Line 8: Line 8:
 * Mark worked on SR2 planning.
 * Mark thought through what would be required to swap an optic (e.g., SRM) in situ (JGW-T1707436).
 * Hirata-san tried removing disks from IM flags (so we could reuse them in flag bases and make a complete set for SR2) but only got 1 of 4 out.
 * Hirata-san ordered more disks for IM flags.
 * Hirata-san asked for quotes on SF LBB blades.
 * Hirata-san got a reduced quote for the LBB damper rings.
 * Hirata-san received and cleaned suspension wires for the SR.
 * Fabian worked on the SR mass budget.
 * Fabian worked out the COM of the SR2 optic, and Mark used it to derive the proper prism positions.
 * Enzo and Kozu-kun worked on control filter design and installation.
 * Mark analyzed the QPD data from Friday 12/1 and derived matrices to diagonalize the QPD, and calibrate output in µrad. In the process an error in the IM OSEM diagonalization was discovered: the P and Y gains were low by a factor 2.
 * Mark re-zeroed the QPD after noting the micrometer readings so we can do TFs over the weekend.
 * We prepared for the SR2 gluing:
  * We aligned the SR2 in the box with the wedge on the correct side.
  * We checked that the remachined BS prism holders fit on the PR2 mirror box.
  * We checked that with Tatsumi-san's support ring, the prisms would go on at the right height.
  * We checked the new magnet jigs.
 * We glued ferromagnetic disks in a large number of IM flag tips and flag bases, and in the SR magnet jigs.
 * We also glued SR magnets in the magnet bases.
Line 19: Line 18:
==== Plan for week of 11/27 ====
 * Fabian at commissioning workshop
 * Hirata-san at Kamioka Tue-Fri to work with Mirapro on SRM LBB installation.
 * All others (Mark, Enzo, Shoda-san, Kozu-kun) at Kamioka to start SR2 assembly.
  * Mark from Mon lunchtime.
  * Kozu-kun from Mon lunchtime through Wed.
  * Mirror gluing.
  * SR2 rack setup.
==== Plan for week of 12/11
 * Mark, Fabian, Enzo, Kozu-kun (Mon-Thu only), Hirata-san, Shoda-san at Kamioka.
 * Mirror gluing.
 * IM assembly and pico test.
 * Assembly frame alignment and optical table centering.
 * Move trolley system from SR3.
 * OL setup.
Line 28: Line 26:
==== Plan for week of 12/4 ====
 * All at Kamioka
  * IM assembly and pico test.
  * Assembly frame alignment and optical table centering.
  * OL setup.
==== Plan for week of 12/18 ====
 * Shoda-san vacation
 * Mark, Fabian, Enzo, Kozu-kun at Kamioka Mon-Wed.

==== Vacation Info ====
 * Mark 12/22-1/3
 * Enzo, 12/21-12/27 (but ''not'' 12/28)
 * Fabian 12/22-1/5
 * Hirata-san 12/21-22 (conference)
 * Shoda-san 12/18-21

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

  • Mark analyzed the QPD data from Friday 12/1 and derived matrices to diagonalize the QPD, and calibrate output in µrad. In the process an error in the IM OSEM diagonalization was discovered: the P and Y gains were low by a factor 2.
  • Mark re-zeroed the QPD after noting the micrometer readings so we can do TFs over the weekend.
  • We prepared for the SR2 gluing:
    • We aligned the SR2 in the box with the wedge on the correct side.
    • We checked that the remachined BS prism holders fit on the PR2 mirror box.
    • We checked that with Tatsumi-san's support ring, the prisms would go on at the right height.
    • We checked the new magnet jigs.
  • We glued ferromagnetic disks in a large number of IM flag tips and flag bases, and in the SR magnet jigs.
  • We also glued SR magnets in the magnet bases.

==== Plan for week of 12/11

  • Mark, Fabian, Enzo, Kozu-kun (Mon-Thu only), Hirata-san, Shoda-san at Kamioka.
  • Mirror gluing.
  • IM assembly and pico test.
  • Assembly frame alignment and optical table centering.
  • Move trolley system from SR3.
  • OL setup.

Plan for week of 12/18

  • Shoda-san vacation
  • Mark, Fabian, Enzo, Kozu-kun at Kamioka Mon-Wed.

Vacation Info

  • Mark 12/22-1/3
  • Enzo, 12/21-12/27 (but not 12/28)

  • Fabian 12/22-1/5
  • Hirata-san 12/21-22 (conference)
  • Shoda-san 12/18-21