Line 5: Line 5:
 * Type B Past Week Summary
  * Fabian worked on IM and dummy BS assembly: [[https://photos.google.com/share/AF1QipMNVSExyP3TuyhK4s_VD-ARDlNoCPCf13ZDbHUlwOw14AKgj4XUe0vYg27dQ12icQ?key=SjJ0dXJ1bjN2OGVCN3d6RnoySEtFSjVJUmVwSlZR|photos1]], [[https://photos.google.com/share/AF1QipPQdoB5vYN1VcD32TkA4QSGldODvKRwiT5h-m122ahSpWmFyyrO5MX-9ajL1LeRIg?key=VFFuUVktcEtlMURQUldhZUlRcGFhbzNDeU5IN3NB|photos2]]
   * A hole in a picomotor holder was too small. ATC staff solved this isue quickly and Hirata-san cleaned the piece.
   * Some ballast discs for the dummy optic were dirty (seen by visual inspection). Hirata-san cleaned them.
   * Some arrows were cleaned from the mirrors for the dummy optic.
  * Hirata-san worked on checking Mirapro's assembly frame design - some minor issues with rail system found.
  * Hirata-san measured another filter.
  * Hirata-san washed a large batch of parts.
  * All parts for gluing of dummy BS are in hand. We arranged with Tatsumi-san to glue magnets at Mitaka on 6/6, glue flags at Kashiwa on 6/8, and inspect bonds and bring dummy BS back to Mitaka 6/13.
  * Mark worked on solutions to allow a [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Subgroups/VIS/TypeB/dummyBS|larger mirror on dummy BS]]. After discussions with Simon and Akutsu-san we decided to go with a stainless steel plate solution. The gluing can go ahead and we can attach the plates later.
  * Mark worked on list of items for purchase in FY2016.
  * Mark worked on finding connectors for vacuum-compatible geophone adapters.
  * Mark worked more on [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235|E1504235 BS Assembly Procedure]] ([[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|Draft on OneDrive]])
 * '''Discussions '''
  * Crane will not be available on 13-14 of June.
  * Review: '''fix the date (Mark) '''
  * Measurement of iKAGRA BS position will be done in the second week of June. Then it will be taken out of the chamber after that (Ohishi)
 * IM, RM, IRM, dummy BS assembly
  * Fabian assembled the dummy BS and started on the IM.
  * Still need to find SDC-treated hook for maraging wire in IM. Still not found. Spare hook is being SDC-treated. Can be added later.
  * Will start assembly 5/30
 * Wires
  * Fabian analysis RM wire thickness versus mode frequency: [[https://onedrive.live.com/redir?resid=1447B05D5B571A84!442&authkey=!AKrjBW2W8vMKyAY&ithint=file,pdf|link]], [[https://onedrive.live.com/redir?resid=1447B05D5B571A84!421&authkey=!ALZY-tFtMCYI9Pw&ithint=file,pdf|another link]],[[https://pfalig.bn1301.livefilestore.com/y3mT7oHnuBfD9_7Ata6H90opTVY5IIIm78MQ8Rl-lChfSUtGhGiEP-mlB1rQuzliimi-pmL1JfYTKCUY_Tgan0Bfa2jq5EeSXWiCracw_5ulsm2iuf6RHJcz0ot34DaeWqdUjFnU6fILnyau69WFkBmUcTwfGYBNwSrs27eyK-jc90/RM_wire.pdf?psid=1|yet another link]] (From last week: [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5106|T1605106]] /[[https://onedrive.live.com/view.aspx?resid=1447B05D5B571A84!354&ithint=file,docx&app=Word&authkey=!AO5CHNP3xlO5RjY|draft]])
 * Can we make SR wire breakers bigger?
  * Fukushima-san has not yet started the work. He will start soon (as of 5/27).
 * Flags, Metal Prisms, Sapphire prisms RECEIVED
 * Mirror box and Flag/Prism gluing
  * All parts in hand.
  * Magnet gluing and check of parts at Mitaka, Monday 6/6.
  * Gluing at Kashiwa, Wednesday 6/8.
  * Inspection of bonds and return to Mitaka, 6/13.
 * An extra structure attached to the EQ stop to prevent tipping over of the BS - no action since last week.
 * Not enough crane height problem (Hirata, Saito) - no action since last week
 * Ballast masses for payload
  * Initial batch received - ordered extra smaller ones to allow for adjustments.
 * Lower breadboard stuff
  * Assembly procedure
   * '''Need to be incorporated into the procedure document. Discuss with Takahashi (Mark)'''
  * Breadboard springs (in manufacture, expected end of July)
  * Nail-head parts: quote from Mirapro received, not urgent, will be combined with assembly frame order.
 * BS Assembly Frame Design (Mark, Hirata)
  * Hirata-san found issues with rail system part - organizing fix.
 * Clean bag
  * Ordered - expected 6/8.
 * 2D and 3D CAD
  * [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5035|E1605035 VIS Document and Drawing Tree (BS)]]
