Line 6: Line 6:
  * Fabian worked on IM and dummy BS assembly: [[https://photos.google.com/share/AF1QipMNVSExyP3TuyhK4s_VD-ARDlNoCPCf13ZDbHUlwOw14AKgj4XUe0vYg27dQ12icQ?key=SjJ0dXJ1bjN2OGVCN3d6RnoySEtFSjVJUmVwSlZR|photos1]], [[https://photos.google.com/share/AF1QipPQdoB5vYN1VcD32TkA4QSGldODvKRwiT5h-m122ahSpWmFyyrO5MX-9ajL1LeRIg?key=VFFuUVktcEtlMURQUldhZUlRcGFhbzNDeU5IN3NB|photos2]]
   * A hole in a picomotor holder was too small. ATC staff solved this isue quickly and Hirata-san cleaned the piece.
   * Some ballast discs for the dummy optic were dirty (seen by visual inspection). Hirata-san cleaned them.
   * Some arrows were cleaned from the mirrors for the dummy optic.
  * Hirata-san worked on checking Mirapro's assembly frame design - some minor issues with rail system found.
  * Hirata-san measured another filter.
  * Hirata-san washed a large batch of parts.
  * All parts for gluing of dummy BS are in hand. We arranged with Tatsumi-san to glue magnets at Mitaka on 6/6, glue flags at Kashiwa on 6/8, and inspect bonds and bring dummy BS back to Mitaka 6/13.
  * Mark worked on solutions to allow a [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Subgroups/VIS/TypeB/dummyBS|larger mirror on dummy BS]]. After discussions with Simon and Akutsu-san we decided to go with a stainless steel plate solution. The gluing can go ahead and we can attach the plates later.
  * Mark worked on list of items for purchase in FY2016.
  * Mark worked on finding connectors for vacuum-compatible geophone adapters.
  * Mark worked more on [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235|E1504235 BS Assembly Procedure]] ([[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|Draft on OneDrive]])
 * '''Discussions '''
  * Crane will not be available on 13-14 of June.
  * Review: '''fix the date (Mark) '''
  * Measurement of iKAGRA BS position will be done in the second week of June. Then it will be taken out of the chamber after that (Ohishi)
 * IM, RM, IRM, dummy BS assembly
  * Fabian assembled the dummy BS and started on the IM.
  * Still need to find SDC-treated hook for maraging wire in IM. Still not found. Spare hook is being SDC-treated. Can be added later.
  * Will start assembly 5/30
 * Wires
  * Fabian analysis RM wire thickness versus mode frequency: [[https://onedrive.live.com/redir?resid=1447B05D5B571A84!442&authkey=!AKrjBW2W8vMKyAY&ithint=file,pdf|link]], [[https://onedrive.live.com/redir?resid=1447B05D5B571A84!421&authkey=!ALZY-tFtMCYI9Pw&ithint=file,pdf|another link]],[[https://pfalig.bn1301.livefilestore.com/y3mT7oHnuBfD9_7Ata6H90opTVY5IIIm78MQ8Rl-lChfSUtGhGiEP-mlB1rQuzliimi-pmL1JfYTKCUY_Tgan0Bfa2jq5EeSXWiCracw_5ulsm2iuf6RHJcz0ot34DaeWqdUjFnU6fILnyau69WFkBmUcTwfGYBNwSrs27eyK-jc90/RM_wire.pdf?psid=1|yet another link]] (From last week: [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5106|T1605106]] /[[https://onedrive.live.com/view.aspx?resid=1447B05D5B571A84!354&ithint=file,docx&app=Word&authkey=!AO5CHNP3xlO5RjY|draft]])
 * Can we make SR wire breakers bigger?
  * Fukushima-san has not yet started the work. He will start soon (as of 5/27).
 * Flags, Metal Prisms, Sapphire prisms RECEIVED
 * Mirror box and Flag/Prism gluing
  * All parts in hand.
  * Magnet gluing and check of parts at Mitaka, Monday 6/6.
  * Gluing at Kashiwa, Wednesday 6/8.
  * Inspection of bonds and return to Mitaka, 6/13.
 * An extra structure attached to the EQ stop to prevent tipping over of the BS - no action since last week.
 * Not enough crane height problem (Hirata, Saito) - no action since last week
 * Ballast masses for payload
  * Initial batch received - ordered extra smaller ones to allow for adjustments.
 * Lower breadboard stuff
  * Assembly procedure
   * '''Need to be incorporated into the procedure document. Discuss with Takahashi (Mark)'''
  * Breadboard springs (in manufacture, expected end of July)
  * Nail-head parts: quote from Mirapro received, not urgent, will be combined with assembly frame order.
 * BS Assembly Frame Design (Mark, Hirata)
  * Hirata-san found issues with rail system part - organizing fix.
 * Clean bag
  * Ordered - expected 6/8.
 * 2D and 3D CAD
  * [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5035|E1605035 VIS Document and Drawing Tree (BS)]]
 * Electronics
  * [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=3600|JGW-D1503600 - BS Suspension Cabling]]
  * [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5111|E1605111 BS Suspension Electronic Items List]]
