Differences between revisions 21 and 402 (spanning 381 versions)
Revision 21 as of 2016-06-03 14:29:12
Size: 5968
Editor: MarkBarton
Comment:
Revision 402 as of 2019-03-14 19:08:46
Size: 3649
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 2: Line 2:
Line 5: Line 4:
 * Type B Past Week Summary
  * Fabian worked on IM and dummy BS assembly: [[https://photos.google.com/share/AF1QipMNVSExyP3TuyhK4s_VD-ARDlNoCPCf13ZDbHUlwOw14AKgj4XUe0vYg27dQ12icQ?key=SjJ0dXJ1bjN2OGVCN3d6RnoySEtFSjVJUmVwSlZR|photos1]], [[https://photos.google.com/share/AF1QipPQdoB5vYN1VcD32TkA4QSGldODvKRwiT5h-m122ahSpWmFyyrO5MX-9ajL1LeRIg?key=VFFuUVktcEtlMURQUldhZUlRcGFhbzNDeU5IN3NB|photos2]]
   * A hole in a picomotor holder was too small. ATC staff solved this isue quickly and Hirata-san cleaned the piece.
   * Some ballast discs for the dummy optic were dirty (seen by visual inspection). Hirata-san cleaned them.
   * Some arrows were cleaned from the mirrors for the dummy optic.
  * Hirata-san worked on checking Mirapro's assembly frame design - some minor issues with rail system found.
  * Hirata-san measured another filter.
  * Hirata-san washed a large batch of parts.
  * All parts for gluing of dummy BS are in hand. We arranged with Tatsumi-san to glue magnets at Mitaka on 6/6, glue flags at Kashiwa on 6/8, and inspect bonds and bring dummy BS back to Mitaka 6/13.
  * Mark worked on solutions to allow a [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Subgroups/VIS/TypeB/dummyBS|larger mirror on dummy BS]]. After discussions with Simon and Akutsu-san we decided to go with a stainless steel plate solution. The gluing can go ahead and we can attach the plates later.
  * Mark worked on list of items for purchase in FY2016.
  * Mark worked on finding connectors for vacuum-compatible geophone adapters.
  * Mark worked more on [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235|E1504235 BS Assembly Procedure]] ([[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|Draft on OneDrive]])
 * '''Discussions '''
  * Crane will not be available on 13-14 of June.
  * Review: '''fix the date (Mark) '''
  * Measurement of iKAGRA BS position will be done in the second week of June. Then it will be taken out of the chamber after that (Ohishi)
 * IM, RM, IRM, dummy BS assembly
  * Fabian assembled the dummy BS and started on the IM.
  * Still need to find SDC-treated hook for maraging wire in IM. Still not found. Spare hook is being SDC-treated. Can be added later.
  * Will start assembly 5/30
 * Wires
  * Fabian analysis RM wire thickness versus mode frequency: [[https://onedrive.live.com/redir?resid=1447B05D5B571A84!442&authkey=!AKrjBW2W8vMKyAY&ithint=file,pdf|link]], [[https://onedrive.live.com/redir?resid=1447B05D5B571A84!421&authkey=!ALZY-tFtMCYI9Pw&ithint=file,pdf|another link]],[[https://pfalig.bn1301.livefilestore.com/y3mT7oHnuBfD9_7Ata6H90opTVY5IIIm78MQ8Rl-lChfSUtGhGiEP-mlB1rQuzliimi-pmL1JfYTKCUY_Tgan0Bfa2jq5EeSXWiCracw_5ulsm2iuf6RHJcz0ot34DaeWqdUjFnU6fILnyau69WFkBmUcTwfGYBNwSrs27eyK-jc90/RM_wire.pdf?psid=1|yet another link]] (From last week: [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5106|T1605106]] /[[https://onedrive.live.com/view.aspx?resid=1447B05D5B571A84!354&ithint=file,docx&app=Word&authkey=!AO5CHNP3xlO5RjY|draft]])
 * Can we make SR wire breakers bigger?
  * Fukushima-san has not yet started the work. He will start soon (as of 5/27).
 * Flags, Metal Prisms, Sapphire prisms RECEIVED
 * Mirror box and Flag/Prism gluing
  * All parts in hand.
  * Magnet gluing and check of parts at Mitaka, Monday 6/6.
  * Gluing at Kashiwa, Wednesday 6/8.
  * Inspection of bonds and return to Mitaka, 6/13.
 * An extra structure attached to the EQ stop to prevent tipping over of the BS - no action since last week.
 * Not enough crane height problem (Hirata, Saito) - no action since last week
 * Ballast masses for payload
  * Initial batch received - ordered extra smaller ones to allow for adjustments.
 * Lower breadboard stuff
  * Assembly procedure
   * '''Need to be incorporated into the procedure document. Discuss with Takahashi (Mark)'''
  * Breadboard springs (in manufacture, expected end of July)
  * Nail-head parts: quote from Mirapro received, not urgent, will be combined with assembly frame order.
 * BS Assembly Frame Design (Mark, Hirata)
  * Hirata-san found issues with rail system part - organizing fix.
