==== Report for week of 1/29 ==== * Mark made two sets of in-air pico splitter cables (each with a triple for IM and a double for BF) for SR2 and SR3. * Fabian, Hirata-san and Kozu-kun worked on cabling and testing the IM pitch/roll/yaw picos, the BF FR and the BF LVDT. The LVDT connections were initially unreliable and Hirata-san had to redo the pins on the coil wires. * Fabian installed ballast masses in the BF. * Mark worked on schedule. * Mark did inventory of the stepper motor drivers (many were not accounted for on the wiki and/or JGWDoc and one is missing) and reserved two for SR3. |
==== Report for week of 3/19 ==== * Fujii-kun successfully assembled and tested a geophone pod (klogs 4492, 4508). * ?? Hirata-san set up the dummy BS to soak off the sapphire prisms. * |
Line 13: | Line 11: |
==== Plan for week of 2/13 ==== * No work Monday (建国記念の日の振替休日) * Enzo on vacation * Hirata-san at Mitaka Tue (self-evaluation interview). * Shoda-san at Mitaka. * All others at Kamioka. * - * Build IRM around IM. * Cable/test/adjust IM OSEMs. * Do TFs from IM OSEMs to IM OSEMs, OL pitch/yaw. |
==== Plan for week of 3/26 ==== * Tanioka-kun joins. * Mark vacation. * Shoda-san at Mitaka * Others at Kamioka * -- * Lay SR3 in-air cabling (Enzo++). * Finish tuning of BFs (Hirata-san++). * SF check (Hirata-san++). * Check load capacity. * Check fit of caps. * Add cable clamps to bases. * Add cable clamps and Cu segments to caps (only if they fit well). * Cable LVDTs and steppers. |
Line 24: | Line 26: |
==== Plan for week of 2/19 ==== * Enzo back from Tuesday. * Shoda-san at Mitaka. * Hirata-san at Mitaka Tue+Wed (to receive and wash parts; hope to change to Mon+Tue). * All others at Kamioka. * - * Lift BF/... section and check total mass and balance. * Cable and test BF picos. * Add section of SS up to SF ring. * Bring in SF. * Hook BF/... section. * Route cables up to under SF. * Check/adjust total mass of BF/... section. |
==== Plan for week of 4/2 ==== * Mark at Mitaka Mon, Kamioka from Tue. * Shoda-san at Mitaka * Others at Kamioka * -- * Glue SR3 (if available) * Build 2xIM, 2xIRM (if parts available - due 3/30) |
Line 38: | Line 34: |
==== Plan for week of 2/26 ==== * Shoda-san at Mitaka. * - * Add Cu segments to SF cap. * Lift SF/... section and check total mass and balance. |
==== Plan for week of 4/9 ==== * Shoda-san at Mitaka * Others at Kamioka * -- * Finish IMs and IRMs * Build 1xRM ==== Plan for week of 4/16 ==== * Start SR3 Hang? ==== Plan for week of 4/23 ==== * F0 blade prototype test ==== Plan for week of 4/30 ==== * Golden Week! ==== To-Do Lists, Schedule ==== * [[KAGRA/Subgroups/VIS/TypeB/March2018]] * [[KAGRA/Subgroups/VIS/TypeB/April2018]] * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]] * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]] * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]] |
Line 45: | Line 58: |
* Enzo 1/30-2/19. * Fabian 4/2-4/27 vacation (then gone). |
* Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun) * Fabian vacation, 3/26-4/27 (then gone). |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 3/19
- Fujii-kun successfully assembled and tested a geophone pod (klogs 4492, 4508).
- ?? Hirata-san set up the dummy BS to soak off the sapphire prisms.
Plan for week of 3/26
- Tanioka-kun joins.
- Mark vacation.
- Shoda-san at Mitaka
- Others at Kamioka
- --
- Lay SR3 in-air cabling (Enzo++).
- Finish tuning of BFs (Hirata-san++).
- SF check (Hirata-san++).
- Check load capacity.
- Check fit of caps.
- Add cable clamps to bases.
- Add cable clamps and Cu segments to caps (only if they fit well).
- Cable LVDTs and steppers.
Plan for week of 4/2
- Mark at Mitaka Mon, Kamioka from Tue.
- Shoda-san at Mitaka
- Others at Kamioka
- --
- Glue SR3 (if available)
- Build 2xIM, 2xIRM (if parts available - due 3/30)
Plan for week of 4/9
- Shoda-san at Mitaka
- Others at Kamioka
- --
- Finish IMs and IRMs
- Build 1xRM
Plan for week of 4/16
- Start SR3 Hang?
Plan for week of 4/23
- F0 blade prototype test
Plan for week of 4/30
- Golden Week!
To-Do Lists, Schedule
Vacation Info
- Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun)
- Fabian vacation, 3/26-4/27 (then gone).