2436
Comment:
|
2060
|
Deletions are marked like this. | Additions are marked like this. |
Line 5: | Line 5: |
* Type B Past Week Summary * Fabian finished dummy BS assembly. * Mark and Tatsumi-san glued magnets into both types of BS optic flags, and discs into BS IM flags. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1815 |klog]] Two optic flags had to be redone because the magnets moved while the glue was drying. Hirata-san helped remove the magnets with acetone in the ultrasonic cleaner. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1818|klog]] * Tatsumi-san, Fabian and Mark took the dummy BS to Kashiwa and glued the flags and prisms. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1821|klog]] We will check status on Mon 6/13. * Hirata-san measured another filter. * Hirata-san washed a batch of parts. * Hirata-san worked on work platforms for the installation. * Hirata-san looked for a crane scale for use at the site. (We decided the 500 kg version of the one used at TAMA.) * Hirata-san worked on making some guide parts for the PI installation (Misumi parts with minor additional machining from ATC). * We finalized a design for simple SS mirror parts for the dummy BS with Akutsu-san. They will be made by ATC. * Mark worked on list of items for purchase in FY2016 and on the schedule. * Fabian did more work on the IM assembly. It is nearly done and he will start on the RM next week. * Type B ongoing issues * Wires * Need to decide RM wire thickness and order. Lead time is a few days from Nilaco. * Can we make SR wire breakers bigger? * Fukushima-san will start on machining test soon (as of 5/27). * Not enough crane height problem (Hirata, Saito) - no action since last week * Ballast masses for payload * Initial batch received - ordered extra smaller ones to allow for adjustments. * Lower breadboard stuff * '''Need to be incorporated into the procedure document. Discuss with Takahashi (Mark)''' * Breadboard springs (in manufacture, expected end of July) * Nail-head parts: quote from Mirapro received, not urgent, will be combined with assembly frame order. * Clean bag - expected 6/8. * Documents * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] |
=== Type B (Mark) === ==== Past week report ==== At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun): * We disconnected the SF/... section and reinstalled the F0-SF rod with the hex cable clamp attached. * We debugged an issue with the actuation (the real-time model needed rebooting). * We routed all the SF/... cables up to the bottom of the PI, and then to the feedthroughs. * We unlocked the F0 keystone and experimented to find the amount of mass needed on the SF (≈845 g). * We attached the SF trim mass, adjusting it laterally so that the SF was level in pitch and roll. * We corrected some errors on the MEDM screens (some broken links and Take/Restore Safe.snap buttons). * We cabled all the PI items through to the rack and did very basic testing. * We disconnected the security structure from the assembly frame and adjusted the PI till the SS was vertical. * We unlocked the IP and adjusted the PI jacks and FRs till the IP was centered. * We passed the halves of the LBB Cu damping ring (less the Cu) into the chamber and joined them. * We put the magnets on the LBB damper ring using the template. * We locked various combinations of keystones and measured the vertical resonance frequencies of the unlocked filters. * We spent time on getting the geophones working. The original descrambler adapters had gone missing, so Enzo created three new ones. We borrowed a cable to replace one that had broken. The geophone distributor (S1402167) failed (no power on the negative rail), and a replacement borrowed from SR3 (S1605513) kept switching off. ==== Plan for week of 9/13 ==== ==== Plan for week of 9/19 ==== No work Mon 9/18 (敬老の日)<<BR>> Mark, Fabian, Enzo, Ohishi-san, Hirata-san, Yoshioka-kun (Tue, Wed, Thu, Fri), Kozu-kun * Install LBB damper magnet rings in tank. * Remove tank lid. * * Install suspension. ==== Vacation Info ==== Mark: 10/16-24 |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Past week report
At Kamioka (Mark, Ohishi-san, Fabian, Enzo, Hirata-san, Yoshioka-kun, Kozu-kun):
- We disconnected the SF/... section and reinstalled the F0-SF rod with the hex cable clamp attached.
- We debugged an issue with the actuation (the real-time model needed rebooting).
- We routed all the SF/... cables up to the bottom of the PI, and then to the feedthroughs.
- We unlocked the F0 keystone and experimented to find the amount of mass needed on the SF (≈845 g).
- We attached the SF trim mass, adjusting it laterally so that the SF was level in pitch and roll.
- We corrected some errors on the MEDM screens (some broken links and Take/Restore Safe.snap buttons).
- We cabled all the PI items through to the rack and did very basic testing.
- We disconnected the security structure from the assembly frame and adjusted the PI till the SS was vertical.
- We unlocked the IP and adjusted the PI jacks and FRs till the IP was centered.
- We passed the halves of the LBB Cu damping ring (less the Cu) into the chamber and joined them.
- We put the magnets on the LBB damper ring using the template.
- We locked various combinations of keystones and measured the vertical resonance frequencies of the unlocked filters.
- We spent time on getting the geophones working. The original descrambler adapters had gone missing, so Enzo created three new ones. We borrowed a cable to replace one that had broken. The geophone distributor (S1402167) failed (no power on the negative rail), and a replacement borrowed from SR3 (S1605513) kept switching off.
Plan for week of 9/13
Plan for week of 9/19
No work Mon 9/18 (敬老の日)
Mark, Fabian, Enzo, Ohishi-san, Hirata-san, Yoshioka-kun (Tue, Wed, Thu, Fri), Kozu-kun
- Install LBB damper magnet rings in tank.
- Remove tank lid.
- Install suspension.
Vacation Info
Mark: 10/16-24