 * Type B Past Week Summary
  * Fabian worked on IM and dummy BS assembly: [[https://photos.google.com/share/AF1QipMNVSExyP3TuyhK4s_VD-ARDlNoCPCf13ZDbHUlwOw14AKgj4XUe0vYg27dQ12icQ?key=SjJ0dXJ1bjN2OGVCN3d6RnoySEtFSjVJUmVwSlZR|photos1]], [[https://photos.google.com/share/AF1QipPQdoB5vYN1VcD32TkA4QSGldODvKRwiT5h-m122ahSpWmFyyrO5MX-9ajL1LeRIg?key=VFFuUVktcEtlMURQUldhZUlRcGFhbzNDeU5IN3NB|photos2]]
   * A hole in a picomotor holder was too small. ATC staff solved this isue quickly and Hirata-san cleaned the piece.
   * Some ballast discs for the dummy optic were dirty (seen by visual inspection). Hirata-san cleaned them.
   * Some arrows were cleaned from the mirrors for the dummy optic.
  * Hirata-san worked on checking Mirapro's assembly frame design - some minor issues with rail system found.
  * Hirata-san measured another filter.
  * Hirata-san washed a large batch of parts.
  * All parts for gluing of dummy BS are in hand. We arranged with Tatsumi-san to glue magnets at Mitaka on 6/6, glue flags at Kashiwa on 6/8, and inspect bonds and bring dummy BS back to Mitaka 6/13.
  * Mark worked on solutions to allow a [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Subgroups/VIS/TypeB/dummyBS|larger mirror on dummy BS]]. After discussions with Simon and Akutsu-san we decided to go with a stainless steel plate solution. The gluing can go ahead and we can attach the plates later.
  * Mark worked on list of items for purchase in FY2016.
  * Mark worked on finding connectors for vacuum-compatible geophone adapters.
  * Mark worked more on [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235|E1504235 BS Assembly Procedure]] ([[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|Draft on OneDrive]])
 * '''Discussions '''
  * Crane will not be available on 13-14 of June.
  * Review: '''fix the date (Mark) '''
  * Measurement of iKAGRA BS position will be done in the second week of June. Then it will be taken out of the chamber after that (Ohishi)
 * IM, RM, IRM, dummy BS assembly
  * Fabian assembled the dummy BS and started on the IM.
  * Still need to find SDC-treated hook for maraging wire in IM. Still not found. Spare hook is being SDC-treated. Can be added later.
  * Will start assembly 5/30
 * Wires
  * Fabian analysis RM wire thickness versus mode frequency: [[https://onedrive.live.com/redir?resid=1447B05D5B571A84!442&authkey=!AKrjBW2W8vMKyAY&ithint=file,pdf|link]], [[https://onedrive.live.com/redir?resid=1447B05D5B571A84!421&authkey=!ALZY-tFtMCYI9Pw&ithint=file,pdf|another link]],[[https://pfalig.bn1301.livefilestore.com/y3mT7oHnuBfD9_7Ata6H90opTVY5IIIm78MQ8Rl-lChfSUtGhGiEP-mlB1rQuzliimi-pmL1JfYTKCUY_Tgan0Bfa2jq5EeSXWiCracw_5ulsm2iuf6RHJcz0ot34DaeWqdUjFnU6fILnyau69WFkBmUcTwfGYBNwSrs27eyK-jc90/RM_wire.pdf?psid=1|yet another link]] (From last week: [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5106|T1605106]] /[[https://onedrive.live.com/view.aspx?resid=1447B05D5B571A84!354&ithint=file,docx&app=Word&authkey=!AO5CHNP3xlO5RjY|draft]])
 * Can we make SR wire breakers bigger?
  * Fukushima-san has not yet started the work. He will start soon (as of 5/27).
 * Flags, Metal Prisms, Sapphire prisms RECEIVED
 * Mirror box and Flag/Prism gluing
  * All parts in hand.
  * Magnet gluing and check of parts at Mitaka, Monday 6/6.
  * Gluing at Kashiwa, Wednesday 6/8.
  * Inspection of bonds and return to Mitaka, 6/13.
 * An extra structure attached to the EQ stop to prevent tipping over of the BS - no action since last week.
 * Not enough crane height problem (Hirata, Saito) - no action since last week
 * Ballast masses for payload
  * Initial batch received - ordered extra smaller ones to allow for adjustments.
 * Lower breadboard stuff
  * Assembly procedure