  * [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=3901|D1503901 In-Vacuum Cable Detail]]
  * Item list and timetable was given to Miyakawa-san - some corrections received and added to schematic but not yet posted.
  * Status on AEL boxes OK according to Miyakawa-san.
  * Signal generator and cable to be used for BS test. May order NIKHEF cards later if concern about AC-driven units in racks.
  * Need to get new longer versions of some previously ordered BF-PI and SF-PI cables (Takahashi).
  * Need to check previously ordered TM-BF and IM-BF OSEM cables have been flipped (Takahashi).
  * Decided to hand-make cables for geophones because previously ordered cables have no conductor on pin 5.
  * Stepper drive box (requested by Sekiguchi-san [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=3385|T1503385]]) is being designed, should be ready in time.
  * Mark looking for connectors for geophone adapters.
 * Procedure documents
  * Mark worked on BS Assembly Procedure [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
  * Mark and Fabian went to Kashiwa to clean up glue residue on the dummy BS and do a fit/function test of Tatsumi-san's modified tooling.
   * Most of the remaining glue came off with soaking in acetone, but there is still some in the machining grooves in the Al surface. Probably more work is required.
   * A set of cleanroom shoes borrowed from the ATC disintegrated when worn (the plastic had perished from age), which put small pieces of foam all over the floor in Hirose-san's cleanroom and required a lot of clean-up with a sticky roller! Cleanroom suits and shoes for use by Type B team at Mitaka/Kashiwa have been ordered, but will take another week to arrive.
   * The flag holding parts are now much easier to place and remove, much reducing the risk of breaking flags after gluing.
   * The sapphire and metal prisms from both the first BS gluing and the PR3 hanging test mirror were brought back to Mitaka for ultrasonic cleaning to remove glue, so they can be reused.
   * We arranged with Hirose-san to collect the dummy BS and mirror box next Thursday 8/4. (This is conditional on the new clean suits arriving.) Further work will be done at Mitaka.
   * Hirata-san arranged to borrow the NAOJ Hi-Ace van for the trip.
  * Hirata-san found the SR versions of the screws for immobilizing the IM and IRM. These fit much better than the BS ones (despite being the same design) and will be used for the BS.
  * Fabian worked on design of the extra 600 g of trim mass that will be needed for the IM.
  * Fabian updated the [[attachment:Geophone_Kamioka.png|geophone noise plot]] with a more accurate calibration and also plotted the [[attachment:Geophone_Kamioka_noise_ratio.png|S/N over readout noise]].
 * Type B ongoing issues
  * OSEMs
   * Akutsu-san is working to get wide-mouth OSEMs ([[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1853|2 assembled]]; first 4 expected to be assembled and washed by 8/8)
  * Longer cables for BF->PI and SF->PI.
   * Connectors RECEIVED, cables being made.
  * SR machining test ongoing.
  * Lower breadboard stuff
   * Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
   * Breadboard springs (in manufacture, expected end of July)
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
 * To-do list during Mark's vacation
  * Weigh IM/RM/IRM (Fabian, Hirata) - DONE but anomalies found.
  * Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian).
  * Analyze geophone data (Fabian/Shoda) - data taken by Shoda-san; Fabian to find calibration factors.
  * Remove glue from dummy BS face (Fabian) - partly done.
  * Reglue flags and prisms (Tatsumi, Fabian)
  * Clean wire for BS and RM (Hirata) - DONE
  * Get new winch parts for new wire diameters - design received from Ikenoue-san
  * Do fit/function test of winches (Fabian/Hirata)
  * Ship winches to Kamioka (Hirata/Fabian)
  * Work on BS simulation (Fabian)
  * Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - ONGOING.
  * Write more of payload assembly procedure (Fabian)
  * Write more of main assembly procedure (Mark)
 * Longer term to-do list
  * Do BS Simulink model (Mark, Kokeyama)
  * Do 2D drawings of SR2 parts (Hirata)
  * Redesign SRx IM wire clamps for larger prisms, remachined RMs.
  * Order SRM/PRM parts (Hirata/Shoda)
  * Order SRx fasteners (Hirata)
  * Check SR RM machining test progress (Hirata)

