Size: 1557
Comment:
|
Size: 1822
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 6: | Line 6: |
==== Past week report ==== * Mark created screens and a macro.txt file for the SR2 and linked to them from the VIS screen. * Enzo and Mark did a new overview screen for the BS. * Enzo added DIO cards to the rack and connected them to the coil drivers. * Fabian and Kozu-kun finished assembling the IM and tested the picos over their full range. * Mark and Hirata-san configured and aligned the assembly frame and optical table and craned in the IM ring. * Hirata-san noticed some oxidization on several of the L-brackets that will hold the IM horizontally, and we should get them cleaned or machined, but we can probably continue with hanging the system in the meantime. |
==== Report for week of 12/25 ==== * Hirata-san got the L-brackets machined and washed, and installed them on the IM ring bars. * Shoda-san recovered the BS from the power outage on 12/25. * Miyakawa-san fixed an issue with the SR2 RTM which had prevented it from running. * Shoda-san, Hirata-san and Kozu-kun weighed the IM without ballast masses, and then added the lower masses and installed the IM on the assembly frame. * They cleaned the assembly frame and installed new jack receptacles on the load gauge adapter. * They installed the winch system on the IM, and inspected the clamp pieces for possible scratches. * They ran cables for the SR2 steppers and OSEMs. * They calibrated the BF LVDT. |
Line 14: | Line 16: |
==== Report for week of 1/4 ==== * Mark fixed a number of errors with the Type B screens. |
|
Line 15: | Line 19: |
==== Plan for week of 12/25 ==== * Power outage 12/25. * Mark, Enzo, Fabian vacation * Shoda-san, Kozu-kun, Hirata-san at Kamioka - Hirata-san from Tue, others TBD. * Recover after power outage. * Create SR2 real-time model. * Install new jack receptacles (in SR3 area, second floor) on load gauge adapter (SR2 area, second floor). (Hirata-san) * Weigh IM (per Fabian's note in the paper log). * Remove L-brackets from bars on IM ring - send for cleaning/remachining. * Setup OL for checking pitch of SR. * Wipe/blow dust off SR2 frame. * Crane IM into frame. |
==== Report for week of 1/9 ==== * We weighed the mirror in its box (and later the empty box), and the RM. * Fabian worked on the SR2/SR3/SRM mass budget and did an inventory of spare ballast masses. * We hung the SR2 and RM. * We assembled the bottom section of the security structure below the RM. * Hirata-san gave up on waiting for a third quote for the blades and blade parts and started the ordering process. * Hirata-san got rod cable clamp parts from Takahashi-san and worked on drawings for the improved BS vertical and yaw adjusters. |
Line 28: | Line 27: |
==== Plan for week of 1/9 ==== | ==== Plan for week of 1/15 ==== * Shoda-san at Mitaka making OSEMs. * ==== Plan for week of 1/22 ==== ==== Plan for week of 1/22 ==== |
Line 33: | Line 37: |
* Enzo 1/30-2/19 | * Enzo 1/30-2/19 (at Mitaka 1/29, part of 1/30) * Kozu-kun 1/29-2/2 |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 12/25
- Hirata-san got the L-brackets machined and washed, and installed them on the IM ring bars.
- Shoda-san recovered the BS from the power outage on 12/25.
- Miyakawa-san fixed an issue with the SR2 RTM which had prevented it from running.
- Shoda-san, Hirata-san and Kozu-kun weighed the IM without ballast masses, and then added the lower masses and installed the IM on the assembly frame.
- They cleaned the assembly frame and installed new jack receptacles on the load gauge adapter.
- They installed the winch system on the IM, and inspected the clamp pieces for possible scratches.
- They ran cables for the SR2 steppers and OSEMs.
- They calibrated the BF LVDT.
Report for week of 1/4
- Mark fixed a number of errors with the Type B screens.
Report for week of 1/9
- We weighed the mirror in its box (and later the empty box), and the RM.
- Fabian worked on the SR2/SR3/SRM mass budget and did an inventory of spare ballast masses.
- We hung the SR2 and RM.
- We assembled the bottom section of the security structure below the RM.
- Hirata-san gave up on waiting for a third quote for the blades and blade parts and started the ordering process.
- Hirata-san got rod cable clamp parts from Takahashi-san and worked on drawings for the improved BS vertical and yaw adjusters.
Plan for week of 1/15
- Shoda-san at Mitaka making OSEMs.
Plan for week of 1/22
Plan for week of 1/22
- Mark, Fabian, Enzo, Shoda-san at Kamioka Tue-Fri.
- Hang SR and RM.
Vacation Info
- Enzo 1/30-2/19 (at Mitaka 1/29, part of 1/30)
- Kozu-kun 1/29-2/2