 * Type B Past Week Summary
  * Fabian finished dummy BS assembly.
  * Mark and Tatsumi-san glued magnets into both types of BS optic flags, and discs into BS IM flags. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1815 |klog]] Two optic flags had to be redone because the magnets moved while the glue was drying. Hirata-san helped remove the magnets with acetone in the ultrasonic cleaner. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1818|klog]]
  * Tatsumi-san, Fabian and Mark took the dummy BS to Kashiwa and glued the flags and prisms. We will check status on Mon 6/13.
  * Hirata-san measured another filter.
  * Hirata-san washed a batch of parts.
  * Hirata-san worked on work platforms for the installation.
  * Hirata-san looked for a crane scale for use at the site. (We decided the 500 kg version of the one used at TAMA.)
  * Hirata-san worked on making some guide parts for the PI installation (Misumi parts with minor additional machining from ATC).
  * We finalized a design for simple SS mirror parts for the dummy BS with Akutsu-san. They will be made by ATC.
  * Mark worked on list of items for purchase in FY2016 and on the schedule.
  * Fabian did more work on the IM assembly. It is nearly done and he will start on the RM next week.
 * Type B ongoing issues
  * Can we make SR wire breakers bigger?
   * Fukushima-san will start on machining test soon (as of 5/27).
  * Not enough crane height problem (Hirata, Saito) - no action since last week
  * Ballast masses for payload
   * Initial batch received - ordered extra smaller ones to allow for adjustments.
  * Lower breadboard stuff
   * '''Need to be incorporated into the procedure document. Discuss with Takahashi (Mark)'''
   * Breadboard springs (in manufacture, expected end of July)
   * Nail-head parts: quote from Mirapro received, not urgent, will be combined with assembly frame order.
  * Clean bag - expected 6/8.
 * Documents
  * BS Assembly Procedure [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
=== Type B (Mark) ===
==== Report for the week of 2/25 ====

 * Fabian monitored suspensions during the vent.
 * Terrence and Mark made lots of changes to the Guardians and RTMs:
  * Added UI to take snapshots with ALIGNED/MISALIGNED channels (for late use by Guardian).
  * Changed "IM1" and "IM2" in channel names to "IMV" and "IMH"; also "DIO" and "BO" -> "BIO".
  * Created library blocks for BIO and made all the Type B models use them.
  * Tweaked the control topology to be more LIGO-style: the error signal for DC control is sensor-setpoint (not setpoint-sensor as in many controls textbooks); the input to the damping block is the uninverted sensor signal(s); there is a hard-wired -1 after the damping block representing default negative gain.
 * Fabian went inside the SRM chamber and diagnosed the problem that had appeared shortly before vent. It turned out to be yaw of the IP causing a payload cable to touch. He fixed it with the F0 yaw stepper. (He had tried this earlier without success but it turned out the problem was another dead output on the stepper driver.)
 * Terrence traced the geophone issue to a group of dead channels (#20-23) on the AA chassis. We tried replacing the chassis and it fixed not only the geophone issue but an issue in the TILT OL path (#24-27) that we had planned to debug next.
 * We retested the BIO for stepper remote enable system and this time it was working (probably due to the refactoring of the BIO stuff in the model and/or all the restarts).
 * We rebuilt all the IOP models after removing an unneeded ADC1 block (corresponding to hardware that Yoshizawa-san had removed).
 * Enzo and Terrence wrote Python scripts to automate the process of adapting the control filters to the new topology (where the DAMP and DCCTRL functions are in parallel instead of series).
==== Plan for week of 3/4 ====
 * Enzo at Mitaka.
 * Mark, Fabian Mon-Wed (Thu is farewell party).
 * Final tweaks of SRM?
 * Monitor (re-)pumpdown.
 * Tests of new Guardian.
 * Final test of stepper remote enable system (someone in cleanroom checks the lights go on/off).
 * Continue monitoring SRM yaw drift.
 * Setup SRM and SR3 LEN OLs.
 * Work on Type B paper.

==== Plan for week of 3/11 =====
 * Mark at Kamioka full week?
 * Enzo at Kamioka Mon, Tue, then JPS.
 *
==== Vacation/Travel Info ====
 * Enzo vacation, 3/5 and 3/6.
 * Enzo et al. Farewell Party, 3/7.
 * Enzo at JPS then final vacation, 3/13-29
 * Terrence's last day, 3/29.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for the week of 2/25

  • Fabian monitored suspensions during the vent.
  • Terrence and Mark made lots of changes to the Guardians and RTMs:
    • Added UI to take snapshots with ALIGNED/MISALIGNED channels (for late use by Guardian).
    • Changed "IM1" and "IM2" in channel names to "IMV" and "IMH"; also "DIO" and "BO" -> "BIO".

    • Created library blocks for BIO and made all the Type B models use them.
    • Tweaked the control topology to be more LIGO-style: the error signal for DC control is sensor-setpoint (not setpoint-sensor as in many controls textbooks); the input to the damping block is the uninverted sensor signal(s); there is a hard-wired -1 after the damping block representing default negative gain.
  • Fabian went inside the SRM chamber and diagnosed the problem that had appeared shortly before vent. It turned out to be yaw of the IP causing a payload cable to touch. He fixed it with the F0 yaw stepper. (He had tried this earlier without success but it turned out the problem was another dead output on the stepper driver.)
  • Terrence traced the geophone issue to a group of dead channels (#20-23) on the AA chassis. We tried replacing the chassis and it fixed not only the geophone issue but an issue in the TILT OL path (#24-27) that we had planned to debug next.
  • We retested the BIO for stepper remote enable system and this time it was working (probably due to the refactoring of the BIO stuff in the model and/or all the restarts).
  • We rebuilt all the IOP models after removing an unneeded ADC1 block (corresponding to hardware that Yoshizawa-san had removed).
  • Enzo and Terrence wrote Python scripts to automate the process of adapting the control filters to the new topology (where the DAMP and DCCTRL functions are in parallel instead of series).

Plan for week of 3/4

  • Enzo at Mitaka.
  • Mark, Fabian Mon-Wed (Thu is farewell party).
  • Final tweaks of SRM?
  • Monitor (re-)pumpdown.
  • Tests of new Guardian.
  • Final test of stepper remote enable system (someone in cleanroom checks the lights go on/off).
  • Continue monitoring SRM yaw drift.
  • Setup SRM and SR3 LEN OLs.
  • Work on Type B paper.

==== Plan for week of 3/11 =====

  • Mark at Kamioka full week?
  • Enzo at Kamioka Mon, Tue, then JPS.

Vacation/Travel Info

  • Enzo vacation, 3/5 and 3/6.
  • Enzo et al. Farewell Party, 3/7.
  • Enzo at JPS then final vacation, 3/13-29
  • Terrence's last day, 3/29.

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)