Line 6: Line 6:
==== Report for week of 2/19 ====
 * We did TFs from the IM OSEMs.
 * We secured the cables inside the BF, added the cap and anchored the cables from below the BF to the cap.
 * We lifted the BF/... section with the load gauge adapter and measured the weight, which was about as expected.
 * Based on the measured weight, Fabian prepared an 800 g set of masses for the top of the BF.
 * We added the AF crossbars and the section of the SS below the SF and craned in the SF.
 * We installed the SF-BF rod and flying saucer and suspended the BF/... section. With the 800 g placed temporarily on the BF, the SF keystone floated at about mid-range.
==== Report for week of 7/17 ====
 * We checked the polarity of the IP LVDTs and flipped coil connections to get the standard arrangement.
 * We debugged an issue where one of the LVDT actuators had half the magnets in backwards resulting in no force.
 * We calibrated all the PI LVDTs.
 * We set the SF damper ring gap.
 * We prepped the suspension for craning, moved it into the tank and hooked the LBB damper ring rods.
 * Type A merged the SRM F0 with the correct IP, and we moved it out of the way (to the second floor behind the SRM tank).
 * We installed more cable clamps on the SR2 PI.
Line 14: Line 15:
==== Plan for week of 2/26 ====
 * Shoda-san at Mitaka.
 * -
 * Enzo at Mitaka Mon 2/26.
 * '''Remove LBB temporary ballast masses from BS chamber.'''
 * Route cables up to under SF.
 * Check/adjust total mass and balance of BF/... section, especially IM OSEMs.
 * Cable and calibrate SF LVDT.
 * Add Cu segments to SF cap.
 * Install cap.
 * Lift SF/... section and check total mass and balance.
==== Plan for week of 7/23 ====
 * Mark, Enzo, Fabian, Kozu-kun, Terrence, Panwei at Kamioka Mon-Fri.
 * Hirata-san at Kamioka Mon-Thu.
 * Mirapro moves assembly frame ≈7/25 (Wed).
Line 26: Line 20:
==== Plan for week of 3/5 ====
 * Shoda-san at Mitaka.
 * Hirata-san vacation Mon 3/5, then Kamioka
 * Others at Kamioka.
 * -
 * Get SRM tank mushroom section installed (Hirata-san, Kimura-san)
 * SR3 rack setup.
 * Other tasks TBD.

==== Plan for week of 3/12 ====
 * Shoda-san at Mitaka.
 * Mark at ASJ (Chiba) Fri 3/16.
 * Hirata-san vacation Mon 3/5, then Kamioka

==== Plan for week of 3/19 ====
 * Mark at LVC meeting
 * Shoda-san, Fabian at Mitaka

==== Plan for week of 3/26 ====
 * Mark vacation.
 * Others ???
===== SR3 =====
 * Unlock suspension.
 * Rearrange cables.
 * Test.
===== SR2 =====
 * Finish PI prep.
 * Crane into AF, suspend.
 * Start cable routing.
===== SRM =====
 * Prepare to assemble SRM metal mass (most parts due Wed 7/25).
 * Help Mirapro with AF move.
 * Start rebuild of top filter of PI #2.
Line 49: Line 34:
 * [[KAGRA/Subgroups/VIS/TypeB/March2018]]
 * [[KAGRA/Subgroups/VIS/TypeB/April2018]]
Line 53: Line 36:
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]]  * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]]
Line 56: Line 39:
 * Enzo Mitaka day 2/26
 * Hirata-san vacation 3/5
 * Hirata-san vacation Mon 3/5
 * Fabian 3/26-4/27 vacation (then gone).
 * Hirata-san at Mitaka 7/27.
 * Terrence: 8/24-26 f2f, then returns to Hong Kong.
 * Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 7/17

  • We checked the polarity of the IP LVDTs and flipped coil connections to get the standard arrangement.
  • We debugged an issue where one of the LVDT actuators had half the magnets in backwards resulting in no force.
  • We calibrated all the PI LVDTs.
  • We set the SF damper ring gap.
  • We prepped the suspension for craning, moved it into the tank and hooked the LBB damper ring rods.
  • Type A merged the SRM F0 with the correct IP, and we moved it out of the way (to the second floor behind the SRM tank).
  • We installed more cable clamps on the SR2 PI.

Plan for week of 7/23

  • Mark, Enzo, Fabian, Kozu-kun, Terrence, Panwei at Kamioka Mon-Fri.
  • Hirata-san at Kamioka Mon-Thu.
  • Mirapro moves assembly frame ≈7/25 (Wed).

SR3
  • Unlock suspension.
  • Rearrange cables.
  • Test.

SR2
  • Finish PI prep.
  • Crane into AF, suspend.
  • Start cable routing.

SRM
  • Prepare to assemble SRM metal mass (most parts due Wed 7/25).
  • Help Mirapro with AF move.
  • Start rebuild of top filter of PI #2.

To-Do Lists, Schedule

Vacation Info

  • Hirata-san at Mitaka 7/27.
  • Terrence: 8/24-26 f2f, then returns to Hong Kong.
  • Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.