* Type B Past Week Summary * Fabian finished dummy BS assembly. * Mark and Tatsumi-san glued magnets into both types of BS optic flags, and discs into BS IM flags. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1815 |klog]] Two optic flags had to be redone because the magnets moved while the glue was drying. Hirata-san helped remove the magnets with acetone in the ultrasonic cleaner. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1818|klog]] * Tatsumi-san, Fabian and Mark took the dummy BS to Kashiwa and glued the flags and prisms. We will check status on Mon 6/13. * Hirata-san measured another filter. * Hirata-san washed a batch of parts. * Hirata-san worked on work platforms for the installation. * Hirata-san looked for a crane scale for use at the site. (We decided the 500 kg version of the one used at TAMA.) * Hirata-san worked on making some guide parts for the PI installation (Misumi parts with minor additional machining from ATC). * We finalized a design for simple SS mirror parts for the dummy BS with Akutsu-san. They will be made by ATC. * Mark worked on list of items for purchase in FY2016 and on the schedule. * Fabian did more work on the IM assembly. It is nearly done and he will start on the RM next week. * Type B ongoing issues * Wires * Need to decide RM wire thickness and order. Lead time is a few days from Nilaco. * Can we make SR wire breakers bigger? * Fukushima-san will start on machining test soon (as of 5/27). * Not enough crane height problem (Hirata, Saito) - no action since last week * Ballast masses for payload * Initial batch received - ordered extra smaller ones to allow for adjustments. * Lower breadboard stuff * '''Need to be incorporated into the procedure document. Discuss with Takahashi (Mark)''' * Breadboard springs (in manufacture, expected end of July) * Nail-head parts: quote from Mirapro received, not urgent, will be combined with assembly frame order. * Clean bag - expected 6/8. * Documents * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] |
=== Type B (Mark) === ==== Past two weeks report ==== Kamioka (Mark, Enzo, Kozu-kun): * Supported IA team. * Replaced LPCDs for IM OSEMs with HPCDs for increased pitch/yaw range. * Re-zeroed OL after significant change of beam position during IA. * Re-laid-out OL to improve focus of lens to LEN QPD. * Offloaded the pitch/yaw actuation at the IM OSEMs using the IM pitch/yaw picos. * Enzo worked on design of control loops using the OL. * Kozu-kun worked on diagonalizing the OL. Mitaka (Fabian, Hirata-san): * Fabian did mechanical design: * F0 FR * Cable clamps for the SR IP base. * New SR recoil ballast masses. * LBB ballast. * Update of BS 3D CAD with the as-built ballast. * Hirata-san * made and updated inventory list for SR. * made order list and asked some quotes. * Ordered some parts. * Talked with mirapro about SRM optical bench. * Made some drawings for SR preparation. ==== Plan for week of 11/13 ==== Enzo and Kozu-kun at Mitaka * Servos * Diagonalization of OL * TFs of BF * Documentation Mark and Fabian at Kamioka. * Mark attends commissioning workshop at U Toyama. * Support BF characterization work. * Prepare for mirror gluing. * Prepare for IM assembly. Hirata-san at Mitaka * SR procurement. * Get BS prism-gluing jigs reworked for use with PR/SR mirror box. ==== Plan for week of 11/20 ==== * Holiday on Thu 3/23 * Fabian at commissioning workshop * |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Past two weeks report
Kamioka (Mark, Enzo, Kozu-kun):
- Supported IA team.
- Replaced LPCDs for IM OSEMs with HPCDs for increased pitch/yaw range.
- Re-zeroed OL after significant change of beam position during IA.
- Re-laid-out OL to improve focus of lens to LEN QPD.
- Offloaded the pitch/yaw actuation at the IM OSEMs using the IM pitch/yaw picos.
- Enzo worked on design of control loops using the OL.
- Kozu-kun worked on diagonalizing the OL.
Mitaka (Fabian, Hirata-san):
- Fabian did mechanical design:
- F0 FR
- Cable clamps for the SR IP base.
- New SR recoil ballast masses.
- LBB ballast.
- Update of BS 3D CAD with the as-built ballast.
- Hirata-san
- made and updated inventory list for SR.
- made order list and asked some quotes.
- Ordered some parts.
- Talked with mirapro about SRM optical bench.
- Made some drawings for SR preparation.
Plan for week of 11/13
Enzo and Kozu-kun at Mitaka
- Servos
- Diagonalization of OL
- TFs of BF
- Documentation
Mark and Fabian at Kamioka.
- Mark attends commissioning workshop at U Toyama.
- Support BF characterization work.
- Prepare for mirror gluing.
- Prepare for IM assembly.
Hirata-san at Mitaka
- SR procurement.
- Get BS prism-gluing jigs reworked for use with PR/SR mirror box.
Plan for week of 11/20
- Holiday on Thu 3/23
- Fabian at commissioning workshop