* Fabian finished dummy BS assembly. * Mark and Tatsumi-san glued magnets into both types of BS optic flags, and discs into BS IM flags. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1815 |klog]] Two optic flags had to be redone because the magnets moved while the glue was drying. Hirata-san helped remove the magnets with acetone in the ultrasonic cleaner. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1818|klog]] * Tatsumi-san, Fabian and Mark took the dummy BS to Kashiwa and glued the flags and prisms. We will check status on Mon 6/13. * Hirata-san measured another filter. * Hirata-san washed a batch of parts. * Hirata-san worked on work platforms for the installation. * Hirata-san looked for a crane scale for use at the site. (We decided the 500 kg version of the one used at TAMA.) * Hirata-san worked on making some guide parts for the PI installation (Misumi parts with minor additional machining from ATC). * We finalized a design for simple SS mirror parts for the dummy BS with Akutsu-san. They will be made by ATC. * Mark worked on list of items for purchase in FY2016 and on the schedule. * Fabian did more work on the IM assembly. It is nearly done and he will start on the RM next week. |
* Fabian, Mark, Yokogawa-kun and Kuwahara-kun did BS installation at Kamioka: * Hung RM. * Did permanent routing of RM OSEM cables to IM. * Did temporary routing of RM OSEM in-vacuum cables to flange (4 channels). * Did semi-permanent routing of all OSEM external cables to satellite amps (10 channels) * Did temporary routing of RM OSEMs to PR2 rack (4 channels). * Took data with geophones connected but immobilized and then stored geophones in boxes. * Tested signals from first satellite amp getting to digital system. * Weighed mirror box. * Did fit check of flag holders for stub flags. Very minor adjustments will be needed. * Covered everything in preparation for modifications to clean booth roof (9/20-21). * Hirata-san: * Finished 3D CAD of SR2 and SR3 in tanks, with optical layout included. * Started 3D CAD for SRM. * Checked flag design. * Assembled a bottom filter (ongoing). * Cleaned maraging rods. |
Line 18: | Line 24: |
* Can we make SR wire breakers bigger? * Fukushima-san will start on machining test soon (as of 5/27). * Not enough crane height problem (Hirata, Saito) - no action since last week * Ballast masses for payload * Initial batch received - ordered extra smaller ones to allow for adjustments. * Lower breadboard stuff * '''Need to be incorporated into the procedure document. Discuss with Takahashi (Mark)''' * Breadboard springs (in manufacture, expected end of July) * Nail-head parts: quote from Mirapro received, not urgent, will be combined with assembly frame order. * Clean bag - expected 6/8. * Documents * BS Assembly Procedure [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] |
* Longer term to-do list * Do Inventor assembly for SRx in chamber and on assembly frame (Hirata) - SR2/SR3 DONE, SRM ongoing. * Part "disk security" top has to be modified - screw positions do not match. * Write more of payload assembly procedure (Fabian) - ONGOING * Write more of BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] (Mark) - ONGOING * Lower breadboard installation to be incorporated into the procedure document. * Work on BS simulation (Fabian) * Do BS Simulink model (Mark, Kokeyama) * Do 2D drawings of SR2 parts (Hirata) * Redesign SRx IM wire clamps for larger prisms, remachined RMs * Order SRM/PRM parts (Hirata/Shoda) * Order SRx fasteners (Hirata) |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
- Type B Past Week Summary
- Fabian, Mark, Yokogawa-kun and Kuwahara-kun did BS installation at Kamioka:
- Hung RM.
- Did permanent routing of RM OSEM cables to IM.
- Did temporary routing of RM OSEM in-vacuum cables to flange (4 channels).
- Did semi-permanent routing of all OSEM external cables to satellite amps (10 channels)
- Did temporary routing of RM OSEMs to PR2 rack (4 channels).
- Took data with geophones connected but immobilized and then stored geophones in boxes.
- Tested signals from first satellite amp getting to digital system.
- Weighed mirror box.
- Did fit check of flag holders for stub flags. Very minor adjustments will be needed.
- Covered everything in preparation for modifications to clean booth roof (9/20-21).
- Hirata-san:
- Finished 3D CAD of SR2 and SR3 in tanks, with optical layout included.
- Started 3D CAD for SRM.
- Checked flag design.
- Assembled a bottom filter (ongoing).
- Cleaned maraging rods.
- Fabian, Mark, Yokogawa-kun and Kuwahara-kun did BS installation at Kamioka:
- Type B ongoing issues
- Longer term to-do list
- Do Inventor assembly for SRx in chamber and on assembly frame (Hirata) - SR2/SR3 DONE, SRM ongoing.
- Part "disk security" top has to be modified - screw positions do not match.
- Write more of payload assembly procedure (Fabian) - ONGOING
Write more of BS Assembly Procedure E1504235, E1504235 draft (Mark) - ONGOING
- Lower breadboard installation to be incorporated into the procedure document.
- Work on BS simulation (Fabian)
- Do BS Simulink model (Mark, Kokeyama)
- Do 2D drawings of SR2 parts (Hirata)
- Redesign SRx IM wire clamps for larger prisms, remachined RMs
- Order SRM/PRM parts (Hirata/Shoda)
- Order SRx fasteners (Hirata)
- Do Inventor assembly for SRx in chamber and on assembly frame (Hirata) - SR2/SR3 DONE, SRM ongoing.