==== Report for week of 1/29 ====
 * Fabian and Kozu-kun tested the FR stepper, and calibrated the keystone height as a function of FR position.
 * Fabian, Hirata-san and Kozu-kun installed and adjusted the IRM, IM OSEMs and associated cables.
 * Mark derived the diagonalization matrices for SR, posted them as [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7663| T1807663]] and entered them in the on-line system.
 * Mark fixed the GASALL screen, which had some elements hardwired to BS and did not work for SR2.
 * Mark initialized the watchdog section of the SR2 model (filters, thresholds etc).
 * Mark re-entered the IM OSEM2EUL offsets and gains, which had been entered by Enzo, but had not been saved and had been lost.
 * Mark identified and fixed a bug in the SF2 whereby the watchdog trigger was derived from the AND of the error signals from the various stages instead of the OR. Thus all stages would have to overload before the watchdog tripped. All other VIS models were similarly affected, and all affected library parts have been fixed, but the other models need to be rebuilt, which should be done at the earliest opportunity, e.g., early next week after the scheduled power outage on Sun 2/18.
 * Mark fixed the indicators for the watchdog on the OVERALL screen, which also had bad logic.
 * Mark tried using Shoda-san's measurement script to do TFs. It ran successfully, but the first data set was no good because of two issues: the excitation was apparently too large (even after a reduction by 20) and the SENSALIGN matrix was not initialized.
 * Hirata-san negotiated with Kimura-san to get the SRM tank mushroom installed (this will probably happen from Tue on the week of 3/5).
==== Report for week of 4/9 ====
 * We packed away the SRM SF and BF.
 * After several failed attempts with one secondary prism, Mark finished the SR3 prism/magnet gluing.
 * Tanioka-kun built two IRMs (less OSEMs).
 * Enzo built an RM.
 * Kozu-kun and Enzo calibrated one set of 6 IM OSEMs for SR3. (6 OSEMs for SRM remain to be done.)
 * Hirata-san aligned the assembly frame, installed the interface bars and IM ring, and installed the IM.
 * Eleonora and Izumi-san revisited the BS length to tilt coupling, which had degraded, and got it working again.
Line 18: Line 15:
==== Plan for week of 2/19 ==== ==== Plan for week of 4/23 ====
Line 20: Line 17:
 * Hirata-san at Mitaka Mon+Tue (to receive and wash parts), then Kamioka Wed-Fri.
 * Enzo back from Tuesday, at Kamioka.
 * Kozu-kun at Kamioka but limited availability (preparing poster).
 * All others at Kamioka.
 * -
 * Do TFs from IM OSEMs to IM OSEMs, OL pitch/yaw.
 * Sort out cables per Enzo's master plan.
 * Lift BF/... section and check total mass and balance.
 * Cable and test BF picos.
 * Add section of SS up to SF ring.
 * Bring in SF.
 * Hook BF/... section.
 * Route cables up to under SF.
 * Check/adjust total mass of BF/... section.
 * Hirata-san at Kamioka Mon-Wed, then Mitaka.
 * Kozu-kun at Kamioka Wed-Fri (but may be working with PEM on Fri).
 * Others (Mark, Enzo, Tanioka-kun) at Kamioka full week
 * --
 * Continue SR3 Hang
  * Hang optic.
  * Hang RM.
  * Cable RM OSEMs.
Line 35: Line 26:
==== Plan for week of 2/26 ==== ==== Plan for week of 4/30 ====
Line 37: Line 28:
 * -
 * Add Cu segments to SF cap.
 * Lift SF/... section and check total mass and balance.

==== Plan for week of 3/5 ====
 * Shoda-san at Mitaka.
 * Hirata-san vacation Mon 3/5, then Kamioka
 * Others at Kamioka.
 * -
 * Get SRM tank mushroom section installed (Hirata-san, Kimura-san)

==== Plan for week of 3/12 ====
 * Shoda-san at Mitaka.
 * Mark at ASJ (Chiba) Fri 3/16.
 * Hirata-san vacation Mon 3/5, then Kamioka

==== Plan for week of 3/19 ====
 * Mark at LVC meeting
 * Shoda-san at Mitaka

==== Plan for week of 3/26 ====
 * Mark ????
 * Shoda-san, Fabian at Mitaka
 * Others ???
 * Mark, Enzo at Kamioka Mon-Wed or TBD.
 * Others having fun doing Golden Week stuff.
 * --
 * Observe KAGRA Phase 1 operations, assist if problems arise.
 * Do BF TFs.
 * Continue SR3 hang.
Line 70: Line 43:
 * Enzo 1/30-2/19.
 * H
irata-san vacation Mon 3/5
 * Fabian 4/
2-4/27 vacation (then gone).
 * Fabian vacation, 3/26-4/27 (then gone).

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 4/9

  • We packed away the SRM SF and BF.
  • After several failed attempts with one secondary prism, Mark finished the SR3 prism/magnet gluing.
  • Tanioka-kun built two IRMs (less OSEMs).
  • Enzo built an RM.
  • Kozu-kun and Enzo calibrated one set of 6 IM OSEMs for SR3. (6 OSEMs for SRM remain to be done.)
  • Hirata-san aligned the assembly frame, installed the interface bars and IM ring, and installed the IM.
  • Eleonora and Izumi-san revisited the BS length to tilt coupling, which had degraded, and got it working again.

Plan for week of 4/23

  • Shoda-san at Mitaka.
  • Hirata-san at Kamioka Mon-Wed, then Mitaka.
  • Kozu-kun at Kamioka Wed-Fri (but may be working with PEM on Fri).
  • Others (Mark, Enzo, Tanioka-kun) at Kamioka full week
  • --
  • Continue SR3 Hang
    • Hang optic.
    • Hang RM.
    • Cable RM OSEMs.

Plan for week of 4/30

  • Shoda-san at Mitaka.
  • Mark, Enzo at Kamioka Mon-Wed or TBD.
  • Others having fun doing Golden Week stuff.
  • --
  • Observe KAGRA Phase 1 operations, assist if problems arise.
  • Do BF TFs.
  • Continue SR3 hang.