:
At Mitaka (Hirata-san):
 * Hirata-san met with manufacturers and requested quotes.
 * Hirata-san made many assembly drawings for sections of the SR.
 * Hirata-san worked on compiling the SR inventory.
==== Plan for week of 1/22 ====
 * Fix or swap BF.
 * Route selected cables to flange.
 * Test IM picos and BF yaw pico.
Line 23: Line 22:
==== Plan for week of 10/16 ====
Kamioka: all but Mark
 * Remove sticker residue and permanent marker writing on PI.
 * Fix broken and unreliable connections on IP LVDTs.
 * Wipe any rust from around IP LVDTs.
 * (If Enzo thinks it necessary and there's time) adjust IP LVDT mechanical offsets to maximize usable range and recalibrate.
 * Add IP LVDT gains and offsets to IP_LVDTINF filter blocks.
 * Calibrate IP LVDT actuation against IP LVDT sensing.
 * Install damping filters for IP LVDTs.
 * Adjust gains and debug damping for IM OSEMs and GAS LVDTs.
 * Modify IP LVDT damping filters to include set point.
 * Install and debug IP LVDT and geophone diagonalization matrices.
 * (Time permitting) Try adding mass to IP.
 * Work with alignment team.
 * Work with Mirapro on SR LBB and tank installation (Hirata-san, from Wed)
 * Work with Miyo-kun to get user interface for stepper motors.
 * Calibrate IP FR actuation against IP LVDT sensing.
 * SR procurement.
==== Plan for week of 1/29 ====
 * Enzo at Mitaka 1/29 and most of 1/30, then vacation.
 * Kozu-kun away.
 * All others at Kamioka.
 * Build IRM around IM.
 * Cable/test/adjust IM OSEMs.
 * Time permitting, do TFs from IM OSEMs to themselves and to optical sensor.
Line 43: Line 31:
Mark: 10/16-24  * Enzo 1/30-2/19 (at Mitaka 1/29, part of 1/30)
 * Kozu-kun 1/29-2/2

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 1/15

  • We set up the QPD for the OL, initialized the OL and TM sections of the RTM, and did TFs from the TM OSEMs to the OL.
  • Initially we had no coherence, but we debugged issues with the watchdog, LPCD, and DAC board and then got good TFs.
  • We lifted the IM/RM/SR with the load gauge adapter and checked the weight, which was close to the mass budget.
  • We installed the section of the AF above the IM, and the BF cross bars and jacks, and craned in the BF.
  • We installed the BF-IRM rods, IRM, BF-IM rod, flying saucer and the cable clamps on the bottom of the BF.
  • We hooked the IM section, but found it was heavy by several hundred grams. We also noticed the BF keystone had a noticeable tilt of about 1.2 mm (high on the +X side).
  • We removed 738 g of trim mass and found that load rose and sat about 2 mm high. So the discrepancy is of order 500-600 g.
  • Shoda-san, Enzo and Kozu-kun made and characterized a batch of OSEMs.
  • Hirata-san finished drawings for the improved BS PI yaw/vertical adjustment, placed orders for damping ring receptacles and other items, and prepared the second SR BF in case we needed to swap it in.

Plan for week of 1/22

  • Fix or swap BF.
  • Route selected cables to flange.
  • Test IM picos and BF yaw pico.

Plan for week of 1/29

  • Enzo at Mitaka 1/29 and most of 1/30, then vacation.
  • Kozu-kun away.
  • All others at Kamioka.
  • Build IRM around IM.
  • Cable/test/adjust IM OSEMs.
  • Time permitting, do TFs from IM OSEMs to themselves and to optical sensor.

Vacation Info

  • Enzo 1/30-2/19 (at Mitaka 1/29, part of 1/30)
  • Kozu-kun 1/29-2/2