2191
Comment:
|
2427
|
Deletions are marked like this. | Additions are marked like this. |
Line 5: | Line 5: |
* Type B Past Week Summary * Fabian finished dummy BS assembly. * Mark and Tatsumi-san glued magnets into both types of BS optic flags, and discs into BS IM flags. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1815 |klog]] Two optic flags had to be redone because the magnets moved while the glue was drying. Hirata-san helped remove the magnets with acetone in the ultrasonic cleaner. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1818|klog]] * Tatsumi-san, Fabian and Mark took the dummy BS to Kashiwa and glued the flags and prisms. We will check status on Mon 6/13. * Hirata-san measured another filter. * Hirata-san washed a batch of parts. * Hirata-san worked on work platforms for the installation. * Hirata-san looked for a crane scale for use at the site. (We decided the 500 kg version of the one used at TAMA.) * Hirata-san worked on making some guide parts for the PI installation (Misumi parts with minor additional machining from ATC). * We finalized a design for simple SS mirror parts for the dummy BS with Akutsu-san. They will be made by ATC. * Mark worked on list of items for purchase in FY2016 and on the schedule. * Fabian did more work on the IM assembly. It is nearly done and he will start on the RM next week. * Type B ongoing issues * Can we make SR wire breakers bigger? * Fukushima-san will start on machining test soon (as of 5/27). * Not enough crane height problem (Hirata, Saito) - no action since last week * Ballast masses for payload * Initial batch received - ordered extra smaller ones to allow for adjustments. * Lower breadboard stuff * '''Need to be incorporated into the procedure document. Discuss with Takahashi (Mark)''' * Breadboard springs (in manufacture, expected end of July) * Nail-head parts: quote from Mirapro received, not urgent, will be combined with assembly frame order. * Clean bag - expected 6/8. * Documents * BS Assembly Procedure [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] |
=== Type B (Mark) === ==== Report for week of 11/12 ==== * SRM * Hirata-san and Mark craned the LBB ring sandwich to the ceiling of the lower half of the tank, and set the heights of the jacks on the upper half. * Fabian and Hirata-san finished the in-vacuum cabling. * Enzo ran DC power to the second SRM stepper driver and did the rest of the in-air cabling. * We're now ready for final tests of the SF/... items and initial tests of the PI items. * Enzo and Fujii-kun built three geophones for SRM. * Mark worked on the height budget. * SR2 * Enzo experimented with [[http://www2.mpq.mpg.de/~ros/geo600_docu/soft/liso/manual.pdf|LISO]] (circuit analysis software which, among other functions, can fit measured TFs with a ZPK model) but then wrote his own fitting software in Python and used it to build Foton models of key TFs of the SR2. (These are in slots FM6-FM8 of the DAMP blocks and should not be accidentally enabled.) ==== To-Do Lists, Schedule ==== * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]] * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]] * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]] ==== Plan for week of 11/19 ==== * Friday 11/23 is Labor Thanksgiving Day. * Mark, Enzo and Fabian at Kamioka Mon-Thu. * Hirata-san at Kamioka Tue-Thu (Mitaka on Mon for Engineering Promotion Office meeting). ===== SRM ===== * Go/no-go test of all electronics items, especially SF/... section. * Finish vertical height check and adjust SF trim mass as required. * Unlock IP and center roughly. * Check/adjust alignment of SS. * Calibrate IP LVDTs. * Add arc weights and geophones. * Improve centering/tuning of IP and SS alignment. * Disconnect cables at feedthroughs, lock suspension. * Crane into tank. ===== SR2 ===== * Assist MIF team with pico cables and LBB breadboard ballast. * Install SR2 OL pillar and shelf (with AOL supervision)? ==== Plan for week of 11/26 ==== * Move SRM in-air cables over to tank. * Remove First Contact. * Unlock and align SRM. * Hook and roughly ballast LBB. ==== Plan for week of 12/3 ==== * f2f Meeting at NAOJ - no Kamioka work. ==== Vacation/Event Info ==== * Hirata-san at Mitaka, Mon 11/19 (Engineering Promotion Office meeting). |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 11/12
- SRM
- Hirata-san and Mark craned the LBB ring sandwich to the ceiling of the lower half of the tank, and set the heights of the jacks on the upper half.
- Fabian and Hirata-san finished the in-vacuum cabling.
- Enzo ran DC power to the second SRM stepper driver and did the rest of the in-air cabling.
- We're now ready for final tests of the SF/... items and initial tests of the PI items.
- Enzo and Fujii-kun built three geophones for SRM.
- Mark worked on the height budget.
- SR2
Enzo experimented with LISO (circuit analysis software which, among other functions, can fit measured TFs with a ZPK model) but then wrote his own fitting software in Python and used it to build Foton models of key TFs of the SR2. (These are in slots FM6-FM8 of the DAMP blocks and should not be accidentally enabled.)
To-Do Lists, Schedule
Plan for week of 11/19
- Friday 11/23 is Labor Thanksgiving Day.
- Mark, Enzo and Fabian at Kamioka Mon-Thu.
- Hirata-san at Kamioka Tue-Thu (Mitaka on Mon for Engineering Promotion Office meeting).
SRM
- Go/no-go test of all electronics items, especially SF/... section.
- Finish vertical height check and adjust SF trim mass as required.
- Unlock IP and center roughly.
- Check/adjust alignment of SS.
- Calibrate IP LVDTs.
- Add arc weights and geophones.
- Improve centering/tuning of IP and SS alignment.
- Disconnect cables at feedthroughs, lock suspension.
- Crane into tank.
SR2
- Assist MIF team with pico cables and LBB breadboard ballast.
- Install SR2 OL pillar and shelf (with AOL supervision)?
Plan for week of 11/26
- Move SRM in-air cables over to tank.
- Remove First Contact.
- Unlock and align SRM.
- Hook and roughly ballast LBB.
Plan for week of 12/3
- f2f Meeting at NAOJ - no Kamioka work.
Vacation/Event Info
- Hirata-san at Mitaka, Mon 11/19 (Engineering Promotion Office meeting).