==== Report for week of 2/26 ==== * We routed all the cables from the BF level up via the flying saucer to the SF. * Hirata-san tried filing the SF cap to improve the fit, but without much success. * Hirata-san installed the Cu segments and cable clamps on the SF cap and the SF LVDT and FR cables. * We cabled and tested the BF cap picos and the SF LVDT and FR. (The LVDT still needs a full calibration.) * We worked on recovering the IM OSEM alignment. |
==== Report for week of 6/11 ==== * Enzo redid the SR3 BIO connections to match the now-working BS setup. He also fixed PR2, which had a similar problem. * Enzo replaced LPCDs with HPCDs in the SR3. * Hirata-san installed the cable clamps and Cu segments on the SF cap. * Hirata-san and Kozu-kun continued tuning the filter in PI #3. Unfortunately it seems to be rather weaker than expected, and we have not found a compression setting that gives a good frequency. We may have to use tricks like reducing the number of Cu segments on the SF (or using Al ones) to save weight. * Mark, Enzo and Terrence suspended the BF/... section from the SF, and got it aligned for TFs. |
Line 13: | Line 13: |
==== Plan for week of 2/26 ==== * Shoda-san at Mitaka. * - * Enzo at Mitaka Mon 2/26. * '''Remove LBB temporary ballast masses from BS chamber.''' * Route cables up to under SF. * Check/adjust total mass and balance of BF/... section, especially IM OSEMs. * Cable and calibrate SF LVDT. * Add Cu segments to SF cap. * Install cap. * Lift SF/... section and check total mass and balance. |
==== Plan for week of 6/18 ==== * Mark Enzo, Hirata-san, Kozu-kun, Terrence at Kamioka Mon-Fri. * -- * Receive second and third sets of LBB damper rings. * Take TFs. * Cable, test SF LVDT and FR. * Add calculated ballast to SF. * Finish tuning F0 #3 for SR3. * Park F0 #1 (for SR2) in top of SR3 assembly frame. * Move F0 #3 behind SR3. * Move F0 #1 to "factory" area (in front of SRM) and start rebuild. * Install PI. * Suspend SF/... section. * Lots of cabling. |
Line 25: | Line 28: |
==== Plan for week of 3/5 ==== * Shoda-san at Mitaka. * Hirata-san vacation Mon 3/5, then Kamioka * Others at Kamioka. * - * Finish recovering IM OSEM alignment. * Calibrate SF LVDT. * Weigh SF/... section. * Get SRM tank mushroom section installed (Hirata-san, Kimura-san) * Set up for rebuilding of two BFs. ==== Plan for week of 3/12 ==== * Shoda-san at Mitaka. * Mark at ASJ (Chiba) Fri, then Mitaka. * Hirata-san vacation Mon 3/5; Kamioka Tue-Thu; Mitaka Fri * Others Kamioka Mon-Thu * Install boxes in SR3 and SRM racks. * Lay SR3 in-air cabling. * Continue rebuild of BFs. ==== Plan for week of 3/19 ==== * Mark at LVC meeting * All others at Mitaka * Make two sets of IM OSEMs * Make last in-air pico adapter cable * Make three in-air stepper splitter cables for SR2, SR3 and SRM. * Set up Dummy BS prism removal. ==== Plan for week of 3/26 ==== * Mark vacation. * Shoda-san at Mitaka * Others at Kamioka * -- * F0 Prototype Blade Test * Characterize blades. * Choose best set of three. * Remove cracked blades from filter in SRM area. * Set up test weights in SRM area, first floor. * Remove floor panel in SRM area, second floor. * Install chosen blades. * Measure load capacity. |
==== Plan for week of 6/25 ==== * Mark Enzo, Hirata-san, Kozu-kun, Terrence at Kamioka Mon-Fri. |
Line 68: | Line 32: |
* [[KAGRA/Subgroups/VIS/TypeB/March2018]] * [[KAGRA/Subgroups/VIS/TypeB/April2018]] |
|
Line 72: | Line 34: |
* [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]] | * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779 Type B Schedule (SR)]] |
Line 75: | Line 37: |
* Mark at LVC, then vacation, 3/18 (Sun) - 4/1 (Sun) * Hirata-san vacation, Mon 3/5. * Fabian vacation, 3/26-4/27 (then gone). |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Report for week of 6/11
- Enzo redid the SR3 BIO connections to match the now-working BS setup. He also fixed PR2, which had a similar problem.
- Enzo replaced LPCDs with HPCDs in the SR3.
- Hirata-san installed the cable clamps and Cu segments on the SF cap.
- Hirata-san and Kozu-kun continued tuning the filter in PI #3. Unfortunately it seems to be rather weaker than expected, and we have not found a compression setting that gives a good frequency. We may have to use tricks like reducing the number of Cu segments on the SF (or using Al ones) to save weight.
- Mark, Enzo and Terrence suspended the BF/... section from the SF, and got it aligned for TFs.
Plan for week of 6/18
- Mark Enzo, Hirata-san, Kozu-kun, Terrence at Kamioka Mon-Fri.
- --
- Receive second and third sets of LBB damper rings.
- Take TFs.
- Cable, test SF LVDT and FR.
- Add calculated ballast to SF.
- Finish tuning F0 #3 for SR3.
- Park F0 #1 (for SR2) in top of SR3 assembly frame.
- Move F0 #3 behind SR3.
- Move F0 #1 to "factory" area (in front of SRM) and start rebuild.
- Install PI.
- Suspend SF/... section.
- Lots of cabling.
Plan for week of 6/25
- Mark Enzo, Hirata-san, Kozu-kun, Terrence at Kamioka Mon-Fri.