Line 6: Line 6:
==== Report for week of 2/19 ====
 * We did TFs from the IM OSEMs.
 * We secured the cables inside the BF, added the cap and anchored the cables from below the BF to the cap.
 * We lifted the BF/... section with the load gauge adapter and measured the weight, which was about as expected.
 * Based on the measured weight, Fabian prepared an 800 g set of masses for the top of the BF.
 * We added the AF crossbars and the section of the SS below the SF and craned in the SF.
 * We installed the SF-BF rod and flying saucer and suspended the BF/... section. With the 800 g placed temporarily on the BF, the SF keystone floated at about mid-range.
==== Report for week of 7/2 ====
 * We double-checked the bounce frequency and it was indeed around 0.5 Hz with the CuBe auxiliary spring installed.
 * We prepared (but did not yet install) 6 arc weights for tuning the IP.
 * We unlocked the security structure from the assembly frame, and raised the whole system on the top jacks. We then unlocked the IP and adjusted the leveling so the IP was centered. We then had to loosen two of the poles at the top level of the security structure to make it vertical again, because it turns out that the jack receptacles (which also serve as the IP leg bases) are welded at very uneven depths in the bottom surface of the PI, so the IP and the bottom surface can't be level at once.
 * We debugged an issue with the height of the payload. It turns out that due to a buildup of errors (especially an extra 3 mm between the SF and BF), the payload is some 5-6 mm low with the F0 keystone at CAD height. Since the frequency is roughly independent of height around 0.5 Hz, we decided to go with a higher F0 keystone.
 * Enzo and Eleonora routed all the SF/... cables up to the PI.
 * We found we needed 4.7 kg of extra mass to get the desired keystone height, so we decided to put the third Cu segment (3.3 kg) back on, purely as ballast.
 * We put some extra small masses on the SF cap to level it. The suspension is now fully ballasted and trimmed except for 1 Promec mass (455 g) standing in for the new PI yaw stepper motor assembly (estimated 330 g) which is yet to arrive.
 * We took all the SR sat amps back to Mozumi to get new capacitors installed, and grabbed three spares for use while that is being done.
 * We investigated and documented Tanaka-san's watchdog for the BS, to see if the BIO Converter chassis that it uses could also drive reset lines for stepper motor driver boxes.
 * Hirata-san and Terrence characterized the last 4 F0 blades.
 * Hirata-san and Terrence installed blades in the top filter for SR2 and tuned it to 0.5 Hz (with the CuBe auxiliary spring) over three rounds of compression.
Line 14: Line 19:
==== Plan for week of 2/26 ====
 * Shoda-san at Mitaka.
 * -
 * Enzo at Mitaka Mon 2/26.
 * '''Remove LBB temporary ballast masses from BS chamber.'''
 * Route cables up to under SF.
 * Check/adjust total mass and balance of BF/... section, especially IM OSEMs.
 * Cable and calibrate SF LVDT.
 * Add Cu segments to SF cap.
 * Install cap.
 * Lift SF/... section and check total mass and balance.
Line 26: Line 20:
==== Plan for week of 3/5 ====
 * Shoda-san at Mitaka.
 * Hirata-san vacation Mon 3/5, then Kamioka
 * Others at Kamioka.
 * -
 * Get SRM tank mushroom section installed (Hirata-san, Kimura-san)
 * SR3 rack setup.
 * Other tasks TBD.
==== Plan for week of 7/9 ====
 * Mark, Enzo, Hirata-san, Kozu-kun, Terrence at Kamioka Mon-Fri.
===== Main Sequence =====
 * Check/restore alignment of payload, especially optic pitch.
 * Install and cable geophones.
 * Install arc weights.
 * Tune IP.
 * Install, cable PI yaw stepper.
 * Make three in-air stepper splitter cables for SR2, SR3 and SRM.
 * Calibrate PI LVDTs and FRs.
 * Cabling, testing, TFs.
Line 35: Line 32:
==== Plan for week of 3/12 ====
 * Shoda-san at Mitaka.
 * Mark at ASJ (Chiba) Fri 3/16.
 * Hirata-san vacation Mon 3/5, then Kamioka
===== F0/LBB Stuff =====
 * Finalize PI #1 for SR2; crane into SR2 cleanbooth.
 * Remove SR3 tank lid, crane LBB rings to top of lower half of the tank, clamp in position.
 * Set tank jacks to nominal height.
 * Clear space for PI #2 (SRM) work.
Line 40: Line 38:
==== Plan for week of 3/19 ====
 * Mark at LVC meeting
 * Shoda-san, Fabian at Mitaka

