2384
Comment:
|
910
|
Deletions are marked like this. | Additions are marked like this. |
Line 5: | Line 5: |
* Type B Past Week Summary * Fabian finished dummy BS assembly. * Mark and Tatsumi-san glued magnets into both types of BS optic flags, and discs into BS IM flags. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1815 |klog]] Two optic flags had to be redone because the magnets moved while the glue was drying. Hirata-san helped remove the magnets with acetone in the ultrasonic cleaner. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1818|klog]] * Tatsumi-san, Fabian and Mark took the dummy BS to Kashiwa and glued the flags and prisms. We will check status on Mon 6/13. * Hirata-san measured another filter. * Hirata-san washed a batch of parts. * Hirata-san worked on work platforms for the installation. * Hirata-san looked for a crane scale for use at the site. (We decided the 500 kg version of the one used at TAMA.) * Hirata-san worked on making some guide parts for the PI installation (Misumi parts with minor additional machining from ATC). * We finalized a design for simple SS mirror parts for the dummy BS with Akutsu-san. They will be made by ATC. * Mark worked on list of items for purchase in FY2016 and on the schedule. * Fabian did more work on the IM assembly. It is nearly done and he will start on the RM next week. * Type B ongoing issues * Wires * Need to decide RM wire thickness and order. Lead time is a few days from Nilaco. * Can we make SR wire breakers bigger? * Fukushima-san will start on machining test soon (as of 5/27). * Not enough crane height problem (Hirata, Saito) - no action since last week * Ballast masses for payload * Initial batch received - ordered extra smaller ones to allow for adjustments. * Lower breadboard stuff * '''Need to be incorporated into the procedure document. Discuss with Takahashi (Mark)''' * Breadboard springs (in manufacture, expected end of July) * Nail-head parts: quote from Mirapro received, not urgent, will be combined with assembly frame order. * Clean bag - expected 6/8. * Documents * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] |
* Hirata-san: * Did drawings of SR damper. * Mark, Fabian, Enzo and Hirata-san (at Kamioka): * Took the end plate off the IM to get access to the pitch/roll picos. * Found the pitch pico was unreliable and replaced it. * Found the springs were not stiff enough, and immobilized 7 turns at the end of each with Cu wire to make them stiffer. * Reassembled and rebalanced the IM. * Reassembled and adjusted the IRM. * Discovered that the transverse offset between IRM and IM could be corrected by adjusting the roll of the BF. * Adjusted IM OSEMs to half-way. * Made and installed a new pair of wires for the BF yaw pico on the IM pico adapter (Hirata-san). * Installed an improved LVDT cable made by Hirata-san. * Made and hung posters for the Elites meeting visitors. |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
- Hirata-san:
- Did drawings of SR damper.
- Mark, Fabian, Enzo and Hirata-san (at Kamioka):
- Took the end plate off the IM to get access to the pitch/roll picos.
- Found the pitch pico was unreliable and replaced it.
- Found the springs were not stiff enough, and immobilized 7 turns at the end of each with Cu wire to make them stiffer.
- Reassembled and rebalanced the IM.
- Reassembled and adjusted the IRM.
- Discovered that the transverse offset between IRM and IM could be corrected by adjusting the roll of the BF.
- Adjusted IM OSEMs to half-way.
- Made and installed a new pair of wires for the BF yaw pico on the IM pico adapter (Hirata-san).
- Installed an improved LVDT cable made by Hirata-san.
- Made and hung posters for the Elites meeting visitors.