==== Report for week of 1/29 ==== * Mark made two sets of in-air pico splitter cables (each with a triple for IM and a double for BF) for SR2 and SR3. * Fabian, Hirata-san and Kozu-kun worked on cabling and testing the IM pitch/roll/yaw picos, the BF FR and the BF LVDT. The LVDT connections were initially unreliable and Hirata-san had to redo the pins on the coil wires. * Fabian installed ballast masses in the BF. * Mark worked on schedule. * Mark did inventory of the stepper motor drivers (many were not accounted for on the wiki and/or JGWDoc and one is missing) and reserved two for SR3. |
==== Report for week of 5/28 ==== * Enzo redid the SR3 BIO connections to match the now-working BS setup. He also fixed PR2, which had a similar problem. * Enzo replaced LPCDs with HPCDs in the SR3. * Hirata-san and Kozu-kun continued tuning the filter in PI #3. Un |
Line 13: | Line 11: |
==== Plan for week of 2/13 ==== * No work Monday (建国記念の日の振替休日) * Enzo on vacation * Hirata-san at Mitaka Tue, Wed (to receive and wash parts). * Shoda-san at Mitaka * All others at Kamioka. * - * Build IRM around IM. * Cable/test/adjust IM OSEMs. * Do TFs from IM OSEMs to IM OSEMs, OL pitch/yaw. |
==== Plan for week of 6/11 ==== * Mark Enzo, Hirata-san, Kozu-kun, Terrence at Kamioka Tue-Fri (Mon is compensation day for f2f.) * -- * Route cables through SF-BF flying saucer up to bottom of SF. * Add minimal ballast mass to SF (rough balance only) and weigh SF/... section. * Adjust BF trim mass. * Readjust payload. * Take TFs. * Cable, test SF LVDT and FR. * Add calculated ballast to SF. * Finish tuning F0 #3 for SR3. * Park F0 #1 (for SR2) in top of SR3 assembly frame. * Move F0 #3 behind SR3. * Move F0 #1 to "factory" area (in front of SRM) and start rebuild. |
Line 24: | Line 26: |
==== Plan for week of 2/19 ==== * Enzo back from Tuesday. * Shoda-san at Mitaka * All others at Kamioka. * - * Lift BF/... section and check total mass and balance. * Cable and test BF picos. * Add section of SS up to SF ring. * Bring in SF. * Hook BF/... section. * Route cables up to under SF. * Check/adjust total mass of BF/... section. |
==== Plan for week of 6/18 ==== * Mark Enzo, Hirata-san, Kozu-kun, Terrence at Kamioka Mon-Fri. * -- * Install PI. * Suspend SF/... section. * Lots of cabling. |
Line 37: | Line 33: |
==== Plan for week of 2/26 ==== * Add Cu segments to SF cap. * Lift SF/... section and check total mass and balance. |
==== To-Do Lists, Schedule ==== * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]] * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]] * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]] |
Line 42: | Line 39: |
* Enzo 1/30-2/19. * Fabian 4/2-4/27 vacation (then gone). |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 5/28
- Enzo redid the SR3 BIO connections to match the now-working BS setup. He also fixed PR2, which had a similar problem.
- Enzo replaced LPCDs with HPCDs in the SR3.
- Hirata-san and Kozu-kun continued tuning the filter in PI #3. Un
Plan for week of 6/11
- Mark Enzo, Hirata-san, Kozu-kun, Terrence at Kamioka Tue-Fri (Mon is compensation day for f2f.)
- --
- Route cables through SF-BF flying saucer up to bottom of SF.
- Add minimal ballast mass to SF (rough balance only) and weigh SF/... section.
- Adjust BF trim mass.
- Readjust payload.
- Take TFs.
- Cable, test SF LVDT and FR.
- Add calculated ballast to SF.
- Finish tuning F0 #3 for SR3.
- Park F0 #1 (for SR2) in top of SR3 assembly frame.
- Move F0 #3 behind SR3.
- Move F0 #1 to "factory" area (in front of SRM) and start rebuild.
Plan for week of 6/18
- Mark Enzo, Hirata-san, Kozu-kun, Terrence at Kamioka Mon-Fri.
- --
- Install PI.
- Suspend SF/... section.
- Lots of cabling.