 * Electronics
  * [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=3600|JGW-D1503600 - BS Suspension Cabling]]
  * [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5111|E1605111 BS Suspension Electronic Items List]]
  * [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=3901|D1503901 In-Vacuum Cable Detail]]
  * Item list and timetable was given to Miyakawa-san - some corrections received and added to schematic but not yet posted.
  * Status on AEL boxes OK according to Miyakawa-san.
  * Signal generator and cable to be used for BS test. May order NIKHEF cards later if concern about AC-driven units in racks.
  * Need to get new longer versions of some previously ordered BF-PI and SF-PI cables (Takahashi).
  * Need to check previously ordered TM-BF and IM-BF OSEM cables have been flipped (Takahashi).
  * Decided to hand-make cables for geophones because previously ordered cables have no conductor on pin 5.
  * Stepper drive box (requested by Sekiguchi-san [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=3385|T1503385]]) is being designed, should be ready in time.
  * Mark looking for connectors for geophone adapters.
 * Procedure documents
  * Mark worked on BS Assembly Procedure [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
=== Type B (Mark) ===
==== Report for week of 12/17 ====
 * BS
  * We opened the top of the BS tank after the vent.
  * We inspected the BS F0 blades for cracks but still didn't find any.
  * We removed the arc weights and geophones, and added new longer studs for the arc weights and new cables for the geophones. We then put back the original arc weights and new geophones.
  * We measured the geometry of the various IP items to check the IP diagonalization matrices.
  * We installed the new double-sided F0 FR. We were not close to needing to add the optional !CuBe spring. Unfortunately the FR had rather less friction but still didn't work. After checking a bunch of possibilities and comparing against SRM (also non-working) and SR2/SR3 (working), we suspect the carriage may be assembled upside down, with the metal plate below and the PEEK plate above. We will try changing it next week.
 * We adjusted the F0 keystone trim mass and were able to get it to sit at CAD nominal height at nominal temperature (24.9°C) with mid-range FR and modest extra mass (413 g). Interestingly, we noticed that removing the arc weights and/or geophones reduced the load capacity by a few hundred grams.
 * We measured the total range of the IP FRs in steps and set them to mid-range in preparation for tuning the IP frequency and (re-)centering the IP.
 * SRM
  * We borrowed an LED from SR2 and set the pitch of the SRM optic.
  * We found the SRM front end had crashed and could not be properly reset by cycling the power from the web interface. Yamamoto-san eventually got it working for us, although it didn't seem to take more than restarting the user and IOP models.
  * We sealed and retested the new geophones originally intended for SRM, but decided to use them on BS instead.
  * We installed the two OL viewports. We also tried to install the camera viewport but we couldn't get the Cu gasket to sit in the recess, so we gave up and will probably reallocate the camera viewport to SR3 for now (where it will go on a different type of flange which we've had success with. Saito-san says that we can get help with the SRM flange from Mirapro on 1/28.
 * SR3
  * We opened the top of the tank briefly to inspect the configuration of the F0 FR, but didn't do any significant work.
  * Hirose-san inspected inside the bottom part of the chamber and found some dust, so he recommended we wipe with Vectra-Alpha wipes (IPA-resistant type) and IPA. he gave us a powerful LED flashlight array and asked us to use it to look for dust in all the chambers.
 * Etc
  * We gave Simon a list of items we still need for the SRM OL. He seemed to think that they should be in stock at Kamioka and will help us look for them next Tue 1/15.
  * Mark and Enzo booked flights for the KAGRA International Workshop.
  * Mark had to schedule a trip to Australia for the week of 1/21 to attend to family business.
==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]]

