Differences between revisions 208 and 229 (spanning 21 versions)
Revision 208 as of 2017-11-24 13:25:05
Size: 1533
Editor: MarkBarton
Comment:
Revision 229 as of 2018-02-09 08:25:19
Size: 1657
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 6: Line 6:
==== Past week report ==== ==== Report for week of 1/29 ====
 * Mark made two sets of in-air pico splitter cables (each with a triple for IM and a double for BF) for SR2 and SR3.
 * Fabian, Hirata-san and Kozu-kun worked on cabling and testing the IM pitch/roll/yaw picos, the BF FR and the BF LVDT. The LVDT connections were initially unreliable and Hirata-san had to redo the pins on the coil wires.
 * Fabian installed ballast masses in the BF.
 * Mark worked on schedule.
 * Mark did inventory of the stepper motor drivers (many were not accounted for on the wiki and/or JGWDoc and one is missing) and reserved two for SR3.
Line 8: Line 13:
 * Mark worked on SR2 planning.
 * Mark thought through what would be required to swap an optic (e.g., SRM) in situ (JGW-T1707436).
 * Hirata-san tried removing disks from IM flags (so we could reuse them in flag bases and make a complete set for SR2) but only got 1 of 4 out.
 * Hirata-san ordered more disks for IM flags.
 * Hirata-san asked for quotes on SF LBB blades.
 * Hirata-san got a reduced quote for the LBB damper rings.
 * Hirata-san received and cleaned suspension wires for the SR.
 * Fabian worked on the SR mass budget.
 * Fabian worked out the COM of the SR2 optic, and Mark used it to derive the proper prism positions.
 * Enzo and Kozu-kun worked on control filter design and installation.
==== Plan for week of 2/13 ====
 * No work Monday (建国記念の日の振替休日)
 * Enzo on vacation
 * Hirata-san at Mitaka Tue, Wed (to receive and wash parts).
 * Shoda-san at Mitaka
 * All others at Kamioka.
 * -
 * Build IRM around IM.
 * Cable/test/adjust IM OSEMs.
 * Do TFs from IM OSEMs to IM OSEMs, OL pitch/yaw.
Line 19: Line 24:
==== Plan for week of 11/27 ====
 * Fabian at commissioning workshop
 * Hirata-san at Kamioka Tue-Fri to work with Mirapro on SRM LBB installation.
 * All others (Mark, Enzo, Shoda-san, Kozu-kun) at Kamioka to start SR2 assembly.
  * Mark from Mon lunchtime.
  * Kozu-kun from Mon lunchtime through Wed.
  * Mirror gluing.
  * SR2 rack setup.
==== Plan for week of 2/19 ====
 * Enzo back from Tuesday.
 * Shoda-san at Mitaka
 * All others at Kamioka.
 * -
 * Lift BF/... section and check total mass and balance.
 * Cable and test BF picos.
 * Add section of SS up to SF ring.
 * Bring in SF.
 * Hook BF/... section.
 * Route cables up to under SF.
 * Check/adjust total mass of BF/... section.
Line 28: Line 37:
==== Plan for week of 12/4 ====
 * All at Kamioka
  * IM assembly and pico test.
  * Assembly frame alignment and optical table centering.
  * OL setup.
==== Plan for week of 2/26 ====
 * Add Cu segments to SF cap.
 * Lift SF/... section and check total mass and balance.
Line 35: Line 42:
 * Mark 12/22-1/3
 * Enzo TBD, probably 12/22-1/3
 * Fabian 12/22-1/5
 * Hirata-san 12/21-22 (conference)
  
 * Enzo 1/30-2/19.
 * Fabian 4/2-4/27 vacation (then gone).

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 1/29

  • Mark made two sets of in-air pico splitter cables (each with a triple for IM and a double for BF) for SR2 and SR3.
  • Fabian, Hirata-san and Kozu-kun worked on cabling and testing the IM pitch/roll/yaw picos, the BF FR and the BF LVDT. The LVDT connections were initially unreliable and Hirata-san had to redo the pins on the coil wires.
  • Fabian installed ballast masses in the BF.
  • Mark worked on schedule.
  • Mark did inventory of the stepper motor drivers (many were not accounted for on the wiki and/or JGWDoc and one is missing) and reserved two for SR3.

Plan for week of 2/13

  • No work Monday (建国記念の日の振替休日)
  • Enzo on vacation
  • Hirata-san at Mitaka Tue, Wed (to receive and wash parts).
  • Shoda-san at Mitaka
  • All others at Kamioka.
  • -
  • Build IRM around IM.
  • Cable/test/adjust IM OSEMs.
  • Do TFs from IM OSEMs to IM OSEMs, OL pitch/yaw.

Plan for week of 2/19

  • Enzo back from Tuesday.
  • Shoda-san at Mitaka
  • All others at Kamioka.
  • -
  • Lift BF/... section and check total mass and balance.
  • Cable and test BF picos.
  • Add section of SS up to SF ring.
  • Bring in SF.
  • Hook BF/... section.
  • Route cables up to under SF.
  • Check/adjust total mass of BF/... section.

Plan for week of 2/26

  • Add Cu segments to SF cap.
  • Lift SF/... section and check total mass and balance.

Vacation Info

  • Enzo 1/30-2/19.
  • Fabian 4/2-4/27 vacation (then gone).

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)