Size: 2003
Comment:
|
Size: 2221
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 6: | Line 6: |
==== Report for week of 1/29 ==== * We moved the top filter intended for SR2 (#1) into the SR3 cleanbooth. * Unfortunately we noticed one of the blades had many small X-shaped stress fractures on the top surface (klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=4058|4058]]). * We moved the top filter entered for SR3 (#3) into the SRM cleanbooth and inspected the blades. Two had one smallish stress fracture each and one had a huge fracture and looks close to failing (klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=4061|4061]]). * We referred the BS OL. * We removed the BS tank lid and inspected the BS top filter blades. They seemed fine (klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=4073|4073]]). * Hirata-san received and washed some ferromagnetic disks for IM flags and other small parts. * Hirata-san moved the BF with the tilted keystone (#1) out of the cleanbooth in preparation for rebuilding. * Hirata-san placed the second order for payload parts, and an order for remachining of nuts for cable clamps on rods. * Fabian measured the gain of the ADC system (homework from the Commissioning Workshop). ==== Plan for week of 2/5 ==== Enzo on vacation; all others at Kamioka. * Make in-air pico adapter cables. * Calibrate LVDT. * Test IM picos and BF yaw pico. * Test FR. * Install ballast mass in BF. * Build IRM around IM. * Cable/test/adjust IM OSEMs. * Time permitting, do TFs from IM OSEMs to themselves and to optical sensor. |
==== Report for week of 2/19 ==== * We did TFs from the IM OSEMs. * We secured the cables inside the BF, added the cap and anchored the cables from below the BF to the cap. * We lifted the BF/... section with the load gauge adapter and measured the weight, which was about as expected. * Based on the measured weight, Fabian prepared an 800 g set of masses for the top of the BF. * We added the AF crossbars and the section of the SS below the SF and craned in the SF. * We installed the SF-BF rod and flying saucer and suspended the BF/... section. With the 800 g placed temporarily on the BF, the SF keystone floated at about mid-range. |
Line 28: | Line 14: |
==== Plan for week of 2/13 ==== * No work Monday (建国記念の日の振替休日)<<BR>> * Enzo on vacation * Hirata-san at Mitaka Tue, Wed (to receive and wash parts). * All others at Kamioka. |
==== Plan for week of 2/26 ==== * Shoda-san at Mitaka. |
Line 34: | Line 17: |
* Lift BF/IM/IRM/RM/TM and check total mass and balance. * Test BF picos. * |
* Enzo at Mitaka Mon 2/26. * '''Remove LBB temporary ballast masses from BS chamber.''' * Route cables up to under SF. * Check/adjust total mass and balance of BF/... section, especially IM OSEMs. * Cable and calibrate SF LVDT. * Add Cu segments to SF cap. * Install cap. * Lift SF/... section and check total mass and balance. ==== Plan for week of 3/5 ==== * Shoda-san at Mitaka. * Hirata-san vacation Mon 3/5, then Kamioka * Others at Kamioka. * - * Get SRM tank mushroom section installed (Hirata-san, Kimura-san) * SR3 rack setup. * Other tasks TBD. ==== Plan for week of 3/12 ==== * Shoda-san at Mitaka. * Mark at ASJ (Chiba) Fri 3/16. * Hirata-san vacation Mon 3/5, then Kamioka ==== Plan for week of 3/19 ==== * Mark at LVC meeting * Shoda-san, Fabian at Mitaka ==== Plan for week of 3/26 ==== * Mark vacation. * Others ??? ==== To-Do Lists, Schedule ==== * [[KAGRA/Subgroups/VIS/TypeB/March2018]] * [[KAGRA/Subgroups/VIS/TypeB/April2018]] * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]] * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]] * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]] |
Line 39: | Line 56: |
* Enzo 1/30-2/19 (at Mitaka 1/29, part of 1/30) * Kozu-kun 1/29-2/2 |
* Enzo Mitaka day 2/26 * Hirata-san vacation 3/5 * Hirata-san vacation Mon 3/5 * Fabian 3/26-4/27 vacation (then gone). |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 2/19
- We did TFs from the IM OSEMs.
- We secured the cables inside the BF, added the cap and anchored the cables from below the BF to the cap.
- We lifted the BF/... section with the load gauge adapter and measured the weight, which was about as expected.
- Based on the measured weight, Fabian prepared an 800 g set of masses for the top of the BF.
- We added the AF crossbars and the section of the SS below the SF and craned in the SF.
- We installed the SF-BF rod and flying saucer and suspended the BF/... section. With the 800 g placed temporarily on the BF, the SF keystone floated at about mid-range.
Plan for week of 2/26
- Shoda-san at Mitaka.
- -
- Enzo at Mitaka Mon 2/26.
Remove LBB temporary ballast masses from BS chamber.
- Route cables up to under SF.
- Check/adjust total mass and balance of BF/... section, especially IM OSEMs.
- Cable and calibrate SF LVDT.
- Add Cu segments to SF cap.
- Install cap.
- Lift SF/... section and check total mass and balance.
Plan for week of 3/5
- Shoda-san at Mitaka.
- Hirata-san vacation Mon 3/5, then Kamioka
- Others at Kamioka.
- -
- Get SRM tank mushroom section installed (Hirata-san, Kimura-san)
- SR3 rack setup.
- Other tasks TBD.
Plan for week of 3/12
- Shoda-san at Mitaka.
- Mark at ASJ (Chiba) Fri 3/16.
- Hirata-san vacation Mon 3/5, then Kamioka
Plan for week of 3/19
- Mark at LVC meeting
- Shoda-san, Fabian at Mitaka
Plan for week of 3/26
- Mark vacation.
- Others ???
To-Do Lists, Schedule
Vacation Info
- Enzo Mitaka day 2/26
- Hirata-san vacation 3/5
- Hirata-san vacation Mon 3/5
- Fabian 3/26-4/27 vacation (then gone).