==== Plan for week of 3/26 ====
 * Mark vacation.
 * Others ???
==== Plan for week of 7/16 ====
 * Monday 7/16 is Sea Day.
 * Mark, Enzo, Hirata-san, Kozu-kun, Terrence at Kamioka Tue-Fri.
===== Main Sequence =====
 * Lock suspension.
 * Crane into tank.
 * Unlock suspension.
 * Rearrange cables.
 * Test.
===== F0/LBB Stuff =====
 * Install correct IP in PI #2.
 * Crane PI #2 to second floor.
 * Rebuild top filter of PI #2.
Line 49: Line 53:
 * [[KAGRA/Subgroups/VIS/TypeB/March2018]]
 * [[KAGRA/Subgroups/VIS/TypeB/April2018]]
Line 53: Line 55:
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]]  * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]]
Line 56: Line 58:
 * Enzo Mitaka day 2/26
 * Hirata-san vacation 3/5
 * Hirata-san vacation Mon 3/5
 * Fabian 3/26-4/27 vacation (then gone).
 * Terrence: 8/24-26 f2f, then returns to Hong Kong.
 * Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 7/2

  • We double-checked the bounce frequency and it was indeed around 0.5 Hz with the CuBe auxiliary spring installed.

  • We prepared (but did not yet install) 6 arc weights for tuning the IP.
  • We unlocked the security structure from the assembly frame, and raised the whole system on the top jacks. We then unlocked the IP and adjusted the leveling so the IP was centered. We then had to loosen two of the poles at the top level of the security structure to make it vertical again, because it turns out that the jack receptacles (which also serve as the IP leg bases) are welded at very uneven depths in the bottom surface of the PI, so the IP and the bottom surface can't be level at once.
  • We debugged an issue with the height of the payload. It turns out that due to a buildup of errors (especially an extra 3 mm between the SF and BF), the payload is some 5-6 mm low with the F0 keystone at CAD height. Since the frequency is roughly independent of height around 0.5 Hz, we decided to go with a higher F0 keystone.
  • Enzo and Eleonora routed all the SF/... cables up to the PI.
  • We found we needed 4.7 kg of extra mass to get the desired keystone height, so we decided to put the third Cu segment (3.3 kg) back on, purely as ballast.
  • We put some extra small masses on the SF cap to level it. The suspension is now fully ballasted and trimmed except for 1 Promec mass (455 g) standing in for the new PI yaw stepper motor assembly (estimated 330 g) which is yet to arrive.
  • We took all the SR sat amps back to Mozumi to get new capacitors installed, and grabbed three spares for use while that is being done.
  • We investigated and documented Tanaka-san's watchdog for the BS, to see if the BIO Converter chassis that it uses could also drive reset lines for stepper motor driver boxes.
  • Hirata-san and Terrence characterized the last 4 F0 blades.
  • Hirata-san and Terrence installed blades in the top filter for SR2 and tuned it to 0.5 Hz (with the CuBe auxiliary spring) over three rounds of compression.

Plan for week of 7/9

  • Mark, Enzo, Hirata-san, Kozu-kun, Terrence at Kamioka Mon-Fri.

Main Sequence
  • Check/restore alignment of payload, especially optic pitch.
  • Install and cable geophones.
  • Install arc weights.
  • Tune IP.
  • Install, cable PI yaw stepper.
  • Make three in-air stepper splitter cables for SR2, SR3 and SRM.
  • Calibrate PI LVDTs and FRs.
  • Cabling, testing, TFs.

F0/LBB Stuff
  • Finalize PI #1 for SR2; crane into SR2 cleanbooth.
  • Remove SR3 tank lid, crane LBB rings to top of lower half of the tank, clamp in position.
  • Set tank jacks to nominal height.
  • Clear space for PI #2 (SRM) work.

Plan for week of 7/16

  • Monday 7/16 is Sea Day.
  • Mark, Enzo, Hirata-san, Kozu-kun, Terrence at Kamioka Tue-Fri.

Main Sequence
  • Lock suspension.
  • Crane into tank.
  • Unlock suspension.
  • Rearrange cables.
  • Test.

F0/LBB Stuff
  • Install correct IP in PI #2.
  • Crane PI #2 to second floor.
  • Rebuild top filter of PI #2.

To-Do Lists, Schedule

Vacation Info

  • Terrence: 8/24-26 f2f, then returns to Hong Kong.
  • Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.