5968
Comment:
|
2251
|
Deletions are marked like this. | Additions are marked like this. |
Line 5: | Line 5: |
* Type B Past Week Summary * Fabian worked on IM and dummy BS assembly: [[https://photos.google.com/share/AF1QipMNVSExyP3TuyhK4s_VD-ARDlNoCPCf13ZDbHUlwOw14AKgj4XUe0vYg27dQ12icQ?key=SjJ0dXJ1bjN2OGVCN3d6RnoySEtFSjVJUmVwSlZR|photos1]], [[https://photos.google.com/share/AF1QipPQdoB5vYN1VcD32TkA4QSGldODvKRwiT5h-m122ahSpWmFyyrO5MX-9ajL1LeRIg?key=VFFuUVktcEtlMURQUldhZUlRcGFhbzNDeU5IN3NB|photos2]] * A hole in a picomotor holder was too small. ATC staff solved this isue quickly and Hirata-san cleaned the piece. * Some ballast discs for the dummy optic were dirty (seen by visual inspection). Hirata-san cleaned them. * Some arrows were cleaned from the mirrors for the dummy optic. * Hirata-san worked on checking Mirapro's assembly frame design - some minor issues with rail system found. * Hirata-san measured another filter. * Hirata-san washed a large batch of parts. * All parts for gluing of dummy BS are in hand. We arranged with Tatsumi-san to glue magnets at Mitaka on 6/6, glue flags at Kashiwa on 6/8, and inspect bonds and bring dummy BS back to Mitaka 6/13. * Mark worked on solutions to allow a [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Subgroups/VIS/TypeB/dummyBS|larger mirror on dummy BS]]. After discussions with Simon and Akutsu-san we decided to go with a stainless steel plate solution. The gluing can go ahead and we can attach the plates later. * Mark worked on list of items for purchase in FY2016. * Mark worked on finding connectors for vacuum-compatible geophone adapters. * Mark worked more on [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235|E1504235 BS Assembly Procedure]] ([[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|Draft on OneDrive]]) * '''Discussions ''' * Crane will not be available on 13-14 of June. * Review: '''fix the date (Mark) ''' * Measurement of iKAGRA BS position will be done in the second week of June. Then it will be taken out of the chamber after that (Ohishi) * IM, RM, IRM, dummy BS assembly * Fabian assembled the dummy BS and started on the IM. * Still need to find SDC-treated hook for maraging wire in IM. Still not found. Spare hook is being SDC-treated. Can be added later. * Will start assembly 5/30 * Wires * Fabian analysis RM wire thickness versus mode frequency: [[https://onedrive.live.com/redir?resid=1447B05D5B571A84!442&authkey=!AKrjBW2W8vMKyAY&ithint=file,pdf|link]], [[https://onedrive.live.com/redir?resid=1447B05D5B571A84!421&authkey=!ALZY-tFtMCYI9Pw&ithint=file,pdf|another link]],[[https://pfalig.bn1301.livefilestore.com/y3mT7oHnuBfD9_7Ata6H90opTVY5IIIm78MQ8Rl-lChfSUtGhGiEP-mlB1rQuzliimi-pmL1JfYTKCUY_Tgan0Bfa2jq5EeSXWiCracw_5ulsm2iuf6RHJcz0ot34DaeWqdUjFnU6fILnyau69WFkBmUcTwfGYBNwSrs27eyK-jc90/RM_wire.pdf?psid=1|yet another link]] (From last week: [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5106|T1605106]] /[[https://onedrive.live.com/view.aspx?resid=1447B05D5B571A84!354&ithint=file,docx&app=Word&authkey=!AO5CHNP3xlO5RjY|draft]]) * Can we make SR wire breakers bigger? * Fukushima-san has not yet started the work. He will start soon (as of 5/27). * Flags, Metal Prisms, Sapphire prisms RECEIVED * Mirror box and Flag/Prism gluing * All parts in hand. * Magnet gluing and check of parts at Mitaka, Monday 6/6. * Gluing at Kashiwa, Wednesday 6/8. * Inspection of bonds and return to Mitaka, 6/13. * An extra structure attached to the EQ stop to prevent tipping over of the BS - no action since last week. * Not enough crane height problem (Hirata, Saito) - no action since last week * Ballast masses for payload * Initial batch received - ordered extra smaller ones to allow for adjustments. * Lower breadboard stuff * Assembly procedure * '''Need to be incorporated into the procedure document. Discuss with Takahashi (Mark)''' * Breadboard springs (in manufacture, expected end of July) * Nail-head parts: quote from Mirapro received, not urgent, will be combined with assembly frame order. * BS Assembly Frame Design (Mark, Hirata) * Hirata-san found issues with rail system part - organizing fix. * Clean bag * Ordered - expected 6/8. * 2D and 3D CAD * [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5035|E1605035 VIS Document and Drawing Tree (BS)]] * Electronics * [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=3600|JGW-D1503600 - BS Suspension Cabling]] * [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5111|E1605111 BS Suspension Electronic Items List]] * [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=3901|D1503901 In-Vacuum Cable Detail]] * Item list and timetable was given to Miyakawa-san - some corrections received and added to schematic but not yet posted. * Status on AEL boxes OK according to Miyakawa-san. * Signal generator and cable to be used for BS test. May order NIKHEF cards later if concern about AC-driven units in racks. * Need to get new longer versions of some previously ordered BF-PI and SF-PI cables (Takahashi). * Need to check previously ordered TM-BF and IM-BF OSEM cables have been flipped (Takahashi). * Decided to hand-make cables for geophones because previously ordered cables have no conductor on pin 5. * Stepper drive box (requested by Sekiguchi-san [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=3385|T1503385]]) is being designed, should be ready in time. * Mark looking for connectors for geophone adapters. * Procedure documents * Mark worked on BS Assembly Procedure [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] |
=== Type B (Mark) === ==== Report for week of 9/17 ==== * Monday 9/17 was holiday. * We optimized the trim mass on the SF to get more balance torque with less total mass. We now have a reserve of 480 g for the yaw pico. * We set the SF damper gap to 6 mm. * We set the SR2 pitch with the optic lever, aligned the IRM, and set all the OSEMs to have good clearance and midrange output. * We locked the SR2 suspension, craned it into the tank and hooked the LBB damper rings (but not the LBB yet). * With help from Ohishi-san, we removed the First Contact from SR2. * Mark did an audit of all the electronics boxes and updated the item list and S-number file cards on JGWDoc. * Mark added some thin arc weights to the inventory and finalized the number of various types to order (8*38 mm + 9*10 mm). * Panwei copied control filters over from the SR3. ==== Plan for week of 9/24 ==== * Monday 9/24 is holiday (Autumn Equinox). * Mark, Hirata-san, Fabian, Panwei at Kamioka Tue-Fri. ===== SR2 ===== * Move SR2 in-air cables. * Unlock and realign suspension. ===== SRM ===== * Set pitch of SRM and RM, tighten clamps, remove winch system. * Weigh IM/... section. * Build up SS to BF level. * Add BF. * Suspend IM and tweak height/balance. ==== Plan for week of 10/1 ==== * Mark, Hirata-san, Fabian, Panwei at Kamioka Mon-Fri. ===== SRM ===== * Cable/test BF. * Install IRM. * Install/cable/test IM OSEMs. ==== Plan for week of 10/8 ==== * Monday 10/8 is Sports Day. * Mark and Terrence (plus TBD) at Kamioka Mon-Fri. * Hirata-san, Fabian and Panwei at Kamioka Tue-Fri. ===== SR2/SR3 ===== * Terrence to set up LEN half of SR3 OL and, time permitting, TILT and LEN for SR2. ===== SRM ===== * Continue installation. ==== To-Do Lists, Schedule ==== * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]] * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]] * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]] ==== Vacation/Visitor Info ==== * Enzo: 9/15 through 10/8 vacation in Chile. * Terrence: 10/8-12, 10/29-11/2 at Kamioka. |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 9/17
- Monday 9/17 was holiday.
- We optimized the trim mass on the SF to get more balance torque with less total mass. We now have a reserve of 480 g for the yaw pico.
- We set the SF damper gap to 6 mm.
- We set the SR2 pitch with the optic lever, aligned the IRM, and set all the OSEMs to have good clearance and midrange output.
- We locked the SR2 suspension, craned it into the tank and hooked the LBB damper rings (but not the LBB yet).
- With help from Ohishi-san, we removed the First Contact from SR2.
- Mark did an audit of all the electronics boxes and updated the item list and S-number file cards on JGWDoc.
- Mark added some thin arc weights to the inventory and finalized the number of various types to order (8*38 mm + 9*10 mm).
- Panwei copied control filters over from the SR3.
Plan for week of 9/24
- Monday 9/24 is holiday (Autumn Equinox).
- Mark, Hirata-san, Fabian, Panwei at Kamioka Tue-Fri.
SR2
- Move SR2 in-air cables.
- Unlock and realign suspension.
SRM
- Set pitch of SRM and RM, tighten clamps, remove winch system.
- Weigh IM/... section.
- Build up SS to BF level.
- Add BF.
- Suspend IM and tweak height/balance.
Plan for week of 10/1
- Mark, Hirata-san, Fabian, Panwei at Kamioka Mon-Fri.
SRM
- Cable/test BF.
- Install IRM.
- Install/cable/test IM OSEMs.
Plan for week of 10/8
- Monday 10/8 is Sports Day.
- Mark and Terrence (plus TBD) at Kamioka Mon-Fri.
- Hirata-san, Fabian and Panwei at Kamioka Tue-Fri.
SR2/SR3
- Terrence to set up LEN half of SR3 OL and, time permitting, TILT and LEN for SR2.
SRM
- Continue installation.
To-Do Lists, Schedule
Vacation/Visitor Info
- Enzo: 9/15 through 10/8 vacation in Chile.
- Terrence: 10/8-12, 10/29-11/2 at Kamioka.