   * '''Need to be incorporated into the procedure document. Discuss with Takahashi (Mark)'''
  * Breadboard springs (in manufacture, expected end of July)
  * Nail-head parts: quote from Mirapro received, not urgent, will be combined with assembly frame order.
 * BS Assembly Frame Design (Mark, Hirata)
  * Hirata-san found issues with rail system part - organizing fix.
 * Clean bag
  * Ordered - expected 6/8.
 * 2D and 3D CAD
  * [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5035|E1605035 VIS Document and Drawing Tree (BS)]]
 * Electronics
  * [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=3600|JGW-D1503600 - BS Suspension Cabling]]
  * [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5111|E1605111 BS Suspension Electronic Items List]]
  * [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=3901|D1503901 In-Vacuum Cable Detail]]
  * Item list and timetable was given to Miyakawa-san - some corrections received and added to schematic but not yet posted.
  * Status on AEL boxes OK according to Miyakawa-san.
  * Signal generator and cable to be used for BS test. May order NIKHEF cards later if concern about AC-driven units in racks.
  * Need to get new longer versions of some previously ordered BF-PI and SF-PI cables (Takahashi).
  * Need to check previously ordered TM-BF and IM-BF OSEM cables have been flipped (Takahashi).
  * Decided to hand-make cables for geophones because previously ordered cables have no conductor on pin 5.
  * Stepper drive box (requested by Sekiguchi-san [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=3385|T1503385]]) is being designed, should be ready in time.
  * Mark looking for connectors for geophone adapters.
 * Procedure documents
  * Mark worked on BS Assembly Procedure [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
=== Type B (Mark) ===
==== Report for week of 10/29 ====
 * SRM
  * Enzo realized that he could cover the next round of needed cables with more cable soldering and did another batch. Because Yamamoto-san's lab was running low on isopropanol, Hirata-san washed them with ethanol at Mozumi.
  * Enzo worked out the optimum output resistance for the LPCDs to substitute for HPCDs with the horizontal IM OSEMs. The value was quite close to that already chosen for modified LPCDs by the cryogenic group, so we're going to standardize. The modified LPCDs will have to be operated with the internal watchdog disabled for now because it was hard-wired to 2 mA.
  * Fabian finished adding the TM OSEM cables out to the rack and tested them.
  * We ran DC power and network to the second SRM stepper driver. We still need to get one more DC power cable to replace one we borrowed from SR3. We added the remaining steppers to the Python driver and MEDM screen.
  * We reconfigured the top of the assembly frame in preparation for the PI (removing crossbars and moving jacks down).
  * Hirata-san put the magnets on the SF damper and we hooked it to the PI, craned the PI into the assembly frame and joined it to the security structure.
  * We installed the F0-SF rod and flying saucer and suspended the SF/... section. We had plenty of spare load capacity, so we changed the CuBe spring to a weaker one and put 2.3 kg of ballast on the SF cap. This leaves 1.2 kg reserve for cables and an F0 yaw stepper mechanism.
  * We reduced the trim mass on the BF to compensate for the mass of the TM OSEM cables.
  * We measured all the bounce frequencies.
  * Hirata-san put magnets on the LBB damper magnet ring, put the pieces into the tank and assembled them into a sandwich ready for craning.
 * SR2
  * Hirata-san unclamped the LBB damper rings and suspended the LBB. It still needs ballast mass and is currently sitting high, with the blades at their upper stops.

