Revision 24 as of 2016-06-09 14:09:55
Size: 2436
Editor: MarkBarton
Comment:
Revision 116 as of 2017-01-06 13:19:19
Size: 1856
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 5: Line 5:
 * Type B Past Week Summary
  * Fabian finished dummy BS assembly.
  * Mark and Tatsumi-san glued magnets into both types of BS optic flags, and discs into BS IM flags. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1815 |klog]] Two optic flags had to be redone because the magnets moved while the glue was drying. Hirata-san helped remove the magnets with acetone in the ultrasonic cleaner. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1818|klog]]
  * Tatsumi-san, Fabian and Mark took the dummy BS to Kashiwa and glued the flags and prisms. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1821|klog]] We will check status on Mon 6/13.
  * Hirata-san measured another filter.
  * Hirata-san washed a batch of parts.
  * Hirata-san worked on work platforms for the installation.
  * Hirata-san looked for a crane scale for use at the site. (We decided the 500 kg version of the one used at TAMA.)
  * Hirata-san worked on making some guide parts for the PI installation (Misumi parts with minor additional machining from ATC).
  * We finalized a design for simple SS mirror parts for the dummy BS with Akutsu-san. They will be made by ATC.
  * Mark worked on list of items for purchase in FY2016 and on the schedule.
  * Fabian did more work on the IM assembly. It is nearly done and he will start on the RM next week.
 * Type B ongoing issues
  * Wires
   * Need to decide RM wire thickness and order. Lead time is a few days from Nilaco.
  * Can we make SR wire breakers bigger?
   * Fukushima-san will start on machining test soon (as of 5/27).
  * Not enough crane height problem (Hirata, Saito) - no action since last week
  * Ballast masses for payload
   * Initial batch received - ordered extra smaller ones to allow for adjustments.
  * Lower breadboard stuff
   * '''Need to be incorporated into the procedure document. Discuss with Takahashi (Mark)'''
   * Breadboard springs (in manufacture, expected end of July)
   * Nail-head parts: quote from Mirapro received, not urgent, will be combined with assembly frame order.
  * Clean bag - expected 6/8.
  * Documents
   * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]]
 * Activity report for weeks of 12/26 and 1/2

  * Hirata-san:
   * Modified parts list and screw list for payload.
   * Sent lists to i-ject and asked for preliminary quotes.
   * Made drawings for some jigs (PR hold-down jig) and some parts for payload (PR/SR wire clamps with disposable jaw pieces - improved version with disposable pieces in both primary and secondary clamps).
   * For Type Bp:
    * Searched for PR gluing jigs.
    * Washed and assembled recoilmass base for mirror hanging jigs, and sent them to Kamioka.
    * Washed additional masses for IM and sent them to Kamioka.
   * For others:
    * Washed IMMT plate and sent them to Kamioka.
  * Fabian
   * Designed a pull down system to fix the PR IM to the EQ stop (similar to the SR one).
   * Worked on design of the SR assembly frame. As hoped, the SR version can be almost identical to the BS version.
   * Worked on design of additional trim mass (≈18 kg) for the BS BF.
   * Checked assembly PR/SR drawings. There were a few corrections/changes.
   * Checked fastener list. There were few corrections/changes.
   * Checked component list for the manufacture order. There were few corrections/changes.
   * Helped in searching for the PR gluing jigs.
  * Mark
   * Started design of SR assembly frame (but then passed it to Fabian).
   * Worked on task lists and schedule.
 * Plan for 1/10-13
  * Mark and Fabian at Kamioka:
   * Finish rebalance of IM
   * Reinstall IRM, adjust OSEMs
   * Replace broken Type 3 cable.
   * Do TFs from IRM OSEMs to IRM and IM OSEMs.
   * Cable up and test BF LVDT and fishing rod (time permitting).
   * Disconnect BF and ship back to Mitaka (time permitting).
  * Hirata-san:
   * More SR procurement.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

  • Activity report for weeks of 12/26 and 1/2
    • Hirata-san:
      • Modified parts list and screw list for payload.
      • Sent lists to i-ject and asked for preliminary quotes.
      • Made drawings for some jigs (PR hold-down jig) and some parts for payload (PR/SR wire clamps with disposable jaw pieces - improved version with disposable pieces in both primary and secondary clamps).
      • For Type Bp:
        • Searched for PR gluing jigs.
        • Washed and assembled recoilmass base for mirror hanging jigs, and sent them to Kamioka.
        • Washed additional masses for IM and sent them to Kamioka.
      • For others:
        • Washed IMMT plate and sent them to Kamioka.
    • Fabian
      • Designed a pull down system to fix the PR IM to the EQ stop (similar to the SR one).
      • Worked on design of the SR assembly frame. As hoped, the SR version can be almost identical to the BS version.
      • Worked on design of additional trim mass (≈18 kg) for the BS BF.
      • Checked assembly PR/SR drawings. There were a few corrections/changes.
      • Checked fastener list. There were few corrections/changes.
      • Checked component list for the manufacture order. There were few corrections/changes.
      • Helped in searching for the PR gluing jigs.
    • Mark
      • Started design of SR assembly frame (but then passed it to Fabian).
      • Worked on task lists and schedule.
  • Plan for 1/10-13
    • Mark and Fabian at Kamioka:
      • Finish rebalance of IM
      • Reinstall IRM, adjust OSEMs
      • Replace broken Type 3 cable.
      • Do TFs from IRM OSEMs to IRM and IM OSEMs.
      • Cable up and test BF LVDT and fishing rod (time permitting).
      • Disconnect BF and ship back to Mitaka (time permitting).
    • Hirata-san:
      • More SR procurement.