==== Plan for week of 1/7 ====
 * Make sure BS is floating, recenter OL to capture current yaw position.
 * Vent BS.
 * Inspect BS F0 blades for cracks.
 * Install new BS F0 FR, and (if necessary) auxiliary CuBe spring.
 * Confirm geometry of LVDTs, geophones, FRs etc and update T1707205 if necessary.
 * Replace geophone preamps and cables (to fix noise, offset, pinout flip issues).
 * Add more mass to IP to get lower frequency.
 * Adjust all GAS filters to near mid-range (using keystone mass for F0 as much as possible, and FR+LVDT for SF and BF).

==== Vacation/Etc Info ====
 * Mark and Enzo: KAGRA International Workshop in Perugia, 2/14-16.
 * Terrence: back at Kamioka from 1/7.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 12/17

  • BS
    • We opened the top of the BS tank after the vent.
    • We inspected the BS F0 blades for cracks but still didn't find any.
    • We removed the arc weights and geophones, and added new longer studs for the arc weights and new cables for the geophones. We then put back the original arc weights and new geophones.
    • We measured the geometry of the various IP items to check the IP diagonalization matrices.
    • We installed the new double-sided F0 FR. We were not close to needing to add the optional CuBe spring. Unfortunately the FR had rather less friction but still didn't work. After checking a bunch of possibilities and comparing against SRM (also non-working) and SR2/SR3 (working), we suspect the carriage may be assembled upside down, with the metal plate below and the PEEK plate above. We will try changing it next week.

  • We adjusted the F0 keystone trim mass and were able to get it to sit at CAD nominal height at nominal temperature (24.9°C) with mid-range FR and modest extra mass (413 g). Interestingly, we noticed that removing the arc weights and/or geophones reduced the load capacity by a few hundred grams.
  • We measured the total range of the IP FRs in steps and set them to mid-range in preparation for tuning the IP frequency and (re-)centering the IP.
  • SRM
    • We borrowed an LED from SR2 and set the pitch of the SRM optic.
    • We found the SRM front end had crashed and could not be properly reset by cycling the power from the web interface. Yamamoto-san eventually got it working for us, although it didn't seem to take more than restarting the user and IOP models.
    • We sealed and retested the new geophones originally intended for SRM, but decided to use them on BS instead.
    • We installed the two OL viewports. We also tried to install the camera viewport but we couldn't get the Cu gasket to sit in the recess, so we gave up and will probably reallocate the camera viewport to SR3 for now (where it will go on a different type of flange which we've had success with. Saito-san says that we can get help with the SRM flange from Mirapro on 1/28.
  • SR3
    • We opened the top of the tank briefly to inspect the configuration of the F0 FR, but didn't do any significant work.
    • Hirose-san inspected inside the bottom part of the chamber and found some dust, so he recommended we wipe with Vectra-Alpha wipes (IPA-resistant type) and IPA. he gave us a powerful LED flashlight array and asked us to use it to look for dust in all the chambers.
  • Etc
    • We gave Simon a list of items we still need for the SRM OL. He seemed to think that they should be in stock at Kamioka and will help us look for them next Tue 1/15.
    • Mark and Enzo booked flights for the KAGRA International Workshop.
    • Mark had to schedule a trip to Australia for the week of 1/21 to attend to family business.

To-Do Lists, Schedule

Plan for week of 1/7

  • Make sure BS is floating, recenter OL to capture current yaw position.
  • Vent BS.
  • Inspect BS F0 blades for cracks.
  • Install new BS F0 FR, and (if necessary) auxiliary CuBe spring.

  • Confirm geometry of LVDTs, geophones, FRs etc and update T1707205 if necessary.
  • Replace geophone preamps and cables (to fix noise, offset, pinout flip issues).
  • Add more mass to IP to get lower frequency.
  • Adjust all GAS filters to near mid-range (using keystone mass for F0 as much as possible, and FR+LVDT for SF and BF).

Vacation/Etc Info

  • Mark and Enzo: KAGRA International Workshop in Perugia, 2/14-16.
  • Terrence: back at Kamioka from 1/7.