==== Report for week of 12/25 ==== * Hirata-san got the L-brackets machined and washed, and installed them on the IM ring bars. * Shoda-san recovered the BS from the power outage on 12/25. * Miyakawa-san fixed an issue with the SR2 RTM which had prevented it from running. * Shoda-san, Hirata-san and Kozu-kun weighed the IM without ballast masses, and then added the lower masses and installed the IM on the assembly frame. * They cleaned the assembly frame and installed new jack receptacles on the load gauge adapter. * They installed the winch system on the IM, and inspected the clamp pieces for possible scratches. * They ran cables for the SR2 steppers and OSEMs. * They calibrated the BF LVDT. |
==== Report for week of 1/29 ==== * We moved the top filter intended for SR2 (#1) into the SR3 cleanbooth. * Unfortunately we noticed one of the blades had many small X-shaped stress fractures on the top surface (klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=4058|4058]]). * We moved the top filter entered for SR3 (#3) into the SRM cleanbooth and inspected the blades. Two had one smallish stress fracture each and one had a huge fracture and looks close to failing (klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=4061|4061]]). * We referred the BS OL. * We removed the BS tank lid and inspected the BS top filter blades. They seemed fine (klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=4073|4073]]). * Hirata-san received and washed some ferromagnetic disks for IM flags and other small parts. * Hirata-san moved the BF with the tilted keystone (#1) out of the cleanbooth in preparation for rebuilding. * Hirata-san placed the second order for payload parts, and an order for remachining of nuts for cable clamps on rods. * Fabian measured the gain of the ADC system (homework from the Commissioning Workshop). ==== Plan for week of 2/5 ==== * Enzo on vacation; all others at Kamioka. * - * Make in-air pico adapter cables. * Calibrate LVDT. * Test IM picos and BF yaw pico. * Test FR. * Install ballast mass in BF. * Build IRM around IM. * Cable/test/adjust IM OSEMs. * Time permitting, do TFs from IM OSEMs to themselves and to optical sensor. |
Line 16: | Line 29: |
==== Report for week of 1/4 ==== * Mark fixed a number of errors with the Type B screens. |
==== Plan for week of 2/13 ==== * No work Monday (建国記念の日の振替休日)<<BR>> * Enzo on vacation * Hirata-san at Mitaka Tue, Wed (to receive and wash parts). * All others at Kamioka. * - * Lift BF/... section and check total mass and balance. * Cable and test BF picos. |
Line 19: | Line 38: |
==== Report for week of 1/9 ==== * We weighed the mirror in its box (and later the empty box), and the RM. * Fabian worked on the SR2/SR3/SRM mass budget and did an inventory of spare ballast masses. * We hung the SR2 and RM. * We assembled the bottom section of the security structure below the RM. * Hirata-san gave up on waiting for a third quote for the blades and blade parts and started the ordering process. * Hirata-san got rod cable clamp parts from Takahashi-san and worked on drawings for the improved BS vertical and yaw adjusters. ==== Plan for week of 1/15 ==== * Shoda-san at Mitaka making OSEMs. * ==== Plan for week of 1/22 ==== ==== Plan for week of 1/22 ==== * Mark, Fabian, Enzo, Shoda-san at Kamioka Tue-Fri. * Hang SR and RM. |
==== Plan for week of 2/19 ==== * Add section of SS up to SF ring. * Bring in SF. * Add Cu segments to SF cap. * Hook BF/... section. * Route cables up to under SF. * Check/adjust total mass of BF/... section. |
Line 37: | Line 47: |
* Enzo 1/30-2/19 (at Mitaka 1/29, part of 1/30) * Kozu-kun 1/29-2/2 |
* Enzo 1/30-2/19 (at Mitaka 1/29, part of 1/30). * Fabian 4/2-4/27 vacation (then gone). |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 1/29
- We moved the top filter intended for SR2 (#1) into the SR3 cleanbooth.
Unfortunately we noticed one of the blades had many small X-shaped stress fractures on the top surface (klog 4058).
We moved the top filter entered for SR3 (#3) into the SRM cleanbooth and inspected the blades. Two had one smallish stress fracture each and one had a huge fracture and looks close to failing (klog 4061).
- We referred the BS OL.
We removed the BS tank lid and inspected the BS top filter blades. They seemed fine (klog 4073).
- Hirata-san received and washed some ferromagnetic disks for IM flags and other small parts.
- Hirata-san moved the BF with the tilted keystone (#1) out of the cleanbooth in preparation for rebuilding.
- Hirata-san placed the second order for payload parts, and an order for remachining of nuts for cable clamps on rods.
- Fabian measured the gain of the ADC system (homework from the Commissioning Workshop).
Plan for week of 2/5
- Enzo on vacation; all others at Kamioka.
- -
- Make in-air pico adapter cables.
- Calibrate LVDT.
- Test IM picos and BF yaw pico.
- Test FR.
- Install ballast mass in BF.
- Build IRM around IM.
- Cable/test/adjust IM OSEMs.
- Time permitting, do TFs from IM OSEMs to themselves and to optical sensor.
Plan for week of 2/13
No work Monday (建国記念の日の振替休日)
- Enzo on vacation
- Hirata-san at Mitaka Tue, Wed (to receive and wash parts).
- All others at Kamioka.
- -
- Lift BF/... section and check total mass and balance.
- Cable and test BF picos.
Plan for week of 2/19
- Add section of SS up to SF ring.
- Bring in SF.
- Add Cu segments to SF cap.
- Hook BF/... section.
- Route cables up to under SF.
- Check/adjust total mass of BF/... section.
Vacation Info
- Enzo 1/30-2/19 (at Mitaka 1/29, part of 1/30).
- Fabian 4/2-4/27 vacation (then gone).