Differences between revisions 240 and 306 (spanning 66 versions)
Revision 240 as of 2018-02-23 14:17:48
Size: 2221
Editor: MarkBarton
Comment:
Revision 306 as of 2018-08-03 15:24:21
Size: 1275
Editor: MarkBarton
Comment:
Deletions are marked like this. Additions are marked like this.
Line 6: Line 6:
==== Report for week of 2/19 ====
 * We did TFs from the IM OSEMs.
 * We secured the cables inside the BF, added the cap and anchored the cables from below the BF to the cap.
 * We lifted the BF/... section with the load gauge adapter and measured the weight, which was about as expected.
 * Based on the measured weight, Fabian prepared an 800 g set of masses for the top of the BF.
 * We added the AF crossbars and the section of the SS below the SF and craned in the SF.
 * We installed the SF-BF rod and flying saucer and suspended the BF/... section. With the 800 g placed temporarily on the BF, the SF keystone floated at about mid-range.
==== Report for week of 7/30 ====
 *
==== Plan for week of 8/6 ====
 * Mark, Enzo, Hirata-san, Fabian, Kozu-kun, Terrence, Panwei at Kamioka Mon-Fri.
 * Kozu-kun works at Mozumi Mon, Fri, and Thu afternoon.
Line 14: Line 12:
==== Plan for week of 2/26 ====
 * Shoda-san at Mitaka.
 * -
 * Enzo at Mitaka Mon 2/26.
 * '''Remove LBB temporary ballast masses from BS chamber.'''
 * Route cables up to under SF.
 * Check/adjust total mass and balance of BF/... section, especially IM OSEMs.
 * Cable and calibrate SF LVDT.
 * Add Cu segments to SF cap.
 * Install cap.
 * Lift SF/... section and check total mass and balance.
===== SR3 =====
 * Finalize optic pitch, OSEM alignment.
 * Do TFs with temporary OL.
 * Install final OL.
 * Hook LBB, add ballast mass, set up temporary OL (horizontal beam, pitch/yaw only).
Line 26: Line 18:
==== Plan for week of 3/5 ====
 * Shoda-san at Mitaka.
 * Hirata-san vacation Mon 3/5, then Kamioka
 * Others at Kamioka.
 * -
 * Get SRM tank mushroom section installed (Hirata-san, Kimura-san)
 * SR3 rack setup.
 * Other tasks TBD.

==== Plan for week of 3/12 ====
 * Shoda-san at Mitaka.
 * Mark at ASJ (Chiba) Fri 3/16.
 * Hirata-san vacation Mon 3/5, then Kamioka

==== Plan for week of 3/19 ====
 * Mark at LVC meeting
 * Shoda-san, Fabian at Mitaka

==== Plan for week of 3/26 ====
 * Mark vacation.
 * Others ???
===== SR2 =====
 * Add estimated final ballast mass.
 * Do PI cable routing.
 * Adjust ballast/trim mass, with reserve for cables.
 
===== SRM =====
 * Assemble metal mass.
 * Glue prisms, flags.
 * Reconfigure, align assembly frame.
 * Tune F0 for SRM.
 * Add LBB blade units, cable clamps etc.
 * Check PI coil connections, IP LVDT magnets.
Line 49: Line 32:
 * [[KAGRA/Subgroups/VIS/TypeB/March2018]]
 * [[KAGRA/Subgroups/VIS/TypeB/April2018]]
Line 53: Line 34:
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]]  * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]]
Line 56: Line 37:
 * Enzo Mitaka day 2/26
 * Hirata-san vacation 3/5
 * Hirata-san vacation Mon 3/5
 * Fabian 3/26-4/27 vacation (then gone).
 * Terrence: 8/24-26 f2f, then returns to Hong Kong.
 * Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.

Scraps of text for incorporation in the VIS Meeting Minutes

KAGRA/Subgroups/VIS/MeetingNAOJ

Type B (Mark)

Report for week of 7/30

Plan for week of 8/6

  • Mark, Enzo, Hirata-san, Fabian, Kozu-kun, Terrence, Panwei at Kamioka Mon-Fri.
  • Kozu-kun works at Mozumi Mon, Fri, and Thu afternoon.

SR3
  • Finalize optic pitch, OSEM alignment.
  • Do TFs with temporary OL.
  • Install final OL.
  • Hook LBB, add ballast mass, set up temporary OL (horizontal beam, pitch/yaw only).

SR2
  • Add estimated final ballast mass.
  • Do PI cable routing.
  • Adjust ballast/trim mass, with reserve for cables.

SRM
  • Assemble metal mass.
  • Glue prisms, flags.
  • Reconfigure, align assembly frame.
  • Tune F0 for SRM.
  • Add LBB blade units, cable clamps etc.
  • Check PI coil connections, IP LVDT magnets.

To-Do Lists, Schedule

Vacation Info

  • Terrence: 8/24-26 f2f, then returns to Hong Kong.
  • Enzo: 9/14 JPS, 9/15 through 10/8 vacation in Chile.

KAGRA/Subgroups/VIS/TypeB/Minutes (last edited 2022-10-28 10:02:46 by fabian.arellano)