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

  • Type B Past Week Summary
    • Mark and Fabian went to Kashiwa to clean up glue residue on the dummy BS and do a fit/function test of Tatsumi-san's modified tooling.
      • Most of the remaining glue came off with soaking in acetone, but there is still some in the machining grooves in the Al surface. Probably more work is required.
      • A set of cleanroom shoes borrowed from the ATC disintegrated when worn (the plastic had perished from age), which put small pieces of foam all over the floor in Hirose-san's cleanroom and required a lot of clean-up with a sticky roller! Cleanroom suits and shoes for use by Type B team at Mitaka/Kashiwa have been ordered, but will take another week to arrive.
      • The flag holding parts are now much easier to place and remove, much reducing the risk of breaking flags after gluing.
      • The sapphire and metal prisms from both the first BS gluing and the PR3 hanging test mirror were brought back to Mitaka for ultrasonic cleaning to remove glue, so they can be reused.
      • We arranged with Hirose-san to collect the dummy BS and mirror box next Thursday 8/4. (This is conditional on the new clean suits arriving.) Further work will be done at Mitaka.
      • Hirata-san arranged to borrow the NAOJ Hi-Ace van for the trip.
    • Hirata-san found the SR versions of the screws for immobilizing the IM and IRM. These fit much better than the BS ones (despite being the same design) and will be used for the BS.
    • Fabian worked on design of the extra 600 g of trim mass that will be needed for the IM.
    • Fabian updated the geophone noise plot with a more accurate calibration and also plotted the S/N over readout noise.

  • Type B ongoing issues
    • OSEMs
      • Akutsu-san is working to get wide-mouth OSEMs (2 assembled; first 4 expected to be assembled and washed by 8/8)

    • Longer cables for BF->PI and SF->PI.

      • Connectors RECEIVED, cables being made.
    • SR machining test ongoing.
    • Lower breadboard stuff
      • Installation to be incorporated into the procedure document. Mark/Takahashi to discuss.
      • Breadboard springs (in manufacture, expected end of July)
    • Documents
  • To-do list during Mark's vacation
    • Weigh IM/RM/IRM (Fabian, Hirata) - DONE but anomalies found.
    • Pack/ship IM/RM/IRM to Kamioka (Hirata/Fabian).
    • Analyze geophone data (Fabian/Shoda) - data taken by Shoda-san; Fabian to find calibration factors.
    • Remove glue from dummy BS face (Fabian) - partly done.
    • Reglue flags and prisms (Tatsumi, Fabian)
    • Clean wire for BS and RM (Hirata) - DONE
    • Get new winch parts for new wire diameters - design received from Ikenoue-san
    • Do fit/function test of winches (Fabian/Hirata)
    • Ship winches to Kamioka (Hirata/Fabian)
    • Work on BS simulation (Fabian)
    • Do Inventor assembly for SR2 in chamber and on assembly frame (Hirata) - ONGOING.
    • Write more of payload assembly procedure (Fabian)
    • Write more of main assembly procedure (Mark)
  • Longer term to-do list
    • Do BS Simulink model (Mark, Kokeyama)
    • Do 2D drawings of SR2 parts (Hirata)
    • Redesign SRx IM wire clamps for larger prisms, remachined RMs.
    • Order SRM/PRM parts (Hirata/Shoda)
    • Order SRx fasteners (Hirata)
    • Check SR RM machining test progress (Hirata)