Line 5: Line 5:
 * Type B Past Week Summary
  * Fabian worked on IM and dummy BS assembly: [[https://photos.google.com/share/AF1QipMNVSExyP3TuyhK4s_VD-ARDlNoCPCf13ZDbHUlwOw14AKgj4XUe0vYg27dQ12icQ?key=SjJ0dXJ1bjN2OGVCN3d6RnoySEtFSjVJUmVwSlZR|photos1]], [[https://photos.google.com/share/AF1QipPQdoB5vYN1VcD32TkA4QSGldODvKRwiT5h-m122ahSpWmFyyrO5MX-9ajL1LeRIg?key=VFFuUVktcEtlMURQUldhZUlRcGFhbzNDeU5IN3NB|photos2]]
   * A hole in a picomotor holder was too small. ATC staff solved this isue quickly and Hirata-san cleaned the piece.
   * Some ballast discs for the dummy optic were dirty (seen by visual inspection). Hirata-san cleaned them.
   * Some arrows were cleaned from the mirrors for the dummy optic.
  * Hirata-san worked on checking Mirapro's assembly frame design - some minor issues with rail system found.
  * Hirata-san measured another filter.
  * Hirata-san washed a large batch of parts.
  * All parts for gluing of dummy BS are in hand. We arranged with Tatsumi-san to glue magnets at Mitaka on 6/6, glue flags at Kashiwa on 6/8, and inspect bonds and bring dummy BS back to Mitaka 6/13.
  * Mark worked on solutions to allow a [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Subgroups/VIS/TypeB/dummyBS|larger mirror on dummy BS]]. After discussions with Simon and Akutsu-san we decided to go with a stainless steel plate solution. The gluing can go ahead and we can attach the plates later.
  * Mark worked on list of items for purchase in FY2016.
  * Mark worked on finding connectors for vacuum-compatible geophone adapters.
  * Mark worked more on [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235|E1504235 BS Assembly Procedure]] ([[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|Draft on OneDrive]])
 * '''Discussions '''
  * Crane will not be available on 13-14 of June.
  * Review: '''fix the date (Mark) '''
  * Measurement of iKAGRA BS position will be done in the second week of June. Then it will be taken out of the chamber after that (Ohishi)
 * IM, RM, IRM, dummy BS assembly
  * Fabian assembled the dummy BS and started on the IM.
  * Still need to find SDC-treated hook for maraging wire in IM. Still not found. Spare hook is being SDC-treated. Can be added later.
  * Will start assembly 5/30
 * Wires
  * Fabian analysis RM wire thickness versus mode frequency: [[https://onedrive.live.com/redir?resid=1447B05D5B571A84!442&authkey=!AKrjBW2W8vMKyAY&ithint=file,pdf|link]], [[https://onedrive.live.com/redir?resid=1447B05D5B571A84!421&authkey=!ALZY-tFtMCYI9Pw&ithint=file,pdf|another link]],[[https://pfalig.bn1301.livefilestore.com/y3mT7oHnuBfD9_7Ata6H90opTVY5IIIm78MQ8Rl-lChfSUtGhGiEP-mlB1rQuzliimi-pmL1JfYTKCUY_Tgan0Bfa2jq5EeSXWiCracw_5ulsm2iuf6RHJcz0ot34DaeWqdUjFnU6fILnyau69WFkBmUcTwfGYBNwSrs27eyK-jc90/RM_wire.pdf?psid=1|yet another link]] (From last week: [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5106|T1605106]] /[[https://onedrive.live.com/view.aspx?resid=1447B05D5B571A84!354&ithint=file,docx&app=Word&authkey=!AO5CHNP3xlO5RjY|draft]])
 * Can we make SR wire breakers bigger?
  * Fukushima-san has not yet started the work. He will start soon (as of 5/27).
 * Flags, Metal Prisms, Sapphire prisms RECEIVED
 * Mirror box and Flag/Prism gluing
  * All parts in hand.
  * Magnet gluing and check of parts at Mitaka, Monday 6/6.
  * Gluing at Kashiwa, Wednesday 6/8.
  * Inspection of bonds and return to Mitaka, 6/13.
 * An extra structure attached to the EQ stop to prevent tipping over of the BS - no action since last week.
 * Not enough crane height problem (Hirata, Saito) - no action since last week
 * Ballast masses for payload
  * Initial batch received - ordered extra smaller ones to allow for adjustments.
 * Lower breadboard stuff
  * Assembly procedure
   * '''Need to be incorporated into the procedure document. Discuss with Takahashi (Mark)'''
  * Breadboard springs (in manufacture, expected end of July)
  * Nail-head parts: quote from Mirapro received, not urgent, will be combined with assembly frame order.
 * BS Assembly Frame Design (Mark, Hirata)
  * Hirata-san found issues with rail system part - organizing fix.
 * Clean bag
  * Ordered - expected 6/8.
 * 2D and 3D CAD
  * [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5035|E1605035 VIS Document and Drawing Tree (BS)]]
 * Electronics
  * [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=3600|JGW-D1503600 - BS Suspension Cabling]]
  * [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5111|E1605111 BS Suspension Electronic Items List]]
  * [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=3901|D1503901 In-Vacuum Cable Detail]]
  * Item list and timetable was given to Miyakawa-san - some corrections received and added to schematic but not yet posted.
  * Status on AEL boxes OK according to Miyakawa-san.
  * Signal generator and cable to be used for BS test. May order NIKHEF cards later if concern about AC-driven units in racks.
  * Need to get new longer versions of some previously ordered BF-PI and SF-PI cables (Takahashi).
  * Need to check previously ordered TM-BF and IM-BF OSEM cables have been flipped (Takahashi).
  * Decided to hand-make cables for geophones because previously ordered cables have no conductor on pin 5.
  * Stepper drive box (requested by Sekiguchi-san [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=3385|T1503385]]) is being designed, should be ready in time.
  * Mark looking for connectors for geophone adapters.
 * Procedure documents
  * Mark worked on BS Assembly Procedure [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
=== Type B (Mark) ===
==== Past week report ====

