2620
Comment:
|
1829
|
Deletions are marked like this. | Additions are marked like this. |
Line 6: | Line 6: |
==== Report for week of 12/25 ==== * Hirata-san got the L-brackets machined and washed, and installed them on the IM ring bars. * Shoda-san recovered the BS from the power outage on 12/25. * Miyakawa-san fixed an issue with the SR2 RTM which had prevented it from running. * Shoda-san, Hirata-san and Kozu-kun weighed the IM without ballast masses, and then added the lower masses and installed the IM on the assembly frame. * They cleaned the assembly frame and installed new jack receptacles on the load gauge adapter. * They installed the winch system on the IM, and inspected the clamp pieces for possible scratches. * They ran cables for the SR2 steppers and OSEMs. * They calibrated the BF LVDT. |
==== Report for week of 1/29 ==== * Mark made two sets of in-air pico splitter cables (each with a triple for IM and a double for BF) for SR2 and SR3. * Fabian, Hirata-san and Kozu-kun worked on cabling and testing the IM pitch/roll/yaw picos, the BF FR and the BF LVDT. The LVDT connections were initially unreliable and Hirata-san had to redo the pins on the coil wires. * Fabian installed ballast masses in the BF. * Mark worked on schedule. * Mark did inventory of the stepper motor drivers (many were not accounted for on the wiki and/or JGWDoc and one is missing) and reserved two for SR3. * We emptied out the external cleanroom in preparation for installing SS sheet. |
Line 16: | Line 14: |
==== Report for week of 1/4 ==== * Mark fixed a number of errors with the Type B screens. ==== Report for week of 1/9 ==== * We weighed the mirror in its box (and later the empty box), and the RM. * Fabian worked on the SR2/SR3/SRM mass budget and did an inventory of spare ballast masses. * We hung the SR2 and RM. * We assembled the bottom section of the security structure below the RM. * We cabled the RM OSEMs up to the IM. * Hirata-san gave up on waiting for a third quote for the blades and blade parts and started the ordering process. * Hirata-san got rod cable clamp parts from Takahashi-san and worked on drawings for the improved BS vertical and yaw adjusters. ==== Plan for week of 1/15 ==== * Fabian at Mitaka Monday 1/15 to inspect filter load test items. * All at Kamioka. * Shoda-san to work on readjusting PR3 and also making OSEMs. * Enzo and Kozu-kun to help with making OSEMs. * Test RM OSEMs. * Check coil driver is successfully driving current. * Time permitting, do TF test from coils to optical sensor. * Suspend IM using load gauge adapter, and check/adjust total mass and balance. ==== Plan for week of 1/22 ==== * All at Kamioka * Bring in BF and suspend IM. * Route final RM/IM cables up to below BF. * Recheck/adjust total mass and balance. * Route selected cables to flange. * Test IM picos and BF yaw pico. ==== Plan for week of 1/29 ==== * Enzo at Mitaka 1/29 and most of 1/30, then vacation. * Kozu-kun away. |
==== Plan for week of 2/13 ==== * No work Monday (建国記念の日の振替休日) * Enzo on vacation * Hirata-san at Mitaka Tue (self-evaluation interview). * Shoda-san at Mitaka. |
Line 50: | Line 20: |
* - | |
Line 52: | Line 23: |
* Time permitting, do TFs from IM OSEMs to themselves and to optical sensor. | * Do TFs from IM OSEMs to IM OSEMs, OL pitch/yaw. ==== Plan for week of 2/19 ==== * Enzo back from Tuesday. * Shoda-san at Mitaka. * Hirata-san at Mitaka Mon+Tue (to receive and wash parts). * All others at Kamioka. * - * Lift BF/... section and check total mass and balance. * Cable and test BF picos. * Add section of SS up to SF ring. * Bring in SF. * Hook BF/... section. * Route cables up to under SF. * Check/adjust total mass of BF/... section. ==== Plan for week of 2/26 ==== * Shoda-san at Mitaka. * - * Add Cu segments to SF cap. * Lift SF/... section and check total mass and balance. |
Line 55: | Line 46: |
* Enzo 1/30-2/19 (at Mitaka 1/29, part of 1/30) * Kozu-kun 1/29-2/2 |
* Enzo 1/30-2/19. * Fabian 4/2-4/27 vacation (then gone). |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 1/29
- Mark made two sets of in-air pico splitter cables (each with a triple for IM and a double for BF) for SR2 and SR3.
- Fabian, Hirata-san and Kozu-kun worked on cabling and testing the IM pitch/roll/yaw picos, the BF FR and the BF LVDT. The LVDT connections were initially unreliable and Hirata-san had to redo the pins on the coil wires.
- Fabian installed ballast masses in the BF.
- Mark worked on schedule.
- Mark did inventory of the stepper motor drivers (many were not accounted for on the wiki and/or JGWDoc and one is missing) and reserved two for SR3.
- We emptied out the external cleanroom in preparation for installing SS sheet.
Plan for week of 2/13
- No work Monday (建国記念の日の振替休日)
- Enzo on vacation
- Hirata-san at Mitaka Tue (self-evaluation interview).
- Shoda-san at Mitaka.
- All others at Kamioka.
- -
- Build IRM around IM.
- Cable/test/adjust IM OSEMs.
- Do TFs from IM OSEMs to IM OSEMs, OL pitch/yaw.
Plan for week of 2/19
- Enzo back from Tuesday.
- Shoda-san at Mitaka.
- Hirata-san at Mitaka Mon+Tue (to receive and wash parts).
- All others at Kamioka.
- -
- Lift BF/... section and check total mass and balance.
- Cable and test BF picos.
- Add section of SS up to SF ring.
- Bring in SF.
- Hook BF/... section.
- Route cables up to under SF.
- Check/adjust total mass of BF/... section.
Plan for week of 2/26
- Shoda-san at Mitaka.
- -
- Add Cu segments to SF cap.
- Lift SF/... section and check total mass and balance.
Vacation Info
- Enzo 1/30-2/19.
- Fabian 4/2-4/27 vacation (then gone).