 * Clean bag
  * Ordered - expected 6/8.
 * 2D and 3D CAD
  * [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5035|E1605035 VIS Document and Drawing Tree (BS)]]
 * Electronics
  * [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=3600|JGW-D1503600 - BS Suspension Cabling]]
  * [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5111|E1605111 BS Suspension Electronic Items List]]
  * [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=3901|D1503901 In-Vacuum Cable Detail]]
  * Item list and timetable was given to Miyakawa-san - some corrections received and added to schematic but not yet posted.
  * Status on AEL boxes OK according to Miyakawa-san.
  * Signal generator and cable to be used for BS test. May order NIKHEF cards later if concern about AC-driven units in racks.
  * Need to get new longer versions of some previously ordered BF-PI and SF-PI cables (Takahashi).
  * Need to check previously ordered TM-BF and IM-BF OSEM cables have been flipped (Takahashi).
  * Decided to hand-make cables for geophones because previously ordered cables have no conductor on pin 5.
  * Stepper drive box (requested by Sekiguchi-san [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=3385|T1503385]]) is being designed, should be ready in time.
  * Mark looking for connectors for geophone adapters.
 * Procedure documents
  * Mark worked on BS Assembly Procedure [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
=== Type B (Mark) ===
==== Report for the week of 3/11 ====
 * Fabian mostly helped Fujii-kun with the PRM.
 * Fabian monitored the SRM yaw drift. It gradually reversed but so far remained small.
 * Mark and Hirata-san debugged the BS:
  * We inspected the payload section and quickly found the problem: two RM EQ stops were touching, on the +L (-X,+Y) side at the top. This was probably because the stops had been adjusted with the IP unlocked and sitting a few mm to -L, whereas now we have the DCCTRL running and have been locking the IP at the LVDT zero. We drove the IP to L=+1.5 mm as a near-worst case, and backed off all the stops to give several mm of margin. Then we zeroed the IP pitch, roll and yaw with the picos.
  * We also opened the top of the BS and confirmed that the mechanical zero defined by the locking mechanism agreed with the LVDT zero. It was very close in L and T, but -728 µrad in Y, driven mostly by a -805 µm offset in H3. That much is probably not a dumb error but just a difference in technique among the three people using calipers to take data for the calibration.
  * We then prepared the BS for close-up:
   * We wiped and inspected the O-ring for the lid and replaced the lid.
   * We wiped all accessible surfaces in the lower half of the tank, rescued some dropped items (some PEEK tube and a small nut) and un-immobilized the LBB.
  * After all the above, the OL was a bit off-center but still on the QPD, and Nagano-san fairly quickly recovered the original alignment.
 * Terrence rebuilt the BS OL according to a new layout suggested by Simon, which avoids scrambling the pitch/yaw at the first steering mirror and greatly reduces the amount of diagonalization required.
 * Terrence noticed some anomalous cross coupling on the SR2 (but not the SR3) and we investigated.
  * We suspected it might be an odd position of the beam spot on the optic, so we took pictures through the camera and LED viewports of SR3, and opened the SR2 tank and used a white target, but the beam spots were in very similar positions - close to central vertically and about 3 cm to the left of center horizontally.
  * We suspected it might be something touching at the IRM (because the IM OSEM TFs were fine), so we checked using a stick mirror with the IP centered, but all EQ stops were well backed off.
  * We suspected it might be a ghost beam from the LEN/TILT beamsplitter (and one was clearly visible on the SR2 TILT QPD) so Terrence set up a beam block, which improved things slightly but not completely.
  * Finally Terrence discovered that the problem was mainly uneven sensitivities of the QPD quadrants, and devised a new calibration and diagonalization procedure which allowed for it.
 * Enzo and Terrence did a health check of the SRM and it was fine except for some apparent electrical noise around 240 Hz. They put in a notch filter to get rid of it for now.