 
==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]]

==== Plan for week of 11/4 ====
 * Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Fri.
===== SRM =====
 * Main sequence
  * Add magnets to SF damper.
  * Install #353 poles
  * Move NB-03 jacks down.
  * Crane PI into AF.
  * Install F0-SF rod (#331) and flying saucer.
  * Route SF/... cables up to underside of F0.
  * Do vertical height budget.
  * Adjust SF trim mass for balance and keystone height.
  * Cable/test IP LVDTs.
  * Cable/test IP FRs.
 * LBB
  * Move KOACH filters
  * Put LBB damper rings in tank.
  * Set tank jacks to nominal height.

==== Plan for week of 11/11 ====
 * Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Fri.
===== SRM =====
 * Unlock IP and center roughly.
 * Calibrate IP LVDTs.
 * Check/adjust alignment of SS.
 * Add arc weights and geophones (or extra mass equivalent to geophones).
 * Cable/test geophones.
 * Improve centering/tuning of IP and SS alignment.

==== Plan for week of 11/18 ====
 * Friday 11/23 is Labor Thanksgiving Day.
 * Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Thu.
===== SRM =====
 * Unlock IP and center roughly.
 * Calibrate IP LVDTs.
 * Check/adjust alignment of SS.
 * Add arc weights and geophones (or extra mass equivalent to geophones).
 * Cable/test geophones.
 * Improve centering/tuning of IP and SS alignment.
 * Crane into tank.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 10/29

  • SRM
    • Enzo realized that he could cover the next round of needed cables with more cable soldering and did another batch. Because Yamamoto-san's lab was running low on isopropanol, Hirata-san washed them with ethanol at Mozumi.
    • Enzo worked out the optimum output resistance for the LPCDs to substitute for HPCDs with the horizontal IM OSEMs. The value was quite close to that already chosen for modified LPCDs by the cryogenic group, so we're going to standardize. The modified LPCDs will have to be operated with the internal watchdog disabled for now because it was hard-wired to 2 mA.
    • Fabian finished adding the TM OSEM cables out to the rack and tested them.
    • We ran DC power and network to the second SRM stepper driver. We still need to get one more DC power cable to replace one we borrowed from SR3. We added the remaining steppers to the Python driver and MEDM screen.
    • We reconfigured the top of the assembly frame in preparation for the PI (removing crossbars and moving jacks down).
    • Hirata-san put the magnets on the SF damper and we hooked it to the PI, craned the PI into the assembly frame and joined it to the security structure.
    • We installed the F0-SF rod and flying saucer and suspended the SF/... section. We had plenty of spare load capacity, so we changed the CuBe spring to a weaker one and put 2.3 kg of ballast on the SF cap. This leaves 1.2 kg reserve for cables and an F0 yaw stepper mechanism.

    • We reduced the trim mass on the BF to compensate for the mass of the TM OSEM cables.
    • We measured all the bounce frequencies.
    • Hirata-san put magnets on the LBB damper magnet ring, put the pieces into the tank and assembled them into a sandwich ready for craning.
  • SR2
    • Hirata-san unclamped the LBB damper rings and suspended the LBB. It still needs ballast mass and is currently sitting high, with the blades at their upper stops.

To-Do Lists, Schedule

Plan for week of 11/4

  • Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Fri.

SRM
  • Main sequence
    • Add magnets to SF damper.
    • Install #353 poles
    • Move NB-03 jacks down.
    • Crane PI into AF.
    • Install F0-SF rod (#331) and flying saucer.
    • Route SF/... cables up to underside of F0.
    • Do vertical height budget.
    • Adjust SF trim mass for balance and keystone height.
    • Cable/test IP LVDTs.
    • Cable/test IP FRs.
  • LBB
    • Move KOACH filters
    • Put LBB damper rings in tank.
    • Set tank jacks to nominal height.

Plan for week of 11/11

  • Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Fri.

SRM
  • Unlock IP and center roughly.
  • Calibrate IP LVDTs.
  • Check/adjust alignment of SS.
  • Add arc weights and geophones (or extra mass equivalent to geophones).
  • Cable/test geophones.
  • Improve centering/tuning of IP and SS alignment.

Plan for week of 11/18

  • Friday 11/23 is Labor Thanksgiving Day.
  • Mark, Enzo, Hirata-san and Fabian at Kamioka Mon-Thu.

SRM
  • Unlock IP and center roughly.
  • Calibrate IP LVDTs.
  • Check/adjust alignment of SS.
  • Add arc weights and geophones (or extra mass equivalent to geophones).
  • Cable/test geophones.
  • Improve centering/tuning of IP and SS alignment.
  • Crane into tank.