==== Report for week of 1/29 ====
 * We moved the top filter intended for SR2 (#1) into the SR3 cleanbooth.
 * Unfortunately we noticed one of the blades had many small X-shaped stress fractures on the top surface (klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=4058|4058]]).
 * We moved the top filter entered for SR3 (#3) into the SRM cleanbooth and inspected the blades. Two had one smallish stress fracture each and one had a huge fracture and looks close to failing (klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=4061|4061]]).
 * We referred the BS OL.
 * We removed the BS tank lid and inspected the BS top filter blades. They seemed fine (klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=4073|4073]]).
 * Hirata-san received and washed some ferromagnetic disks for IM flags and other small parts.
 * Hirata-san moved the BF with the tilted keystone (#1) out of the cleanbooth in preparation for rebuilding.
 * Hirata-san placed the second order for payload parts, and an order for remachining of nuts for cable clamps on rods.
 * Fabian measured the gain of the ADC system (homework from the Commissioning Workshop).
 
==== Plan for week of 2/5 ====
 * Enzo on vacation; all others at Kamioka.
 * -
 * Make in-air pico adapter cables.
 * Calibrate LVDT.
 * Test IM picos and BF yaw pico.
 * Test FR.
 * Install ballast mass in BF.
 * Build IRM around IM.
 * Cable/test/adjust IM OSEMs.
 * Time permitting, do TFs from IM OSEMs to themselves and to optical sensor.
==== Report for week of 5/28 ====
 * Enzo redid the SR3 BIO connections to match the now-working BS setup. He also fixed PR2, which had a similar problem.
 * Enzo replaced LPCDs with HPCDs in the SR3.
 * Hirata-san and Kozu-kun continued tuning the filter in PI #3. Un
Line 29: Line 11:
==== Plan for week of 2/13 ====
 * No work Monday (建国記念の日の振替休日)<<BR>>
 * Enzo on vacation
 * Hirata-san at Mitaka Tue, Wed (to receive and wash parts).
 * All others at Kamioka.
 * -
 * Lift BF/... section and check total mass and balance.
 * Cable and test BF picos.
==== Plan for week of 6/11 ====
 * Mark Enzo, Hirata-san, Kozu-kun, Terrence at Kamioka Tue-Fri (Mon is compensation day for f2f.)
 * --
 * Route cables through SF-BF flying saucer up to bottom of SF.
 * Add minimal ballast mass to SF (rough balance only) and weigh SF/... section.
 * Adjust BF trim mass.
 * Readjust payload.
 * Take TFs.
 * Cable, test SF LVDT and FR.
 * Add calculated ballast to SF.
 * Finish tuning F0 #3 for SR3.
 * Park F0 #1 (for SR2) in top of SR3 assembly frame.
 * Move F0 #3 behind SR3.
 * Move F0 #1 to "factory" area (in front of SRM) and start rebuild.
Line 38: Line 26:
==== Plan for week of 2/19 ====
 * Add section of SS up to SF ring.
 * Bring in SF.
 * Add Cu segments to SF cap.
 * Hook BF/... section.
 * Route cables up to under SF.
 * Check/adjust total mass of BF/... section.
==== Plan for week of 6/18 ====
 * Mark Enzo, Hirata-san, Kozu-kun, Terrence at Kamioka Mon-Fri.
 * --
 * Install PI.
 * Suspend SF/... section.
 * Lots of cabling.

==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]]
Line 47: Line 39:
 * Enzo 1/30-2/19 (at Mitaka 1/29, part of 1/30).
 * Fabian 4/2-4/27 vacation (then gone).

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 5/28

  • Enzo redid the SR3 BIO connections to match the now-working BS setup. He also fixed PR2, which had a similar problem.
  • Enzo replaced LPCDs with HPCDs in the SR3.
  • Hirata-san and Kozu-kun continued tuning the filter in PI #3. Un

Plan for week of 6/11

  • Mark Enzo, Hirata-san, Kozu-kun, Terrence at Kamioka Tue-Fri (Mon is compensation day for f2f.)
  • --
  • Route cables through SF-BF flying saucer up to bottom of SF.
  • Add minimal ballast mass to SF (rough balance only) and weigh SF/... section.
  • Adjust BF trim mass.
  • Readjust payload.
  • Take TFs.
  • Cable, test SF LVDT and FR.
  • Add calculated ballast to SF.
  • Finish tuning F0 #3 for SR3.
  • Park F0 #1 (for SR2) in top of SR3 assembly frame.
  • Move F0 #3 behind SR3.
  • Move F0 #1 to "factory" area (in front of SRM) and start rebuild.

Plan for week of 6/18

  • Mark Enzo, Hirata-san, Kozu-kun, Terrence at Kamioka Mon-Fri.
  • --
  • Install PI.
  • Suspend SF/... section.
  • Lots of cabling.