* Type B Past Week Summary * Fabian finished dummy BS assembly. * Mark and Tatsumi-san glued magnets into both types of BS optic flags, and discs into BS IM flags. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1815 |klog]] Two optic flags had to be redone because the magnets moved while the glue was drying. Hirata-san helped remove the magnets with acetone in the ultrasonic cleaner. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1818|klog]] * Tatsumi-san, Fabian and Mark took the dummy BS to Kashiwa and glued the flags and prisms. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=1821|klog]] We will check status on Mon 6/13. * Hirata-san measured another filter. * Hirata-san washed a batch of parts. * Hirata-san worked on work platforms for the installation. * Hirata-san looked for a crane scale for use at the site. (We decided the 500 kg version of the one used at TAMA.) * Hirata-san worked on making some guide parts for the PI installation (Misumi parts with minor additional machining from ATC). * We finalized a design for simple SS mirror parts for the dummy BS with Akutsu-san. They will be made by ATC. * Mark worked on list of items for purchase in FY2016 and on the schedule. * Fabian did more work on the IM assembly. It is nearly done and he will start on the RM next week. * Type B ongoing issues * Wires * Need to decide RM wire thickness and order. Lead time is a few days from Nilaco. * Can we make SR wire breakers bigger? * Fukushima-san will start on machining test soon (as of 5/27). * Not enough crane height problem (Hirata, Saito) - no action since last week * Ballast masses for payload * Initial batch received - ordered extra smaller ones to allow for adjustments. * Lower breadboard stuff * '''Need to be incorporated into the procedure document. Discuss with Takahashi (Mark)''' * Breadboard springs (in manufacture, expected end of July) * Nail-head parts: quote from Mirapro received, not urgent, will be combined with assembly frame order. * Clean bag - expected 6/8. * Documents * BS Assembly Procedure [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4235| E1504235]], [[https://onedrive.live.com/redir?resid=D5CCFA70A378E0D0!195&authkey=!AM_usynuo9QI57g&ithint=folder,webloc|E1504235 draft]] |
=== Type B (Mark) === ==== Report for week of 2/19 ==== * We did TFs from the IM OSEMs. * We secured the cables inside the BF, added the cap and anchored the cables from below the BF to the cap. * We lifted the BF/... section with the load gauge adapter and measured the weight, which was about as expected. * Based on the measured weight, Fabian prepared an 800 g set of masses for the top of the BF. * We added the AF crossbars and the section of the SS below the SF and craned in the SF. * We installed the SF-BF rod and flying saucer and suspended the BF/... section. With the 800 g placed temporarily on the BF, the SF keystone floated at about mid-range. ==== Plan for week of 2/26 ==== * Shoda-san at Mitaka. * - * Enzo at Mitaka Mon 2/26. * '''Remove LBB temporary ballast masses from BS chamber.''' * Route cables up to under SF. * Check/adjust total mass and balance of BF/... section, especially IM OSEMs. * Cable and calibrate SF LVDT. * Add Cu segments to SF cap. * Install cap. * Lift SF/... section and check total mass and balance. ==== Plan for week of 3/5 ==== * Shoda-san at Mitaka. * Hirata-san vacation Mon 3/5, then Kamioka * Others at Kamioka. * - * Get SRM tank mushroom section installed (Hirata-san, Kimura-san) * SR3 rack setup. * Other tasks TBD. ==== Plan for week of 3/12 ==== * Shoda-san at Mitaka. * Mark at ASJ (Chiba) Fri 3/16. * Hirata-san vacation Mon 3/5, then Kamioka ==== Plan for week of 3/19 ==== * Mark at LVC meeting * Shoda-san, Fabian at Mitaka ==== Plan for week of 3/26 ==== * Mark vacation. * Others ??? ==== To-Do Lists, Schedule ==== * [[KAGRA/Subgroups/VIS/TypeB/March2018]] * [[KAGRA/Subgroups/VIS/TypeB/April2018]] * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]] * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]] * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]] ==== Vacation Info ==== * Enzo Mitaka day 2/26 * Hirata-san vacation 3/5 * Hirata-san vacation Mon 3/5 * Fabian 3/26-4/27 vacation (then gone). |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 2/19
- We did TFs from the IM OSEMs.
- We secured the cables inside the BF, added the cap and anchored the cables from below the BF to the cap.
- We lifted the BF/... section with the load gauge adapter and measured the weight, which was about as expected.
- Based on the measured weight, Fabian prepared an 800 g set of masses for the top of the BF.
- We added the AF crossbars and the section of the SS below the SF and craned in the SF.
- We installed the SF-BF rod and flying saucer and suspended the BF/... section. With the 800 g placed temporarily on the BF, the SF keystone floated at about mid-range.
Plan for week of 2/26
- Shoda-san at Mitaka.
- -
- Enzo at Mitaka Mon 2/26.
Remove LBB temporary ballast masses from BS chamber.
- Route cables up to under SF.
- Check/adjust total mass and balance of BF/... section, especially IM OSEMs.
- Cable and calibrate SF LVDT.
- Add Cu segments to SF cap.
- Install cap.
- Lift SF/... section and check total mass and balance.
Plan for week of 3/5
- Shoda-san at Mitaka.
- Hirata-san vacation Mon 3/5, then Kamioka
- Others at Kamioka.
- -
- Get SRM tank mushroom section installed (Hirata-san, Kimura-san)
- SR3 rack setup.
- Other tasks TBD.
Plan for week of 3/12
- Shoda-san at Mitaka.
- Mark at ASJ (Chiba) Fri 3/16.
- Hirata-san vacation Mon 3/5, then Kamioka
Plan for week of 3/19
- Mark at LVC meeting
- Shoda-san, Fabian at Mitaka
Plan for week of 3/26
- Mark vacation.
- Others ???
To-Do Lists, Schedule
Vacation Info
- Enzo Mitaka day 2/26
- Hirata-san vacation 3/5
- Hirata-san vacation Mon 3/5
- Fabian 3/26-4/27 vacation (then gone).