==== Plan for week of 3/18 ====
 * Mark, Fabian, Terrence at Kamioka full week.
 * More OL stuff.
 * SRM controls and Guardian.
 * Reset SRM yaw and continue monitoring yaw drift.
 * Assist with pump down.
 * Work on Type B paper.
 * Tidy up.
  * Throw out foil and other garbage.
  * Gather and clean tools.
  * Gather and organize unused parts and fasteners.
  * Pull out unused cables in cable tray near SR3.
  * Return all unused cables to tent.
  * Tidy up cables in rear of SR2 rack.
  *



==== Vacation/Travel Info ====
 * Enzo at JPS then final vacation, 3/13-29
 * Terrence's last day, 3/29.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for the week of 3/11

  • Fabian mostly helped Fujii-kun with the PRM.
  • Fabian monitored the SRM yaw drift. It gradually reversed but so far remained small.
  • Mark and Hirata-san debugged the BS:
    • We inspected the payload section and quickly found the problem: two RM EQ stops were touching, on the +L (-X,+Y) side at the top. This was probably because the stops had been adjusted with the IP unlocked and sitting a few mm to -L, whereas now we have the DCCTRL running and have been locking the IP at the LVDT zero. We drove the IP to L=+1.5 mm as a near-worst case, and backed off all the stops to give several mm of margin. Then we zeroed the IP pitch, roll and yaw with the picos.
    • We also opened the top of the BS and confirmed that the mechanical zero defined by the locking mechanism agreed with the LVDT zero. It was very close in L and T, but -728 µrad in Y, driven mostly by a -805 µm offset in H3. That much is probably not a dumb error but just a difference in technique among the three people using calipers to take data for the calibration.
    • We then prepared the BS for close-up:
      • We wiped and inspected the O-ring for the lid and replaced the lid.
      • We wiped all accessible surfaces in the lower half of the tank, rescued some dropped items (some PEEK tube and a small nut) and un-immobilized the LBB.
    • After all the above, the OL was a bit off-center but still on the QPD, and Nagano-san fairly quickly recovered the original alignment.
  • Terrence rebuilt the BS OL according to a new layout suggested by Simon, which avoids scrambling the pitch/yaw at the first steering mirror and greatly reduces the amount of diagonalization required.
  • Terrence noticed some anomalous cross coupling on the SR2 (but not the SR3) and we investigated.
    • We suspected it might be an odd position of the beam spot on the optic, so we took pictures through the camera and LED viewports of SR3, and opened the SR2 tank and used a white target, but the beam spots were in very similar positions - close to central vertically and about 3 cm to the left of center horizontally.
    • We suspected it might be something touching at the IRM (because the IM OSEM TFs were fine), so we checked using a stick mirror with the IP centered, but all EQ stops were well backed off.
    • We suspected it might be a ghost beam from the LEN/TILT beamsplitter (and one was clearly visible on the SR2 TILT QPD) so Terrence set up a beam block, which improved things slightly but not completely.
    • Finally Terrence discovered that the problem was mainly uneven sensitivities of the QPD quadrants, and devised a new calibration and diagonalization procedure which allowed for it.
  • Enzo and Terrence did a health check of the SRM and it was fine except for some apparent electrical noise around 240 Hz. They put in a notch filter to get rid of it for now.

Plan for week of 3/18

  • Mark, Fabian, Terrence at Kamioka full week.
  • More OL stuff.
  • SRM controls and Guardian.
  • Reset SRM yaw and continue monitoring yaw drift.
  • Assist with pump down.
  • Work on Type B paper.
  • Tidy up.
    • Throw out foil and other garbage.
    • Gather and clean tools.
    • Gather and organize unused parts and fasteners.
    • Pull out unused cables in cable tray near SR3.
    • Return all unused cables to tent.
    • Tidy up cables in rear of SR2 rack.

Vacation/Travel Info

  • Enzo at JPS then final vacation, 3/13-29
  • Terrence's last day, 3/29.

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)