Size: 2191
Comment:
|
Size: 1275
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 5: | Line 5: |
* Type B Past Week Summary * Fabian finished dummy BS assembly. * Mark and Tatsumi-san glued magnets into both types of BS optic flags, and discs into BS IM flags. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1815 |klog]] Two optic flags had to be redone because the magnets moved while the glue was drying. Hirata-san helped remove the magnets with acetone in the ultrasonic cleaner. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1818|klog]] * Tatsumi-san, Fabian and Mark took the dummy BS to Kashiwa and glued the flags and prisms. We will check status on Mon 6/13. * Hirata-san measured another filter. * Hirata-san washed a batch of parts. * Hirata-san worked on work platforms for the installation. * Hirata-san looked for a crane scale for use at the site. (We decided the 500 kg version of the one used at TAMA.) * Hirata-san worked on making some guide parts for the PI installation (Misumi parts with minor additional machining from ATC). * We finalized a design for simple SS mirror parts for the dummy BS with Akutsu-san. They will be made by ATC. * Mark worked on list of items for purchase in FY2016 and on the schedule. * Fabian did more work on the IM assembly. It is nearly done and he will start on the RM next week. * Type B ongoing issues * Can we make SR wire breakers bigger? * Fukushima-san will start on machining test soon (as of 5/27). * Not enough crane height problem (Hirata, Saito) - no action since last week * Ballast masses for payload * Initial batch received - ordered extra smaller ones to allow for adjustments. * Lower breadboard stuff * '''Need to be incorporated into the procedure document. Discuss with Takahashi (Mark)''' * Breadboard springs (in manufacture, expected end of July) * Nail-head parts: quote from Mirapro received, not urgent, will be combined with assembly frame order. * Clean bag - expected 6/8. * Documents * BS Assembly Procedure [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] |
=== Type B (Mark) === ==== Report for week of 7/30 ==== * ==== Plan for week of 8/6 ==== * Mark, Enzo, Hirata-san, Fabian, Kozu-kun, Terrence, Panwei at Kamioka Mon-Fri. * Kozu-kun works at Mozumi Mon, Fri, and Thu afternoon. ===== SR3 ===== * Finalize optic pitch, OSEM alignment. * Do TFs with temporary OL. * Install final OL. * Hook LBB, add ballast mass, set up temporary OL (horizontal beam, pitch/yaw only). ===== SR2 ===== * Add estimated final ballast mass. * Do PI cable routing. * Adjust ballast/trim mass, with reserve for cables. ===== SRM ===== * Assemble metal mass. * Glue prisms, flags. * Reconfigure, align assembly frame. * Tune F0 for SRM. * Add LBB blade units, cable clamps etc. * Check PI coil connections, IP LVDT magnets. ==== To-Do Lists, Schedule ==== * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]] * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]] * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]] ==== Vacation Info ==== * Terrence: 8/24-26 f2f, then returns to Hong Kong. * Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile. |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 7/30
Plan for week of 8/6
- Mark, Enzo, Hirata-san, Fabian, Kozu-kun, Terrence, Panwei at Kamioka Mon-Fri.
- Kozu-kun works at Mozumi Mon, Fri, and Thu afternoon.
SR3
- Finalize optic pitch, OSEM alignment.
- Do TFs with temporary OL.
- Install final OL.
- Hook LBB, add ballast mass, set up temporary OL (horizontal beam, pitch/yaw only).
SR2
- Add estimated final ballast mass.
- Do PI cable routing.
- Adjust ballast/trim mass, with reserve for cables.
SRM
- Assemble metal mass.
- Glue prisms, flags.
- Reconfigure, align assembly frame.
- Tune F0 for SRM.
- Add LBB blade units, cable clamps etc.
- Check PI coil connections, IP LVDT magnets.
To-Do Lists, Schedule
Vacation Info
- Terrence: 8/24-26 f2f, then returns to Hong Kong.
- Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.