 * Mark finished the OL calibration/diagonalization calculation and wrote it up as klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=3835|3835]] and [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7205| T1707205-v4]].
 * We glued the prisms and magnets on the SR2.
 * We got Miyo-kun to set up the SR2-IM pico driver and tested it and the picos that will be used in the IM.
 * We weighed the BF for the SR2.
 * Enzo put DIO cards in the IO chassis and cabled them to the coil drivers.
 * Enzo found more of the in-vacuum cables that will be needed for SR2. Only a few remain to be found.
 * Enzo and Shoda-san installed the vacuum-feedthroughs on the assembly frame and routed many of the in-air cables.
 * Hirata-san and Mark moved the PR/SR trolley system from SR3 to SR2, reconfigured the top of the assembly frame and checked the crossbar heights. (Everything was quite close to the drawing, but a few small adjustments up/down will be required.)
 * Fabian found an issue with the IM: we have two of the upper movable masses and no lower ones. Probably one of the PRs has been built with two lower masses. Unfortunately an upper mass has an extra hole in an inconvenient place and can't be used as a lower mass. Hirata-san ordered a suitable plug part from Misumi, and Fabian washed it and glued it in with EP30.
 * Fabian assembled the RM and test-assembled the IRM. (The IRM will have to be partly disassembled during installation.)
 * Shoda-san and Enzo got all the control loops working on the BS, and worked with Izumi-san to steer the beam down the Y-arm. They found the passive damping was not working very well, even after correcting a 1.5 mm height error in F0. We may need to lower the damper ring.
 * Shoda-san created a BS Guardian.
 * We got Yamamoto-san to connect up the SR2 rack and create an SR2 real-time model.

==== Plan for week of 12/18 ====
 * Shoda-san vacation
 * Mark, Fabian, Enzo, Kozu-kun at Kamioka Mon-Wed.
 * Assembly frame alignment and optical table centering.
 * Install IM ring interface blocks and IM ring.
 * Finish IM assembly and pico test.
 * Do inventory of ballast masses.
 * OL setup.
 * Install new jack receptacles (in SR3 area, second floor) on load gauge adapter (SR2 area, second floor).

==== Plan for week of 12/25 ====
 * Mark, Enzo, Fabian vacation
 * Shoda-san, Kozu-kun, Hirata-san at Kamioka Mon-Thu.
 * Hang SR and RM?

==== Vacation Info ====
 * Mark 12/22-1/3
 * Enzo, 12/21-12/27 (but ''not'' 12/28)
 * Fabian 12/22-1/5
 * Hirata-san 12/21-22 (conference)
 * Shoda-san 12/18-21
  

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Past week report

  • Mark finished the OL calibration/diagonalization calculation and wrote it up as klog 3835 and T1707205-v4.

  • We glued the prisms and magnets on the SR2.
  • We got Miyo-kun to set up the SR2-IM pico driver and tested it and the picos that will be used in the IM.
  • We weighed the BF for the SR2.
  • Enzo put DIO cards in the IO chassis and cabled them to the coil drivers.
  • Enzo found more of the in-vacuum cables that will be needed for SR2. Only a few remain to be found.
  • Enzo and Shoda-san installed the vacuum-feedthroughs on the assembly frame and routed many of the in-air cables.
  • Hirata-san and Mark moved the PR/SR trolley system from SR3 to SR2, reconfigured the top of the assembly frame and checked the crossbar heights. (Everything was quite close to the drawing, but a few small adjustments up/down will be required.)
  • Fabian found an issue with the IM: we have two of the upper movable masses and no lower ones. Probably one of the PRs has been built with two lower masses. Unfortunately an upper mass has an extra hole in an inconvenient place and can't be used as a lower mass. Hirata-san ordered a suitable plug part from Misumi, and Fabian washed it and glued it in with EP30.
  • Fabian assembled the RM and test-assembled the IRM. (The IRM will have to be partly disassembled during installation.)
  • Shoda-san and Enzo got all the control loops working on the BS, and worked with Izumi-san to steer the beam down the Y-arm. They found the passive damping was not working very well, even after correcting a 1.5 mm height error in F0. We may need to lower the damper ring.
  • Shoda-san created a BS Guardian.
  • We got Yamamoto-san to connect up the SR2 rack and create an SR2 real-time model.

Plan for week of 12/18

  • Shoda-san vacation
  • Mark, Fabian, Enzo, Kozu-kun at Kamioka Mon-Wed.
  • Assembly frame alignment and optical table centering.
  • Install IM ring interface blocks and IM ring.
  • Finish IM assembly and pico test.
  • Do inventory of ballast masses.
  • OL setup.
  • Install new jack receptacles (in SR3 area, second floor) on load gauge adapter (SR2 area, second floor).

Plan for week of 12/25

  • Mark, Enzo, Fabian vacation
  • Shoda-san, Kozu-kun, Hirata-san at Kamioka Mon-Thu.
  • Hang SR and RM?

Vacation Info

  • Mark 12/22-1/3
  • Enzo, 12/21-12/27 (but not 12/28)

  • Fabian 12/22-1/5
  • Hirata-san 12/21-22 (conference)
  • Shoda-san 12/18-21